Logo Passei Direto
Material
Study with thousands of resources!

Text Material Preview

AACE-PSP Planning & Scheduling Professional (PSP) Exam exam dumps
questions are the best material for you to test all the related AACE exam topics.
By using the AACE-PSP exam dumps questions and practicing your skills, you
can increase your confidence and chances of passing the AACE-PSP exam.
Features of Dumpsinfo’s products
Instant Download
Free Update in 3 Months
Money back guarantee
PDF and Software
24/7 Customer Support
Besides, Dumpsinfo also provides unlimited access. You can get all
Dumpsinfo files at lowest price.
Planning & Scheduling Professional (PSP) Exam AACE-PSP exam free
dumps questions are available below for you to study. 
Full version: AACE-PSP Exam Dumps Questions
1.Which of the following is NOT a tool or technique used to perform scope planning?
A. Benefit cost analysis.
B. Schedule performance indexing.
C. Expert Judgment.
D. Alternatives identification.
Answer: B
2.Which activity is drawn in the incorrect position?
Refer to the time-scaled network diagram and other information to answer the following questions.
Please consider this to be the entire network.
 1 / 12
https://www.dumpsinfo.com/unlimited-access/
https://www.dumpsinfo.com/exam/aace-psp
A. Activity G.
B. Activity E.
C. Activity C.
D. Activity D.
Answer: D
3.If drafting of the product manual overruns its planned duration by 5 days, how many days may the
manufacturing be delayed without affecting release of the product?
 2 / 12
https://www.dumpsinfo.com/
A. 15 days.
B. 10 days.
C. 0 days.
D. 5 days.
Answer: C
4.Using the "normal" schedule, and assuming you are billing on the last day of the month for previous
month and for appropriate partial months, how many invoices will you have for this project?
A. 42.
B. 36.
C. 40.
D. 37.
Answer: B
5.In its simplest form, what is the main drawback of critical path method scheduling?
A. It requires a backward pass to calculate late dates.
B. It assumes that resources are unlimited.
C. It doesn't account for interdependent between activities.
D. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
Answer: B
6.Identify the late finish to develop plans and specs.
 3 / 12
https://www.dumpsinfo.com/
A. 9 months.
B. 10 months.
C. 8 months.
D. 7 months.
Answer: A
7.Activity durations are normally estimated in an intuitive and subjective way. All of the following will
improve duration accuracy EXCEPT
A. Use gross building square footages. The pluses and minuses all average out.
B. Look at each activity independently and don't follow specific logic paths when assigning activity
durations.
C. Divide activities into smaller activities. This will increase activity detail and duration estimate
accuracy.
D. Use the people responsible for performing the work as a resource to assign activity durations.
 4 / 12
https://www.dumpsinfo.com/
Answer: A
8.There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single
crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum
number of tower cranes that should be used for the above described column pours?
A. 2 cranes
B. 1 crane
C. 4 cranes
D. 3 cranes
Answer: A
9.Management has determined the need to release the product 20 days earlier than planned.
What tasks need to be expedited?
 5 / 12
https://www.dumpsinfo.com/
A. Drafting and Proofing the Manual.
B. Packaging only.
C. Printing the Manual.
D. Testing, Manufacturing and Packaging.
Answer: D
10.Which of the following will NOT affect the total float calculation of a non-resource leveled
schedule?
A. Multiple calendars.
B. Start and finish constraints.
C. Preferential logic.
D. Front end loading.
Answer: D
11.What is the actual duration as of the status date or data date of Activity B?
Refer to the time-scaled network diagram and other information to answer the following questions.
Please consider this to be the entire network.
 6 / 12
https://www.dumpsinfo.com/
A. 7.
B. 3.
C. 0.
D. 4.
Answer: B
12.Based on the stated costs, what percentage of the total cost comes from the 2000 series of
activities?
A. 3.9% (1 : 25.708)
 7 / 12
https://www.dumpsinfo.com/
B. 2.3% (1 : 43.501).
C. 9.1% (1 : 11.000).
D. 8.6% (1 : 11.591)
Answer: B
13.Time-scaled logic diagrams are
A. Only calculated using a computer.
B. The same as a pure-logic diagram.
C. Used to calculate the most probable activity duration.
D. Logic networks that are drawn to match the calendar.
Answer: C
14.What is a key first step in developing a critical path method schedule?
A. Drawing a bar chart of the key phrases of the work.
B. Defining the execution plan to meet the required scope of work.
C. Setting out the resource to be used and its limitations.
D. Drawing the logic diagram.
Answer: D
15.In order for a claimant to be entitled to an extension of contract time for a delay event (and further
to be considered compensable):
A. The delay must affect the critical path.
B. The delay must be concurrent with the delay attributable to both parties.
C. The delay must not cause monetary harm to the defendant.
D. The delay must affect the contractor's planned construction schedule.
Answer: A
16.What owner action could have mitigated the late completion of the project?
A. Hire a more senior project manager.
B. Self-perform more of the work.
C. Use a procurement agent to monitor and expedite equipment deliveries.
D. Prepare better structural steel drawings.
Answer: C
17.Theoretically construct a summary activity for activities 6001 through 6003.
Identify the governing predecessor and successor activities for the hammock:
 8 / 12
https://www.dumpsinfo.com/
 9 / 12
https://www.dumpsinfo.com/
A. Predecessor is activity 5001, successor is activity 8001
B. Predecessor is activity 4001, successor is activity 8001
C. Predecessor is activity 9001, successor is activity 9002
D. Predecessor is activity 5001, successor is activity 8002
Answer: A
18.Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?
 10 / 12
https://www.dumpsinfo.com/
 11 / 12
https://www.dumpsinfo.com/
A. 12-27-03 and 24 days of float
B. 12-18-03 and 4 days of float
C. 12-17-03 and 4 days of float
D. 12-18-03 and 25 days of float
Answer: C
19.What is the cycle time?
A. 5 minutes
B. 17 minutes
C. 14 minutes
D. 6 minutes
Answer: B
Powered by TCPDF (www.tcpdf.org)
 12 / 12
https://www.dumpsinfo.com/
http://www.tcpdf.org