Baixe o app para aproveitar ainda mais
Prévia do material em texto
American Journal of Small Business, Vol. V, No. 2, Fall (Oct-Dec), 1980 Start-up Of Small Manufacturing Ventures In Developing Countries* KASRA FERDOWS, The European Institute of Business Administration (INSEAD) ABSTRACT Most entrepreneurs wishing to set up a small manufacturing venture in a developing country underestimate the amount of time and funds required for hringing the plant on-stream. Study of the establishment of forty small and medium size manufacturing plants in Iran from 1972 to 1975 showed that contrary to one's intuition, the degree of this under- estimation has no relation with the plant's technological or logistic complexities. Rather, a few other variables related to the management of the start-up project itself are the keys. Most important are certain attributes of the entrepreneur in charge of the project. INTRODUCTION Most entrepreneurs wishing to set up a small manufacturing venture in a developing country underestimate the amount of resources required for bringing the plant on-stream. Often the actual time, money and personal energy spent on such a project tum out to be signiflcantly more than expected. Why does this underestimation occur? Which factors influence its magnitude? How can one minimize the unfavorable effects of this underestimation? The objective in this article is to answer these questions. The author has been unable to flnd any study which addresses these issues. Only some of the studies which have examined the cost of technology transfer have some relevance to the subject here. Since starting a manufacturing venture in a developing country inevitably involves some technology transfer, some of the cost components of technology transfer are related to plant start-up. UNCTAD in a 1970 report [l,p.711] emphasizes the importance of identiflcation and measurement of the elements of the cost of technology transfer. The same report states that, "It is not clear whether the cost differentials in the transfer of technology for similar industries in various developing countries are related to the level of development of the country concerned and/or to the organizational form (direct investment, joint venture, or semi-puhlic or public enterprise) employed in the transfer process. [An] identiflcation of the costs and the factors which influence * This article has been referred by three editorial members. 12 American Journal of Small Business, Vol. V, No. 2, Fall (Oct-Dec), 1980 them [would] furnish a meaningful basis for the consideration of national and international policies to reduce them." Teece, in a 1976 study [2,p.75-97] identifies three primary factors: (a) the number of previous start-ups by the transferor, (b) the number of years of manufacturing experience in the transferee's organization, and (c) the age of technology. Teece's study, viewing the issue mainly from the viewpoint of multination- als, concludes that suppliers prefer to transfer tested technology to experienced recipients. Wallender [3] places the emphasis on the manage- rial resources of the recipient firm and concludes that the key in the successful transfer of technology lies in the stage of managerial develop- ment of the user's firm. The findings of these studies, however, are not necessarily applicable here because they address mostly large projects and large enterprises. To examine the start-up problems of small manufacturing ventures in developing countries, new empirical data had to be collected. Case histories of the establishment of 40 privately owned small and medium size' manufacturing plants in Iran provided the data for this investigation. The plants, selected randomly from a variety of industries, had started commercial production between 1972 and 1975. Data was gathered by site visits, interviews with the principal managers/entrep- reneurs, examination of companies' internal documents, analysis of project feasibility studies, and review of follow-up reports held by the banks which financed the projects. EXHIBIT 1 — START-UP TIME AND COST OVERRUNS Time Overrun Cost Overrun Nil* 13 23 Mod* 7 10 High* 20 7 Total 40 40 Significance level (t-test) for both time and cost overruns < 0.005. * Notes: 1. Classiflcation of overruns into these three categories is based on the discrepancy between planned (estimates in feasibility report or original start-up plan) and actual values as follows: Nil: "Actual" less than 110% of "planned." Moderate (Mod.): "Actual" between 110% and 140% of "planned." High: "Actual" more than 140% of "planned." 2. A plant is considered on-stream when the first batch for commercial sale is produced; going on-stream is the culmination of many start-up activities such as feasibility analysis, securing finances, land acquisition, site development, construction of building, acquisition and installation of machinery, hiring and training of workers and factory management personnel, securing suppliers of product parts and raw materials, pilot run production and debugging, and preparation for commercial production. 13 American Journal of Small Business, VoL V, No. 2, Fall (Oct-Dec), 1980 The data confirmed the existence of the underestimation bias. As shown in Exhibit 1, half of the forty manufacturing start-ups surveyed in this study incurred long delays; seven had moderate delays; only 13 finished on schedule. Similarly, seven projects had a high cost overrun and ten a moderate one. Only four of the remaining 23 projects spent less money than planned — none significantly less. The first task was to look into the "successful start-ups" (i.e., those plants which were brought on-stream without time or cost overrun). FACTORS INFLUENCING OVERRUNS Intuition said that the successful projects probably involved simple plants. By "simple" one might be referring to a certain set of plant characteristics such as its size, type of product, degree of vertical integration, percentage of machinery supplied locally, product's domestic value added, and number of direct production workers employed. For example, one might have expected to find the plants of the successful projects to be generally smaller than those of the less successful ones. Surprisingly, that was not the case. Close examination of the data showed that no specific conclusions regarding any of these factors could be drawn. The results for five of the more important plant characteristics — size of investment, location of plant site, percentage of domestic machin- ery, local product value added, and plant value added (a crude measure of the degree of vertical integration) — are presented in Exhibit 2. Statistical tests — or a cursory look — show no significant dependence. There are, of course, many other important plant characteristics to be analyzed, but the existing data strongly suggest that, contrary to its intuitive appeal, the degree of success in a manufacturing start-up cannot be predicted on the basis of the plant's technological or logistical characteristics."" For example, time and cost overruns expected in a small home appliance plant are not necessarily more, or less, than time and cost overruns expected in a small food processing plant. The difference between successful and unsuccessful manufacturing start-ups, therefore, lay in factors other than those related to the plant characteristics. Amongst such factors are those related to the management of the start-up project itself: for example, the role and the reputation of the major supplier of machinery, degree of subcontracting employed, availabil- ity of utilities on site, availability of funds during the start-up period, and perhaps some specific attributes of the entrepreneur involved. (List of these attributes later.) Here the successful start-ups did show some important patterns (Exhibit 3). But, again many factors which one expectedto affect start-up significantly did not seem to make much difference. For example, no particular role of the major supplier of plant 14 American Journal of Small Business, Vol. V, No. 2, Fall (Oct-Dec), 1980 EXHIBIT 2 — EFFECTS OF PLANT CHARACTERISTICS ON START-UP TIME AND COST OVERRUNS PLANT CHARACTERISTIC 1. Investment in Plant:' Less than $1 Mn. $1 Mn. to $2 Mn. More than $2 Mn. 2. Plant Site — Commuting Time from Capital City: Within one Hour Possible in one day Overnight stay necessary 3. Percent of Domestic Equipment (value): Less than 10% 10% to 20% More than 20% 4. Percent of Product's Domestic Value Added:^ Less than 40% 40% to 60% 60% to 80% More than 80% 5. Percent of Product's Value Added in Plant^: Less than 20% 20% to 40% More than 40% Time Overrun Nil Mod. Hi 4 5 4 6 4 3 6 5 2 1 3 5 4 IN CO 00 (N CO IN 3 1 3 3 3 1 IN O IN CO 1 5 1 5 5 10 7 4 9 9 6 5 3 4 7 6 4 9 7 Cost Overrun Nil Mod. Hi 00 00 - . ] 8 5 10 8 9 6 1 5 10 7 3 10 10 4 1 5 3 3 4 6 3 1 2 1 3 4 1 4 5 0 4 3 5 1 1 4 2 1 3 1 1 2 3 3 1 Chi-square tests show no significance. Notes: 1. Investment in land and site development, building, machinery, transportation, installation, and shakedown. 2. These percentages refer to total manufacturing costs. equipment, ranging from a fairly detached seller-installer to a rather involved designer-seller/procurer-installer, seemed to have significantly contributed to the success, or lack of success ofthe start-up (see Exhibit 3, Characteristic 1). Similarly, no particular degree of subcontracting, ranging from the entrepreneur doing almost everything himself (i.e., negligible subcontracting) to subcontracting almost everything (approaching a "turnkey" contract) showed any clear success pattern. (Exhibit 3, characteristic 2) 15 American Journal of Small Business, Vol. V, No. 2, Fall (Oct-Dec), 1980 EXHIBIT 3 — EFFECTS OF PROJECTS MANAGEMENT CHARACTERISTICS ON START-UP TIME AND COST OVERRUNS PROJECT MANAGEMENT CHARACTERISTICS 1. Role of Machinery Supplier:' Designer-seller-installer Advisor-seller-installer Seller-installer 2. Subcontracting:' None Civil work only Plant design and civil work 3. Owner's experience in the industry: Considerable Moderate Short 4. Owner's ability to mobilize funds: ^Considerable Moderate Low 5. Reputation of Machinery Supplier: Highly reputable Average Not well known Time Overrun Nil 1 5 6 1 7 3 6 5 2 4 8 1 4 9 0 Mod. 1 0 3 1 5 0 4 1 2 CM CO (N 0 6 1 Hi CM 00 00 CO CO eo 4 8 8 5 9 6 3 10 7 Cost Overrun Nil 1 8 11 3 13 4 9 8 6 7 9 7 6 16 1 Mod. 1 4 2 0 7 2 2 3 5 2 7 1 en en o Hi 2 1 4 2 5 0 3 3 1 2 4 1 1 4 2 Chi-square tests show no significance; only Characteristic 5 suggests a relationship. Notes: 1. Machinery suppliers in six projects acted in various other roles. 2. Subcontracting in four projects were different from categories listed above. Entrepreneur's Roles The most apparent common denominator among successful projects was a particular set of attributes amongst their entrepreneurs (i.e., those who had the primary responsibility for execution ofthe start-up activities). Among these attributes, three stand out: (a) Constant first-hand monitoring of progress — In each of the successful projects in the sample, the entrepreneur put forth a considerable effort in monitoring the details of work which was underway. He seemed to have been constantly up-to-date on the actual day-to-day progress of everj^ctivity. He seldom relied solely on the subordinates' oral or written reports; often went after first-hand knowledge himself. For example, these 16 American Journal of Small Business, VoL V, No. 2, Fall (Oct-Dec.), 1980 entrepreneurs visited the site frequently, personally went to government agencies or banks, and dealt directly with the subcontractors. The close monitoring obviously taxed their time and emotional energy heavily — but they appeared to go through it willingly. (b) Swift reaction — The time lag between emergence of a problem and remedial action was generally shorter in successful projects. Through personal involvement, the entrepreneur was able to detect existing and potential problems faster. Furthermore, he had the organizational author- ity and fiexibility to make fast, sometimes on-the-spot, decisions. This was particularly important since the subordinates were often reluctant to bring up a problem in its early phases. They either felt they could solve it themselves, or simply did not appreciate the full impact of the delay in solving that problem. In some other cases, the difficulty arose because a subordinate, not having sufficient authority, had to take many problems to an entrepreneur who was not often immediately accessible. Examples of each of these cases were many. In a chemical plant, when a critical control valve was found to be damaged during installation, one of the entrepreneurs (who had been closely following the installation) simply got on the plane to Europe the next day and returned with a new one within three days. In another case, entrepreneurs in a textile plant, sensing that cement was becoming increasingly scarce in the city, pushed into the black market and procured sufficient quantity for their contractor to finish the plant on schedule. Another case involved an entrepreneur in a food processing plant. While he was visiting a trade fair in Europe, he saw a machine similar to one he had ordered for his plant from a different supplier. His order could not be delivered until the next year. He immediately purchased the demonstration unit and subsequently cancelled his original order. (c) Sensitivity to delays — Entrepreneurs in successful projects generally showed a high degree of sensitivity to delays. Normally they were not reluctant to spend more if they felt that by doing so they would avoid delays. Most of the subordinates (and entrepreneurs themselves) in the successful projects in the sample worked against established short- term target dates. (These dates were not necessarily related to those set in the original start-up plan). In the case of activities not on the "critical path," usually the full "slack" would not be taken.^ That is, these entrepreneurs tended to be on the safe side so far as the timing was concerned. Of course, this meant earlier outlays of funds, but these costs were generally accepted as an insurance against potential delays. Furthermore, they did not hesitate to spend what appeared to be a considerable sum to get a potentially troublesome job done faster. In the control valve example mentioned previously, the cost of an air ticket to Europe was almost double the cost of the valve itself — but to the entrepreneur that was an irrelevant comparison. What did matter was that a potentially expensive delay was avoided. 17 American Journal of Small Business, Vol. V, No. 2, Fall (Oct-Dec), 1980 Entrepreneurs in successful projects seemed to have maintained this outlook throughout the start-up work. In many instances, what seemed like an extravagant expenditure at the time eventually turned out to be a less costly alternative. A good example was the case of a carpeting plant. The two entrepreneurs in that plant had estimated their daily loss due to delay in the opening of their plant to be around $3,000. They were, therefore, ready to spend what seemed to be a lot of money to avoid delays or to gain time. The project was finished almost four months ahead of the originally estimated19 months, with 22% less than overall planned expenditures! This hypersensitivity to delay rarely seemed to result in cost overrun. Again, as shown in Exhibit 4, only one of the thirteen projects which met or beat time schedule had a moderate cost overrun. The rest were all within projected costs.'' To summerize, successful entrepreneurs appeared to be constantly on the look-out for existing and potential problems, had the flexibility, authority, and ability to move swiftly and decisively to alleviate many of the hitherto unforeseen problems, and showed considerable sensitivity to delays. Entrepreneur's Background: Surprisingly, the entrepreneur's experience in the particular industry did not seem to increase the chance of success significantly. Data in Exhibit 3 (Characteristic 3) show that time and cost overruns in projects whose investors had the most experience in the corresponding industries were not clearly lower than in other projects; nor were the overruns clearly higher in the case of investors with less experience in their industries. Again, contrary to its intuitive appeal, abundance of funds during start-up period did not seem to increase the likelihood of success EXHIBIT 4 — INTERDEPENDENCE BETWEEN STARTUP TIME AND COST OVERRUNS Time Cost Nil Mod High Total Nil 12 1 0 13 Mod 3 2 2 7 High 8 7 5 20 Total 23 10 7 40 Chi-square significance: p<0.05. 18 American Journal of Small Business, Vol. V, No. 2, Fall (Oct-Dec), 1980 significantly. The data (Exhibit 3, Characteristic 4) show that a greater ability of the owner(s) to mobilize funds in excess of the original bank loan(s) did not necessarily result in more successful start-up. On the other hand, deficiency in this ability did hurt the chances of success. Only one of the twelve successful start-ups was accomplished by owners who did not seem to have personal or additional institutional back-up financial reserves. Note that the owners' ability to mobilize funds may have no relationship with the amount of funds left at the entrepreneur's discretion during the start-up. Regardless of the owners' financial strength, the successful entrepreneurs in the sample seemed to have had easy (organiza- tional) access to sufficient working funds throughout most of the start-up period. Machinery Supplier's Reputation As mentioned earlier, success during start-up was not significantly affected by any particular role assumed by the major supplier of plant equipment. But a positive correlation did appear to exist between reputation of the supplier (as judged by the entrepreneurs and others) and a successful start-up. As shown in Exhibit 3 (Characteristic 5), machinery suppliers in the successful projects were generally well established and enjoyed a good reputation in the trade. The successful entrepreneurs preferred dealing with reputable suppliers wherever possible, in spite of the fact that these suppliers normally charged anywhere from 5 to 25% higher prices than industry average. In fact, none of the twelve successful entrepreneurs dealt with a company as a major supplier whose machinery was significantly cheaper than industry average. Conversely, almost every project in the sample which relied on cheap machinery suppliers for a major portion of its equipment ran into start-up problems. Undoubtedly, one reason for the emergence of this pattern is that reputable suppliers are generally better equipped and more willing to help entrepreneurs formulate an accurate start-up plan. Also, evaluation of the suppliers' reputation may have been infiuenced by their performance in the very projects studied. But in general, successful entrepreneurs appeared to be willing to pay the extra price of dealing with suppliers who were more dependable, who required less monitoring and follow-up efforts, and who seemed to run into fewer unforeseen problems and delays. The Planning Approach Despite their sensitivity to timetables and schedules, most successful entrepreneurs did not have formal master schedules. Except in two cases, common project planning models — such as PERT or CPM^ — were either not employed at all or, if employed, not seriously adhered to. In fact, most 19 American Journal of Small Business, VoL V, No. 2, Fall (Oct-Dec.), 1980 of the entrepreneurs — with successful start-ups or with time and cost overruns — neither invested heavily in, nor followed, a master project schedule. Instead, they typically scheduled their work incrementally — that is, to use Lindblom's phrase [4,p.79-88], they "muddled through" the start-up work. The overall or "master" schedule prepared at the time of feasibility analysis was gradually set aside and not updated; consequently, its usefullness as a guide for the entrepreneur's course of action deteriorated rapidly. The intriguing question is why most of the successful entrepreneurs, too, followed this pattern in their planning. In my opinion, there are three reasons: (a) The Uncertain Environment — Setting up a manufacturing plant in a developing country requires a great deal of interaction with an environment which changes at a rather rapid rate in directions which are difficult to predict. Government policies and regulations, price and availability of resources required during the start-up (e.g., manpower, construction materials), competitive situation in the raw materials, supplies and sales market, and general level of services rendered by the country's infrastructural institutions (e.g., transportation companies, utili- ties suppliers) may all vary considerably while a plant is being erected. Such variations, which are essentially beyond the control of entrepreneurs, frustrate efforts to produce accurate plans. Projection of environmental trends beyond a short planning horizon is more complex and expensive than most entrepreneurs seem to be able or willing to do. In other words, entrepreneurs seem to view the benefit of the information potentially available from an in-depth analysis of long-term environmental trends to be less than its cost. Their breakeven planning horizon usually appears to be far shorter than full duration of the start-up period. (b) The Newness of Activities — Estimation of the amount of resources required to accomplish many activities involved in setting up a new manufacturing plant in a developing country is, in itself, difficult. Often, no previous experience from a comparable job is available to the entrepreneur. Even for a specialist, the task is a complex one because experience from a similar project elsewhere can seldom be transplanted onto a new site, country, set of entrepreneurs, labor force, and culture. Too many factors infiuence the outcome. Too many outsiders — government bureaucrats, for example — can make entrepreneurs' predictions go wrong. Thus, rather than strenuously attempting to predict resource and time requirements for each activity, entrepreneurs appear to lean towards a policy of "crossing the bridge when coming to it." (c) The Interdependence of Activities — A related reason to (b) above is the high degree of interdependence of manufacturing start-up activities: machinery cannot be installed until a building is more or less completed; electrical lines cannot be brought into the plant unless official permission for industrial activity is obtained; technicians sent by a machinery 20 American Journal of Small Business, Vol. V, No. 2, Fall (Oct-Dec.), 1980 supplier would be wasting time if machinery is not released from customs on time. Given the uncertainties surrounding completion of an earlier activity, entrepreneurs are generally reluctant to make firm commitments of resources to subsequent activities; hence, a detailed plan of action is usually drawn up only for the near future. CONCLUSION Successful executionof a manufacturing start-up plan in a developing country depends essentially upon the entrepreneur. A successful entrep- reneur is able to push the start-up work forward and keep it on schedule and within budget regardless of the plant's technological or logistical characteristics. He does this by being flexible, monitoring progress closely, reacting to problems quickly and decisively, and being hypersensitive to delays. He does not usually follow an elaborate master plan; instead, he muddles through the start-up work — always attentively, always ready to change course, always pushing. Sound project feasibility analysis is still needed; obviously, the project should be viable, and the initial course should be set wisely. For example, selection of a reputable machinery supplier, even at an extra cost, is usually a wise decision. But to turn a feasibility plan into reality, there are more ways than following a refined master start-up plan. Strict application of the widely accepted network models — such as PERT — is not necessarily a superior planning approach in this situation. Many successful entrepreneurs in developing countries plan their way through the start-up work incrementally. A partner, an investor, a banker, a foreign expert, or a government official, who forces such an entrepreneur to apply sophisticated planning techniques not only may not be helping him, but may in fact be hindering the progress of the project. Such pressure often results in the entrepreneur's pretending that he is following a sophisticated planning model when in reality he continues to apply his sharp business instinct to get the work done his way. He needs a certain degree of organizational and financial latitude to do his job; if he becomes a subject of mistrust and his latitude is taken away, he is likely to run into more difficulties — hence, worsening the mistrust. A viable feasibility plan is a prerequisite to successful start-up of a small manufacturing venture in a developing country — but no guarantee. The entrepreneur is the key. Perhaps that is one reason why in the developing countries sometimes resources, are allocated to projects more on the basis of the individuals involved rather than the merits of the projects themselves. 21 American Journal of Small Business, Vol. V, No, 2, Fall (Oct-Dec), 1980 FOOTNOTES ' Classified according to the size of total investment. For these projects, the range was $0.2 to 9.5 million with the median $1.4 million. For more detailed breakdown, please refer to Exhibit 2 (Plant Characteristic Number 1). ^ This proposition is indirectly supported by the findings of the previously mentioned studies [1][2][3]. Only one of Teece's [3] conclusions — that the cost of technology transfer is inversely related to the age of technology — appears to be incompatible with this proposition's broad implications. But this incompatibility may be mostly due to the fact that Teece has examined large projects, some of which may have been publicly owned, whereas this study has focused on small and medium size ventures owned by private investors, principally. There are, naturally, practical limits on the technological and logistical characteristics of a plant started up by a private investor or entrepreneur in a developing country: seldom would he venture into untested technology, locate his plant in a particularly remote area, or undertake an obviously unprofitable project for the country's general welfare. The Government, on the other hand, may. ' See project planning literature for definitions. For example, see Edward W. Davis, "Resource Allocation in PERT Network Models — A Survey," Journal of Industrial Engineering, Volume XVII, No. 4. * Teece (3,p.91) has suggested a theoretical U-shape curve for technology transfer time-cost trade-off: i.e., as the project duration is increased the project cost is first lowered (negatively-sloped range) but after reaching a minimum point, it is increased (positively- sloped range). My study suggests that for small and medium size plants in developing countries, the practical time-cost trade-off is mostly positive — i.e., it is limited to the positively-sloped portion of Teece's curve. REFERENCES 1. UNCTAD, "The Transfer of Technology," Journal of World Trade Law, 4, (September- October 1970). 2. Teece, David J., The Multinational Corporation and the Resource Cost of International Technology Transfer, Ballinger, 1976. 3. Wallender III, Harvey W., Technology Transfer and Management in the Developing Countries: Company Cases and Policy Analysis in Brazil, Kenya, Korea, Peru, and Tanzania, Ballinger, 1978. 4.'Lindblom, C.E., "The Science of "Muddling Through,'" Public Administration Review, Vol. 19. 22
Compartilhar