What approach should the project manager propose? A. Change to an agile model, focusing primarily on the incremental life cycle, leaving the iter...

What approach should the project manager propose?


A. Change to an agile model, focusing primarily on the incremental life cycle, leaving the iterative approach as a next step.
B. Maintain a predictive approach, but increase the focus on better planning and tracking to anticipate problems and avoid delays.
C. Migrate to an agile model, focusing primarily on an iterative approach, leaving the incremental life cycle as a next step.
D. Propose a hybrid approach, leveraging the benefits of an agile approach while respecting some aspects of the company’s industry.

💡 1 Resposta

User badge image

Ed Verified user icon

Based on the given options, the project manager should propose option D: Propose a hybrid approach, leveraging the benefits of an agile approach while respecting some aspects of the company's industry. This approach allows for flexibility and adaptability while still considering the specific requirements and constraints of the company's industry.

0
Dislike0

Faça como milhares de estudantes: teste grátis o Passei Direto

Esse e outros conteúdos desbloqueados

16 milhões de materiais de várias disciplinas

Impressão de materiais

Agora você pode testar o

Passei Direto grátis

Você também pode ser Premium ajudando estudantes

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta.

User badge image

Outros materiais