Baixe o app para aproveitar ainda mais
Prévia do material em texto
1 MINE3123 - Mine Planning Project Management & Network Techniques Week 13 ContentContentContentContent � Project Management & Network Techniques � Critical Path Method (CPM) � Mine Closure Planning � Final Exam Review 2 MINE3123 - Mine Planning Project Management & Network Techniques BackgroundBackgroundBackgroundBackground Once feasibility studies have been completed, an optimal mine plan has been generated that meets corporate objectives and finance has been established - project construction may commence. Project Management is all about the best way in which to complete a task (such as the construction of a mine) within the shortest time frame at the lowest possible cost. 3 Mathematical AnalysisMathematical AnalysisMathematical AnalysisMathematical Analysis Mathematical Analysis – may be used to model and then evaluate the schedule of a series of activities required to complete a task. This may be useful in an answering questions as such, what cost and resources are required to reduce the time required to complete a task. The most well-regarded mathematical/network analysis techniques are: � Critical Path Method (CPM) – Calculates a single early and late start and a completion date for each activity based on a specified single duration estimate. CPM calculates a “Float Time” to determine which activities have the least scheduling flexibility. � Program Evaluation and Review Technique (PERT) – Average activity duration estimate to calculate a project duration. Critical Path Method (CPM)Critical Path Method (CPM)Critical Path Method (CPM)Critical Path Method (CPM) Two types of project networks: �Activity-on-Arc (AOA) � In this diagram, the activity is represented on an arc, or an arrow, while a node is used to separate an activity from its immediate predecessors. �Activity-on-Node (AON) � In this diagram, the activity is represented by the node, while the arc or arrow is used to show the precedence relationship between the activities. 4 CPMCPMCPMCPM TerminologyTerminologyTerminologyTerminology Start Node – This is a node that represents the beginning of the project. Finish Node – This node represents the end of the project. Immediate Predecessor - These are activities that must be completed by no later than the start time of the given activity. Immediate Successor - Given the immediate predecessor of an activity, this activity becomes the immediate successor of each of these immediate predecessors. If an immediate successor has multiple immediate predecessors, then all must be finished before an activity can begin. CPMCPMCPMCPM TerminologyTerminologyTerminologyTerminology Earliest start time of an activity (ES) - The earliest possible time at which an activity will begin if there are no delays in a project. Earliest finish time of an activity (EF) - The earliest possible time at which an activity will finish if there are no delays in a project. Latest start time of an activity (LS) - The latest possible time that an activity can start without delaying the project. Latest finish time of an activity (LF) - The latest possible time that an activity can be completed without delaying the project. 5 CPMCPMCPMCPM TerminologyTerminologyTerminologyTerminology Forward pass - The process of moving through a project from start to finish to determine the earliest start and finish times for the activities in the project. Backward pass - The process of moving through a project from finish to start to determine the latest start and finish times for the activities in the project. Slack for an activity - The amount of time that a particular activity can be delayed without delaying the whole project. It is calculated by taking the difference between the latest finish time with the earliest finish time. Dummy activity - to indicate interdependencies that cannot be represented correctly solely with the conventional activity and event structure and are useful when doing hand solutions of the network for creating parallel activities or merging several parallel activities. Finding the Critical PathFinding the Critical PathFinding the Critical PathFinding the Critical Path � Once the earliest and latest times have been determined for each node or event in the network, the critical path is then defined as those tasks for which the earliest times are equal to the latest times. � The critical path or paths (there may be more than one critical path within a network) represents the series of tasks or activities in which no delay in their start or finish can be tolerated without delaying the project as a whole. � Other nodes that are not considered critical have what is termed float or slack time. This float time is the difference between latest and earliest times and represents flexibility of task initiation by a project manager. � A project manager can use float or slack time to delay initiation of various project tasks in order to better schedule manpower, equipment, or other company resources without delaying project completion. 6 InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise The development of an energy project involves the following activities: Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na a) Draw the Network Diagram for this project, indicating the duration of each activity. b) Using the CPM method, determine the critical path for this project and the completion time. c) Crash the project in the cheapest possible way so as to have a completion time which is 4 months shorter than the current completion time. InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise a) Draw the Network Diagram for this project, indicating the duration of each activity. 2 A=5 1 Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na 7 InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise a) Draw the Network Diagram for this project, indicating the duration of each activity. 2 A=5 B=4 3 1 Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise a) Draw the Network Diagram for this project, indicating the duration of each activity. 2 C=3A=5 B=4 3 41 Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200(j) (g,h) 4 $3,600 0 na 8 InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise a) Draw the Network Diagram for this project, indicating the duration of each activity. 5 2 C=3A=5 B=4 3 41 D=4 Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise a) Draw the Network Diagram for this project, indicating the duration of each activity. 5 6 2 C=3A=5 B=4 E=6 3 41 D=4 Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na 9 InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise a) Draw the Network Diagram for this project, indicating the duration of each activity. 7 5 6 2 C=3A=5 F=4 B=4 E=6 3 41 D=4 Dummy arc Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise a) Draw the Network Diagram for this project, indicating the duration of each activity. 7 5 6 2 C=3A=5 F=4 B=4 E=6 3 41 D=4 Dummy arc Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na 8G=5 10 InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise a) Draw the Network Diagram for this project, indicating the duration of each activity. 7 5 6 2 C=3A=5 F=4 B=4 E=6 3 41 D=4 Dummy arc Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na 8G=5 9H=6 InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise a) Draw the Network Diagram for this project, indicating the duration of each activity. 7 5 6 2 C=3A=5 F=4 B=4 E=6 3 41 D=4 Dummy arc Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na 8G=5 9H=6 10 I=6 11 InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise a) Draw the Network Diagram for this project, indicating the duration of each activity. 7 5 6 2 C=3A=5 F=4 B=4 E=6 3 41 D=4 Dummy arc Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na 8G=5 9H=6 10 I=6 J=4 Dummy arc InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise b) Using the CPM method, determine the critical path for this project and the completion time. 7 5 6 2 10 C=3A=5 F=4 I=6 B=4 E=6 Notation: LFLS EFES / / ES = Earliest Start EF = Earliest Finish LS = Latest Start LF = Latest Finish 11/7 4/0 21/15 18/125/0 5/0 21/17 21/17 3 8 4 9 1 17/12 14/9 15/11 12/8 17/11 17/11 11/5 11/5 12/8 9/5 H=6 G=5 J=4 11/8 8/5 D=4 Dummy arc Dummy arc Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na 12 InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise b) Using the CPM method, determine the critical path for this project and the completion time. 7 5 6 2 10 C=3A=5 F=4 I=6 B=4 E=6 Notation: LFLS EFES / / ES = Earliest Start EF = Earliest Finish LS = Latest Start LF = Latest Finish 11/7 4/0 21/15 18/125/0 5/0 21/17 21/17 3 8 4 9 1 17/12 14/9 15/11 12/8 17/11 17/11 11/5 11/5 12/8 9/5 H=6 G=5 J=4 11/8 8/5 D=4 Dummy arc Dummy arc Therefore the critical path is � → � → � → �. This requires 21 months completion time. Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise c) Crash the project in the cheapest possible way so as to have a completion time which is 4 months shorter than the current completion time. 7 5 6 2 10 C=3A=5 F=4 I=6 B=4 E=6 Notation: LFLS EFES / / ES = Earliest Start EF = Earliest Finish LS = Latest Start LF = Latest Finish 11/7 4/0 21/15 18/125/0 5/0 21/17 21/17 3 8 4 9 1 17/12 14/9 15/11 12/8 17/11 17/11 11/5 11/5 12/8 9/5 H=6 G=5 J=4 11/8 8/5 D=4 Dummy arc Dummy arc Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200(j) (g,h) 4 $3,600 0 na 13 InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise The activities that can be crashed are A, H and I. Of this A and H belong to the critical path. � The crashing cost of A is $300 per month for up to 2 months. � The crashing cost of H is $200 per month for up to 4 months. c) Crash the project in the cheapest possible way so as to have a completion time which is 4 months shorter than the current completion time. 7 5 6 2 10 C=3A=5 F=4 I=6 B=4 E=6 Notation: LFLS EFES / / ES = Earliest Start EF = Earliest Finish LS = Latest Start LF = Latest Finish 11/7 4/0 21/15 18/125/0 5/0 21/17 21/17 3 8 4 9 1 17/12 14/9 15/11 12/8 17/11 17/11 11/5 11/5 12/8 9/5 H=6 G=5 J=4 11/8 8/5 D=4 Dummy arc Dummy arc Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise c) Crash the project in the cheapest possible way so as to have a completion time which is 4 months shorter than the current completion time. 7 5 6 2 10 C=3A=5 F=4 I=6 B=4 E=6 Notation: LFLS EFES / / ES = Earliest Start EF = Earliest Finish LS = Latest Start LF = Latest Finish 11/7 4/0 21/15 18/125/0 5/0 21/17 21/17 3 8 4 9 1 17/12 14/9 15/11 12/8 17/11 17/11 11/5 11/5 12/8 9/5 H=6 G=5 J=4 11/8 8/5 D=4 Dummy arc Dummy arc Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na Since activity H is the cheapest, we should try crashing this first. Unfortunately it can only be crashed by 3 months because otherwise the critical path changes from: � → � → � → � to � → � → � → �. 14 InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise c) Crash the project in the cheapest possible way so as to have a completion time which is 4 months shorter than the current completion time. 7 5 6 2 10 C=3A=5 F=4 I=6 B=4 E=6 Notation: LFLS EFES / / ES = Earliest Start EF = Earliest Finish LS = Latest Start LF = Latest Finish 11/7 4/0 21/15 18/125/0 5/0 21/17 21/17 3 8 4 9 1 17/12 14/9 15/11 12/8 17/11 17/11 11/5 11/5 12/8 9/5 H=6 G=5 J=4 11/8 8/5 D=4 Dummy arc Dummy arc Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na Since D or G can’t be crashed the remaining month must be crashed from activity A. The cheapest way to reduce the project’s completion time by 4 months costs 3 $200 � 1 $300 � $900. InInInIn----class Exerciseclass Exerciseclass Exerciseclass Exercise c) Crash the project in the cheapest possible way so as to have a completion time which is 4 months shorter than the current completion time. 7 5 6 2 10 C=3A=4 F=4 I=6 B=4 E=6 Notation: LFLS EFES / / ES = Earliest Start EF = Earliest Finish LS = Latest Start LF = Latest Finish 3 8 4 9 1 H=3 G=5 J=4 D=4 Dummy arc Dummy arc Notice that there are now 3 critical paths: � → � → � → � � → � → � → � � → � → � → � 17/13 17/13 13/10 13/10 13/8 13/8 17/11 17/11 11/7 11/7 7/4 7/4 8/4 8/4 10/4 10/4 4/0 4/0 7/3 4/0 Activity Predecessor Normal Duration (months) Cost Normal Duration ($/month) Crash Duration (months) Cost Crash / Duration ($/month) (a) - 5 $2,900 2 $300 (b) - 4 $3,400 0 na (c) (a) 3 $3,700 0 na (d) (a) 4 $4,500 0 na (e) (a) 6 $3,300 0 na (f) (b,c) 4 $3,100 0 na (g) (d) 5 $5,800 0 na (h) (e) 6 $3,700 4 $200 (i) (f) 6 $2,200 3 $1,200 (j) (g,h) 4 $3,600 0 na 15 MINE3123 - Mine Planning Mine Closure Planning BackgroundBackgroundBackgroundBackground Environmental legislation typically requires mining companies to return mine sites to a state whereby they fit in and complement their natural surrounds. This may require (but is not limited to): � Dismantling of infrastructure. � Appropriate disposal/burial of waste/reactive materials and products. � Reclamation and revegetation of disturbed land. � Re-introduction of native flora & fauna. 16 BackgroundBackgroundBackgroundBackground Mine closure also presents other costs to mining companies which may include (but is not limited to): � Redundancy payments to workforce. � Contract closure payments. � Community & native title settlement payments. Mine Closure ConsiderationsMine Closure ConsiderationsMine Closure ConsiderationsMine Closure Considerations � For most new operations, environmental legislation requires that mining companies make a bond payment before project approval to cover the costs of unfinished environmental rehabilitation in the event that the company files for bankruptcy. � A mining operation may also receive a salvage value for old plant and infrastructure (typically 5% – 10% of CAPEX). � Mine closure is an important part of the mine financial evaluation process. � It should be considered from the outset during the feasibility and strategic planning phase. 17 Mine Closure ConsiderationsMine Closure ConsiderationsMine Closure ConsiderationsMine Closure Considerations From an NPV perspective, in many cases it is actually better for a company to extend mine life by continuing to mine and process low grade ore (even at a slight loss) if it means that it delays the cost associated with mine closure. InInInIn----classclassclassclass Case StudyCase StudyCase StudyCase Study A small mining operation nearing the end of its life has 7 potential remaining copper satellite deposits as displayed in the Table below. The company is utilising its lowest possible mill throughput rate of 5Mtpa in order to achieve a maximum recovery of 95% Cu. The cost associated with mining and processing each tonne of ore is $17.80. A discount rate of 18% applies. The copper price is $5,000/t. Investigate the impact that present value mine closure costs of $30M, $50M and $70M (in the year immediately after ceasing operations) have on the NPV of the project and if altering the closure costs in any way changes the optimal production schedule for this operation. Tonnes (Mt) Grade (% Cu) Deposit L 5.0 0.50 Deposit M 5.0 0.44 Deposit N 5.0 0.41 Deposit O 5.0 0.37 Deposit P 5.0 0.35 Deposit Q 5.0 0.33 Deposit R 5.0 0.22 18 InInInIn----classclassclassclass Case StudyCase StudyCase StudyCase Study The present values for each deposit is firstly calculated to form the basis for production scheduling:Tonnes (Mt) Grade (% Cu) Present Value ($M) Deposit L 5.0 0.50 29.75 Deposit M 5.0 0.44 15.50 Deposit N 5.0 0.41 8.38 Deposit O 5.0 0.37 -1.13 Deposit P 5.0 0.35 -5.88 Deposit Q 5.0 0.33 -10.63 Deposit R 5.0 0.22 -36.75 Cu%3747.0 000,5$95.0 80.17$ = × As expected, the cut-off grade is somewhere between the grades for deposit N and O: Under normal circumstances any grade below 0.3747% Cu would thus not be considered as part of the mine planning and scheduling process. Breakeven Cut-off Grade = InInInIn----classclassclassclass Case StudyCase StudyCase StudyCase Study As shown below, the greater the closure cost the better it is to alter the mine plan to increase mine life, even if this is at a loss: Closure costs ($M) 30 50 70 Deposit L Deposit M Deposit N 25.97 15.65 5.34 Deposit O 27.75 19.00 10.26 Deposit P 27.18 19.77 12.36 Deposit Q 24.94 18.66 12.38 Deposit R 14.84 9.52 4.20 NPV’s associated with mining to each deposit at each closure cost Tonnes (Mt) Grade (% Cu) Present Value ($M) Deposit L 5.0 0.50 29.75 Deposit M 5.0 0.44 15.50 Deposit N 5.0 0.41 8.38 Deposit O 5.0 0.37 -1.13 Deposit P 5.0 0.35 -5.88 Deposit Q 5.0 0.33 -10.63 Deposit R 5.0 0.22 -36.75 19 MINE3123 - Mine Planning Final Exam Review Are YouAre YouAre YouAre You Prepared?Prepared?Prepared?Prepared? Do you: (i) have your current student ID card? (ii) know where your exam is? (iii) know what materials you are permitted to bring to the exam? – check with your course coordinator. (iv) have your calculator tagged by EAIT Faculty. For each exam, ensure you: (i) have rechecked the timetable for exam date, time and venue and checked your emails. (ii) have your student ID card on hand, and ready to present on entry to the exam room – should you forget it, you should report to the Student Centre before your exam. (iii) have spare pencils and pens. (iv) have any permitted materials. (v) arrive at your exam venue at least 15 minutes before the scheduled start of the exam. 20 MINE3123 Exam InformationMINE3123 Exam InformationMINE3123 Exam InformationMINE3123 Exam Information � Date & Time: Monday 17th November at 2:30pm. � Location: Michie Building (9): � Banister, Sam - Maher, Kim: Room 217. � Mastrogiannis, Yia - Zhou, Nin: Room 211. � Worth 40% of the MINE3123 course. � 2 Hours plus 10 minutes perusal time (no writing during perusal). � Provided with on 14 page answer booklet. � Calculators - Casio FX82 series or UQ approved (labelled), no other electronic aids permitted (eg. laptops, phones, etc.). � Closed book exam. No notes are permitted. � Formulas provided. � 5 Questions: � Each worth 25%. � Answer any 4 of the 5 questions. � Answer each question in the writing booklet unless stated otherwise. Question 1Question 1Question 1Question 1 (25%)(25%)(25%)(25%) �Open pit mine optimisation �Floating Cone / Lerchs Grossmann �Determine ultimate pit limit �Sequencing �Capacity constrained scheduling �Present value calculation of mine plan 21 Question 2Question 2Question 2Question 2 (25%)(25%)(25%)(25%) �Open pit phase/pushback analysis �Scheduling �Mine life / phase life / stripping ratios �Overall optimum mining strategy. �Phase-wise stripping schedules �Inventory/Saw-Graphs Question 3Question 3Question 3Question 3 (25%)(25%)(25%)(25%) �Linear/Mixed Integer Programming & Critical Path Method �LP/MIP modelling for a given problem �Define variables �Formulate objective function �Formulate constraint equations �Graphical representation �Sensitivity �Draw a network flow diagram for a given set of activities �Consider all precedence information carefully �Be familiar with what the critical path represents �Be familiar with float times �Be familiar with earliest & latest, start & finish times and all other definitions �Reducing completion time – crashing 22 Question 4Question 4Question 4Question 4 (25%)(25%)(25%)(25%) �Cut-off grade �Breakeven/Basic cut-off �Strategic life of mine cut-off grade policy �Lane’s 6 cut-off grades �Know the grade-tonnage curve and be prepared to be able to calculate/determine cut-off/average grades within each interval Question 5Question 5Question 5Question 5 (25%)(25%)(25%)(25%) �Financial Technical Modelling (FTM) �WACC �Debt to equity �Interest �Taxation �Carry forward tax loses �Debt repayments �Present value factors �Present values �Net Smelter Return �ROM Tonnes versus Washed Tonnes
Compartilhar