Prévia do material em texto
85 Hector Choy, Long-Range Planning Supervisor, Black Thunder Mine, Gillete, Wyoming, United States CHAPTER 5 Strip Mine Planning and Design Hector Choy INTRODUCTION Modern strip mining (which is often referred to as open pit or open-cast mining) began with the development of the steam shovel used in the excavation of the Panama Canal. However, underground mining continued to dominate the extraction industries until the early 1900s, when strip mining proved itself to be more economical for near-surface, flat-lying deposits. Strip mining is a form of surface mining that uses strip cuts to mine generally shallow, flat-lying deposits. Strip mines are typically layered deposits—a classic example is surface coal mining. This chapter concentrates on considerations in the mine planning and design process of strip coal mines. The primer for mining engineers is Surface Mining (Pfleider 1972); see Kennedy (1990) for the updated second edition of that text, and SME’s Mining Engineering Handbook, 3rd edi- tion (Darling 2011). Mine Planning and Design There are two general approaches to mine planning. The first is the development of a greenfield or new property. Capital investments have not been committed; the property may already have been acquired or is in the process of evaluation. The prefeasibility study establishes the value of the property and potential capital commitment. Prefeasibility may require a general mine plan to establish if mining is practical and may go as far as suggesting what equipment would be used. The feasibility study then details the capital commitment and life of the property and includes a detailed economic evaluation. To develop economics in terms of cash flow, expected net present value (NPV), and internal rate of return (IRR), the fea- sibility study requires a detailed mine plan, equipment selec- tion, schedules identifying the timing and amount of capital expenditures, and estimates of projected revenue and costs. Information on mining economics can be found in Stermole and Stermole (2019). Table 1 lists items to consider in a mine plan feasibility study. An existing property or brownfield expansion consid- ers an operation where equipment and facilities are already in place and future development is planned. Mine planning for existing operations may require a different approach to address market conditions and the need to expand, scale back, or maintain a steady-state production level. In an existing property, where equipment and facilities are established, the two stages of mine planning are the short- term mine plan and the long-term or (life-of-mine) plan. These stages are significant in that mines often assign designated staff and instigate significant mine planning efforts to best meet the differing requirements and level of detail for these two functions. A list of items to consider in the mine planning process is shown in Table 2. Short-Term Mine Planning The short-term mine plan (or operating plan) generally relates to a period of less than 5 years and is typically broken down into monthly, quarterly, and annual operating plans. Each stage reflects a level of detail designed to guide the mining toward fulfilling annual production and economic budgets and capital expenditures. A high degree of planning detail is placed on the first 2 years of short-range planning with col- laboration from other departments such as production, main- tenance, electrical, and plant. Each of these departments provides essential information to the planning process, such as mining methods, major equipment outages, preventive maintenance and repairs, substation relocation, and railroad and power plant outages, and it is the responsibility of the mining engineer to incorporate relevant information into the mine plan. During the first 2 years of short-range planning, sequencing and scheduling is performed on a monthly basis. For each month of the plan, the first step is to sequence and schedule the removal of soil material (topsoil), either by plac- ing this into individual piles where it can be stored for later use during the reclamation process or laid down directly onto previously mined areas in the ongoing reclamation process. The second step is the sequencing and scheduling of the over- burden removal process through conventional drilling and blasting, truck and shovel overburden prestrip (if required), cast blast, dragline bench (pad) construction, and dragline or Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. 86 SME Surface Mining Handbook truck and shovel overburden removal to expose the coal seam beneath. The final step is the sequencing and scheduling of coal removal and blending from different pits if available. The process will include coal blasting, loading and hauling, crush- ing, and storage to meet the production and quality require- ments necessary to satisfy power plant contract agreements. Long-Term Mine Planning The defined planning periods can vary depending on the size and life of the reserves, along with the general purpose and objectives of the operation. The objectives of the long- term mine plan include identifying and scheduling labor lev- els, equipment production levels, and capital requirements Table 1 Salient factors requiring consideration in mine planning and feasibility studies Information About Deposit General Project Information Development and Extraction Economic Analysis Geology: overburden Stratigraphy Geologic structure Physical properties (highwall arid spoil characteristics, degree of consolidation) Thickness and variability Overall depth Topsoil parameters Geology: coal Quality (rank and analysis) Thickness and variability Variability of chemical characteristics Structure (particularly at contacts) Physical characteristics Hydrology: overburden and coal Permeability Porosity Transmissivity Extent of aquifer(s) Geometry Size Shape Attitude Continuity Geography Location Topography Altitude Climate surface conditions (vegetation, stream diversion) Drainage patterns Political boundaries Exploration Historical (area, property) Current program Sampling (types, procedures) Market Customers Product specifications (tonnage, quality) Locations Contract agreements Spot sale considerations Preparation requirements Transportation Property access Coal transportation (methods, distance, cost) Utilities Availability Location Right-of-way Costs Land and mineral rights Ownership (surface, mineral, acquisition) Acreage requirements (on-site, off-site) Location of oil and gas wells, cemeteries, etc. Water Potable and preparation Sources Quantity Quality Costs Labor Availability and type (skilled, unskilled) Rates and trends Degree of organization Labor history Governmental considerations Taxation (local, state, federal) Royalties Reclamation and operating requirements Zoning Proposed and pending mining legislation Compilation of geologic and geographic data Surface and coal contours Isopach development (thickness of coal arid overburden, stripping ratio, quality, costs) Mine size determination Market constraints Optimum economics Reserves Method(s) of determination Economic stripping ratio Mining and barrier losses Burned, oxidized areas Mining method selection Topography Refer to previous geologic/ geographic factors Production requirements Environmental considerations Pit layout Extent of available area Pit dimensions and geometry Pit orientation Haulage, power, and drainage systems Equipment selection Sizing, production estimates Capital and operating cost estimates Repeat for each unit operation Project cost estimation (capital and operating) Mine Mine support equipment Office, shop, and other facilities Auxiliary facilities Labor requirements Development schedule Additional exploration Engineering and feasibility studyPermitting Environmental approval Equipment purchase and delivery Site preparation and construction Start-up Short-range and long-range production plan Cash flow Revenue Capital Labor Operating costs Royalties Taxes Evaluation Risk reward Net present value Internal rate of return Source: Hrebar and Atkinson 1998 Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. Strip Mine Planning and Design 87 (including major equipment purchases, infrastructure expan- sion, reserve expansion, acquisition of new reserves, mine permit acquisition, and end-of-life reclamation). Long-term mine plans usually cover a period greater than a year beyond the current active operations, up to and including the point when the life-of-mine plan starts. Typically, these long-term mine plans are broken down into levels of detail that include quarterly plans for up to 5 years, annual plans out to a mini- mum of 10 years, and general plans out to the life-of-mine planning horizon. Other applications of long-term planning are to determine production sensitivity to revenues and costs (which would affect production rates), capital projects, and the life of the reserve. Both short- and long-term mine plans are decision tools to help manage the risk and reward opportu- nities that confront mine management. Risk and Reward The successful implementation of a correctly formulated mine plan will yield the optimal recovery of the resource, as mea- sured by optimizing the resulting revenues (reward) and effec- tively controlling costs (risk). Costs for a new property can vary substantially because of unknown conditions. It is the mining engineer’s task to identify and characterize key condi- tions and factors and to assign costs to them that realistically represent the risks involved in developing and safely mining the reserve. It is also the mining engineer’s function to get the most value from the reserve by using proven methods to mine and produce the resource in a timely manner. Determining the time value of money—or the NPV of a project—is the most common method of measuring the economic balance between risk (costs) and reward (revenues) for a mine development project: i1NPV cash flows t= +^ h (EQ 1) where NPV = net present value cash flows = net cash flows at time t i = discount rate t = time of cash flow A base-case mine plan is typically developed to identify and quantify the costs and revenues associated with develop- ing the property. Successive planning scenarios are usually developed to evaluate the cost/revenue effects of changing mine plan layout, sequencing, production schedules, equip- ment, or other parameters to minimize cost impacts and maxi- mize the resource recovery and revenues to optimize NPV. This process is a daunting one but is nevertheless a necessary task, and as multiple plans are developed and evaluated the what-if scenario begins to gel into a solid base-case plan. Table 2 Major steps in surface mine development preceding production buildup and full production Assembly of Minable Coal Package Market Development Environmental and Related Studies Preliminary Design, Machine Ordering NEPA Process Permits Design and Construction Mining Preparation Lease acquisition Mapping the area Drilling program Surface drilling rights acquisition Drilling, sampling, logging, analysis Mineral evaluation (determination on commercial quantities present) Drilling on closer centers (development drilling) Sampling, logging analysis Surface acquisition Market survey Potential customer identification Letter of intent to develop and supply Contract negotiation Initial reconnaissance Scope of work development Consultant selection Implementation Environmental impact report Environmental monitoring Conceptual mining development Economic size determination Mining system design, layout, and development Equipment selection Stripping machine ordering Mine plan development Identification of lead agency for EIS Draft EIS EIS review and comments EIS hearing and record Federal EIA review Council on Environmental Quality filing Mining and/ or reclamation plan approval State water well rights appropriation permits State special use permit, such as a reservoir State mining permit State industrial siting permit Federal NPDES permit U.S. Forest Service special land use permit Preliminary design and estimation Material ordering and contracting Water well development Access road and site preparation Railroad construction Power supply installation Facilities and coal handling construction Warehouse building and yards Coal preparation and loading facilities construction Overland conveyor construction Stripping machine(s) erection Loader erection Support equipment readying Labor recruitment and training Source: Jones 1977 Note: EIA = environmental impact assessment; EIS = environmental impact statement; NEPA = National Environmental Policy Act of 1969; NPDES = National Pollutant Discharge Elimination System. Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. 88 SME Surface Mining Handbook OUTLINING RESERVES Project mapping often begins with a general location map that shows geopolitical boundaries, towns, roads, general topo- graphic features, the mine location, and any nearby residences or structures. In addition to the general location map, one should also be aware of any old abandoned or active under- ground mines beneath the surface mine property. Mapping Planning starts with more detailed mapping of topography, surface drainage features, surface and mineral ownership, existing facilities and infrastructure, and potential mine area and disturbance boundaries. Commercial aerial mapping flights and unmanned aerial vehicles (UAVs or drones) retro- fitted with GPS and LiDAR lasers can provide accurate digital images of the terrain and are now easily obtained and inexpen- sive. The acquired data can be processed into a digital terrain model and subsequently into a surface contour of the property to help identify existing structures, facilities, and other sur- face features. Ground surveys using GPS equipment provide additional detail and have, in the short time since its incep- tion, become the basis for the ongoing process of mapping and documenting mining and related activities. Infrastructure includes the location of existing features—roads, rail lines, pipelines, power lines, communication lines and cell towers, wells, buildings, and structures on and adjacent to the mining property—that may be used for or affected by mining activi- ties. It is important to identify not only features related to the mining activities, but also features and resources that may require special environmental considerations, such as streams, ponds, forest land, fire breaks, wetlands, wildlife habitat, and other protected or environmentally sensitive areas. Initial geo- logical maps should include surficial geology (outcrops, sur- face geologic exposures, structural features) and indications of strike and dip of structures. Maps prepared by governmen- tal research organizations such as the U.S. Geological Survey are a typical starting point for new operations. Conversion of GPS surveys to a geographic information system format allow the ongoing collection and integration of ownership, environ- mental, geologic, mine, and reclamation planning and opera- tional information. Because modern mapping is computerized, map infor- mation is developed and saved as individual layers that can then be selected and combined to produce a range of special- ized maps. Although it is important to define and establish a common mapping datum for compatibility, determining a map scale is not critical because the scale can be adjusted later to meet map presentation requirements.After a standard map- ping datum is established, all mapping should be completed and input to that datum. The mapping datum and coordinate system should be compatible with the maximum area expected to be affected by mining and should accommodate both short- and long-term planning. Documenting the basis for the map- ping information (metadata) and preserving original data in a digital format with appropriate backups is important. Access and ability to change, alter, or delete information on original data maps should be carefully restricted, and any such altera- tions properly and securely logged. Drill-Hole Coverage Sufficient drill-hole information is critical for the development of geologic and mine planning models. For example, if a com- pany has a history of drilling in the area, such as oil and gas exploration; other mining companies or government research agencies have drilled in the area, then all known drilling infor- mation should be reviewed and evaluated for reliability and content. Field geologist data and drilling and geophysical information are then consolidated into a geologic computer model. In a new operation (or one that is expanding into a new reserve area), a drilling program will be required to col- lect enough information to adequately evaluate the property. A resource is typically defined by the level of confidence in the occurrence and extent of the minable seams. In open pit min- ing, the terms measured, indicated, and inferred convey both the extent of drilling and the level of confidence in the reserve characterization. In surface strip mines, the deposits tend to have consistent thickness characteristics; therefore, drill spac- ing for initial exploration often involves a grid spacing of 0.4 to 0.8 km (Figure 1). Areas that require more extensive drilling (or seismic studies) are seam boundaries, structural features, and surface disconformities such as valleys, surface displacements indicating faulting, and depositional uncon- formities. The greater the variation in reserve characteris- tics, the greater is the need for increased drilling density or supplementary data collection. Data quality can be evaluated and supplemented using geostatistics techniques, which take into consideration variances in the coal seam when drill data are being correlated. In operating mines, geologic structure and coal quality information from the initial drilling program can be supplemented by performing infill exploration drill- ing ahead of the active pit areas. Infill drilling refers to drill- ing additional exploration holes within the initial exploration drilling grid spacing. Normally, drill spacing for infill explora- tion drilling is in the range of 122 to 244 m apart (Figure 2). Figure 1 Initial exploration drilling spacing: undeveloped area Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. Strip Mine Planning and Design 89 This tighter drill spacing will yield a more refined geological structure and coal quality model. Some mines prefer to obtain structural and quality information from drilling and blasting activities in active operating areas. Once a geological model is developed, the engineer should use the model to become familiar with the reserve and identify structure, thickness, and quality issues that may exist in planned mining areas. Geology to Mine Planning Using the drill-hole information and surface structural fea- tures, the geologist develops a geological model. This model should include seam identification, structure, thickness, qual- ity, and characteristics that may affect mining efficiency such as overburden or interburden thickness and characteristics, fracturing, variations in thickness, washouts, and water table. The engineer should be looking for inconsistencies in qual- ity and thickness to determine the extent of minable seams and the mining characteristics that would affect equipment selection and productivity. It is also important to understand overburden, interburden, and floor characteristics and struc- tural constraints as indicators of potential stability prob- lems. Information on highwall angle and spoil angle can be estimated by material type and stability characteristics from geotechnical analysis. Thickness, strike or dip, strip ratio, and quality maps should be developed for all potentially minable seams. This can either be a fairly straightforward process, or more complex and time-consuming if seams combine and split. Transitioning from a geological model to a mining model requires the understanding of reserve characteristics, potential structure hazards, equipment capabilities, and strip mining methods. Geological cross sections, history and knowledge of the area, research on similar deposits, and knowledge of mining methods are all resources the engineer can use to opti- mize mine planning. The basis for a good mine plan is a good understanding of the topography and geology of the property. To facilitate this, there are numerous geologic and mining computer soft- ware programs that can produce accurate topographical maps based on aerial and land survey data information that cover all of the projected mining area along with potential facili- ties and any significant surface structures. Most topographical surfaces are normally stored electronically as a grid or trian- gulated irregular network (TIN) file. In addition, it is neces- sary to become familiar with seam characteristics, structure, and the quality information for each minable seam (referred to as target seams). Contour thickness maps (also known as iso- pach maps) should be generated for each of the targeted seams and should include information on overburden, interburden (waste material between targeted seams), and the undiluted thickness of the targeted seams. Quality maps (sometimes called isopleth maps) should also be created for each targeted seam. Geologic structure maps (also known as contour maps) need to be developed to identify any structures (e.g., faulting and offsets) that would affect the mining method or decrease recovery and increase dilution and waste. Coal loss due to ribs, barriers, top or bottom of coal seam dilution, and overblasting can be as high as 10% in eastern U.S. operations (Secor et al. 1977). Reserve Evaluation Modern mine planning starts with a computer model of the resource. The extent, structure, quantity, and quality of the resource and the associated burden material should be well defined. These data allow the engineer to develop a mining model. The mining model will incorporate and consolidate data of the resource into a model of minable seams, waste, and soil materials (sometimes referred to as suitable plant growth material or topsoil). For this purpose, a reserve is identified as a resource that is delineated by its economic strip ratio. Strip Ratio The economic stripping limit is usually the first factor to be determined in establishing the mine plan. The economic stripping ratio (ESR) is defined as the cubic meters of waste material to be removed to uncover 1 t (metric ton) of product. For illustration purposes in this chapter, coal will be used as the resource. Developing maps that show the ratio of over- burden thickness to a minable coal thickness is a good place to begin. This ratio can be converted to a strip ratio map by mapping the thickness of the overburden and interburden converted to cubic meters and divided by the thickness of the coal converted to metric tons. This ratio is calculated using the cumulative thickness of both overburden/interburden and coal seams down to, and including, the lowest minable seam. For example, for a 61-m cumulative overburden/interbur- den thickness with a total coal thickness of 6.1 m, and assum- ing the average density of bituminous coal at 1.28 t/m3, the stripping ratio would be calculated as follows: burden = 61 m × 0.91 m × 0.91 m = 51.0 m3 coal resource= 6.1 m × 0.91 m × 0.91 m × 1.281 t/m3 = 6.47 t or Figure 2 Infill exploration drilling spacing Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. 90 SME Surface Mining Handbook stripping ratio = 51.0 m3 ÷ 6.47 t = 7.88:1 (EQ 2) These calculations can be used to define an economic limit: • Cost for overburden/interburden mining is $1.63/m3 • Cost of coal mining is $2.76/t • Estimated revenue is $13.23/t The economic stripping ratio is defined as RESR MCO MCC= − (EQ 3) where ESR = economic stripping ratio (m3/t) R = revenue from coal or ore ($/t) MCC = mining cost of coal or ore ($/t) MCO = mining cost of overburden/interburden/waste ($/m3) ($13.23/t – $2.76/t) ÷ $1.63 = 6.41 or 6.41:1 The ratio becomes the economic mining limit and is the first step in establishing the economically minable reserve. The formula can become more complex as issues of quality affect the economic value of the coal. It is important for the engineer to understand the mining economics and contract restrictions, including coal quality penalties and bonus provi- sions (such as lower ash and sulfur, and higher BTU content), may affect revenues. Other adjustments to coal recovery (and actual minable reserves) would be dilution and in-seam losses, which tend to downgrade the stripping ratio by increasing the cubic meters of waste and decreasing the number of metric tons of resource. Depending on mining conditions and thick- ness and quality of the seam, losses can amount to several percent and have a significant impact on the reserve. RESOURCE CONTROL Ownership of land and minerals is a key consideration that should be addressed and determined early in the planning process because it can affect development time frames, per- mitting requirements, development cost structure, and project profitability. Land and Mineral Ownership Land ownership typically consists of two components: the surface estate and the mineral estate. Either or both may be held by private (fee estate) or public (public estates are gener- ally managed by federal or state agencies) entities. In some cases, the surface and mineral estates may be held separately (severed estate). The rights to access and utilize the surface and to develop and produce the mineral resource can be secured through direct ownership (purchase of the surface and/or mineral estate), lease agreement, or a combination of these legal vehi- cles. In the instance of federally managed public estate coal, a company with a proposed coal lease must submit its request to acquire the lease with the Bureau of Land Management (BLM) through a lease by application. The BLM then per- forms an environmental assessment study and establishes coal lease market value and sale criteria. Interested companies that can mine the coal lease economically must submit competitive bids and the BLM awards the coal lease to the highest bid- der. The successful bidder must pay a bonus bid for each ton of coal in the lease. In many cases, the right to develop and produce the mineral resource (particularly where public estate minerals are involved) carries with it certain rights of sur- face access and use. However, there may be instances where the surface is privately owned and the coal beneath publicly owned or vice versa. In either case, lease agreements will need to be developed and agreed upon by both parties. With the exception of direct ownership, other access and development rights typically involve structured payments to secure and exercise these rights. These typically take the form of advance payments to secure the rights, flat-rate annual fees for use of the lands, royalty payments based on mineral production rates, fee payments keyed to specific activities, or combinations of these payment mechanisms. Secure, well-defined access and development rights are an important element of a stable cost structure and are key to project cost control and profitability. Also, ownership rights for the project area and an adjacent buffer zone can be impor- tant in minimizing and successfully addressing potential con- flicts with adjacent landowners and uses. Other Resources In Wyoming (United States) during the 1990s and 2000s, gas collected from coal seams (i.e., coal-bed methane) became a significant consideration relative to permitting and the timing for development of coal reserves where both (independently recoverable) resources exist. Existing oil and gas (or other mineral) leases must be a consideration in the extent of and timing for development and production of reserves because most of these wells will need to be purchased to mine through them or the well bypassed altogether. PERMITTING Mine permitting is the process of preparing and submitting relevant project information for review and approval by jurisdictional government authorities to verify project plan compliance with applicable laws and regulations. In general, applicable laws and regulations as they relate to mining are designed to prevent, control, minimize, or effectively mitigate potential adverse mining-related impacts on the environment, wildlife, and human health and welfare. Mine permitting may involve submittal of individual permit applications for approval of specific mining-related activities (mining and reclamation, air emissions, water dis- charge, wildlife surveys, facility construction, and so on). Alternately, it may involve environmental analysis and plan approvals for the project as a whole or a combination of all these approval mechanisms may be involved. An outline of typical mine permitting requirements is provided later in this chapter. Typically, the process involves a review by national or state/provincial agencies that have approval authority over land uses or mining and reclamation plans. It may also involve review by agencies with authority over specific environmental resources such as air, water, wildlife, and other specific project aspects. Normally, some provision is provided in the permit- ting process for input by affected parties and nongovernmen- tal organizations. Environmental Baseline At the start of the permitting process, it is important to effec- tively characterize environmental resources and values as they exist in the project area (this is the baseline) prior to min- ing disturbance. Generally, baseline characterization involves field studies by qualified professionals of all resources and Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. Strip Mine Planning and Design 91 values that may be affected. The following resource values are typically characterized: • Land use • Cultural, archaeological, and paleontological resources • Geology • Meteorology and air quality • Surface and groundwater hydrology • Soils • Vegetation and wetlands • Fish, wildlife, and related habitat values • Aesthetics and noise • Socioeconomic conditions Baseline characterization then forms the basis for devel- opment of specific measures to prevent, control, minimize, or mitigate the potential impacts and for the evaluation of poten- tial mining-related impacts with consideration of planned con- trol and mitigation measures. Mitigation Plans At the point in a project at which permitting activities are initiated, mining and reclamation plans are generally well defined, including the locations, extent, and nature of surface- disturbing activities. Comparison of the extent and nature of mining activities with information from environmental baseline characterization provides the basis for development of project mitigation plans. In many cases, required mitiga- tion measures are defined to some extent by specific regula- tory requirements. A common example is the requirement for the collection and treatment of runoff from mine disturbance areas to comply with effluent standards before water is dis- charged to natural drainages. To address site conditionsand constraints or enhance postmining land use, the mine operator may have an opportunity to develop site-specific mitigation plans or to modify mitigation plans within the limits of regula- tory constraints. Impact Analysis and Monitoring Environmental impact analysis is an integral part of the per- mitting process, whether it is the evaluation of regulatory compliance as part of a permit review or of the significance of potential impacts. In the context of a permit review, impact analysis focuses on whether the proposed mining and related activities (and planned mitigation measures) meet specific regulatory require- ments and performance standards. For environmental factors, impact analysis typically includes the evaluation of direct, indirect, and cumulative impacts and assesses whether potential impacts meet an objec- tive, or indeed the subjective measure of significance. Prepared and evaluated as part of the permitting process, monitoring plans provide a mechanism for the direct mea- surement of impacts on specific environmental resources. If properly designed and administered, monitoring can identify significant changes in resource conditions. It can be used to assess the effectiveness of mitigation measures and the accu- racy of impact assessments and to modify operating and miti- gation practices. Timing It is critical to allow sufficient time in the project schedule for project permitting. It normally takes between 12 and 18 months to collect adequate information for the environmental baseline characterization. Depending on project complexity, permit preparation may require between 6 and 24 months. Required agency reviews and approval may extend the over- all permitting schedule by another 6–24 months. Important factors in minimizing permitting time frames include ensur- ing adequate and timely baseline characterization, conduct- ing effective ongoing communication with stakeholders, and coordinating closely with jurisdictional agencies. INFRASTRUCTURE Existing infrastructure (i.e., roads, water wells, oil or gas wells, pipelines, phone lines or power lines that run through the property) must be identified and mapped. The landowners must be contacted and be informed of the intent and potential impacts of mining. Existing Infrastructure Where existing infrastructure may be affected by mining, mit- igation action may be necessary, either in the form of compen- sation or relocation/replacement of the structures. Mine Infrastructure The necessary infrastructure to support mining and related operations will need to be planned, developed, and accounted for in the economic evaluation process. This infrastructure will include roads and utilities, office and change-house facili- ties, warehouse and maintenance facilities, material handling, processing and product transportation facilities, drainage and sediment control systems, and so forth. Infrastructure Mapping Maps showing both existing and planned mine infrastructure are typically developed as part of the mine planning process. Features that will be mined around or that are not within the mining area are not shown on the reserve map. Some struc- tures require economic analysis to determine whether min- ing around or compensation, relocation, or replacement is the better economic approach. These areas may be included in the reserve, but until the status of the areas is resolved they should be excluded in the base-case mine plan as non-minable reserves. PIT DESIGN For surface strip mines, the choice of mining method is dic- tated by the terrain, geology, and depth of the resource. The terms contour mining and area mining are used to describe mining methods that are suited to specific geologic and topo- graphic conditions. Mining Methods Where the terrain is variable and multiple seams are present, contour mining may be the best option. In the Appalachian mines of the United States, thin seams, undulating topography, and sometimes steeply dipping seams require equipment that is highly adaptive and mobile and can move material relatively long distances. These conditions favor contour mining using large-tracked dozers, rubber-tired scrapers, truck and shovel or loader-truck equipment fleets, and occasionally small drag- lines (23–35 m3). As the ESR increases, contour mining may be coupled with follow-up to auger, highwall mining or with conventional underground methods. Where the terrain is relatively uniform and the seam or seams are flat lying, area mining is often the preferred Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. 92 SME Surface Mining Handbook approach. Relatively large flat-lying deposits such as the coal reserves of Wyoming’s Powder River Basin (PRB), phosphate deposits in Florida (United States) and the Middle East, and the Canadian tar sands are well suited to area mining meth- ods using large draglines (46–120 m3), fleets of large-scale shovel trucks (shovel capacity 46–76 m3; truck capacity 140–230 m3), or even bucket-wheel excavators (BWEs) and cross-pit conveyor systems. Using large stripping equipment and moving large quantities of material keeps unit operating costs to a minimum. The PRB mines initially commenced in the mid-1970s because of the Organization of the Petroleum Exporting Countries (OPEC) oil embargo. They started at the coal seam outcrop and were typically mined at a 1:1 stripping ratio up until the 1980s; however, by the 1990s the stripping ratio had increased to more than 2:1 and at present the strip- ping ratio is more than 3:1. As mining progresses to the west, the stripping ratio increases as the coal seams dip between 1% and 2% to the southwest and the overburden gets thicker. This increase in strip ratio is also reflected where split seams occur. Coal quality also increases from north to south, which can have a significant effect on the ESR. Changes in geology must be taken into consideration in pit design and equipment selec- tion. Bise (2003) gives several examples of equipment selec- tion. Bucyrus-Erie Company (1979), Caterpillar Performance Handbook (Caterpillar, Inc. 2018), and Specifications and Applications Handbook (Komatsu 2013) are good sources of information on shovel and truck selection and operation. Large electric shovels are used in both contour and area mining. They offer good flexibility, reasonable mobility, and moderate to high loading capacity, and they can be used for both stripping overburden and ore loading. However, electric shovels do require a truck fleet, along with associated support equipment (dozers, blades, and water trucks) and haulage- road requirements, which can increase production costs. Draglines are high-production machines used to strip and move overburden over short distances. Draglines have limited mobility and are generally not suited for loading product. It can take up to a year to construct a dragline, and its cost can range from $50 to $100 million. Nevertheless, draglines are dominant in the large surface coal mines in the United States and in other large flat-lying deposits throughout the world (Cassidy 1973). In the lignite mines of Europe and the U.S. Gulf Coast, large BWEs and conveyor-belt systems are used to excavate and move large volumes of overburden and product economi- cally. The BWE is a continuous-excavation machine capable of removing up to 240,000 m3 of material per day. BWEs are found mostly in coal mining in Europe, Australia, and India. A BWE can cost more than $100 million and take 5 years to construct. A compilation of equipment application and various mining scenarios as applied at operating properties can be found in Chironis (1978) and Kirk (1989). Support equip- ment including drills, dozers, scrapers, loaders, graders, water trucks, and—depending on individual mine requirements—a multitude of other equipment required to complete the min- ing cycle is a significant capital and operatingcost. Sources for accounting for this equipment include vendor publications such as the Caterpillar Performance Handbook, Edition 48 (Caterpillar, Inc. 2018) and vendor websites. Cast blasting is a technique generally used in combination with dragline operations to increase overburden production capacity and reduce costs. Occasionally truck and shovel, dozers, and scrapers are used in lieu of draglines. Cast blast- ing utilizes the blast energy and gravity to move a portion of overburden from the highwall side of the pit into the previous empty pit and against the previous spoils. The portion of the overburden that is not casted onto the empty pit is then moved onto the spoils using the dragline effectively, thereby reduc- ing overall dragline production and rehandling requirements. However, the effective design and control of blasting is impor- tant to maximize overburden movement while preventing loss of the underlying resource, particularly in multiple-seam pits. Highwall mining is a method of increasing coal recov- ery in a pit where the stripping ratio has reached its economic limit and surface operations are no longer cost-effective. Two types of highwall mining are commonly used: auger min- ing, in which a large-diameter auger bores parallel holes into the exposed coal seam; and conventional mining, in which a remote-controlled continuous miner, coupled with an exten- sible conveyor, extends parallel entries into the exposed coal seam. For highwall mining to be effective, the key criterion is that the coal and surrounding rock must be competent to be self-supporting when a portion of the coal seam is removed. Geotechnical calculations determine the size and allowable depth of the auger or miner entries. Recoveries above 50% are possible with augers as large as 2.4 m in diameter, and conventional methods can result in slightly higher recover- ies. Experience has shown that highwall mining is not well adapted to steeply dipping seams. Pit Geometry After the boundary of the minable reserves is established, the geometry and structure of the reserve dictate pit orientation and configuration. When the pit orientation is laid out, the mapped dip and strike of the seams and any geological struc- tures such as faulting or discontinuities should be taken into consideration. Geotechnical evaluations provide additional valuable information for determining highwall and spoil slope angles, slope angles for waste and soil stockpiles, pit-end and interbench slope angles, and the overall highwall angle for multiple-seam operations. For both planning and operations tracking and reporting, a standard naming convention should be established for desig- nating and referring to specific mining areas, pits within each mining area, and cut sequencing within each pit. This nam- ing convention should designate and explain mining units to be used in the scheduling process. The width and length of the pits are typically constrained by the pit geometry, physical limitations of the equipment (e.g., dragline reach), and the tar- geted production rate required. Pits are generally broken down into strips and mining blocks based on both production sched- uling considerations and the accuracy required for reporting volumes. Each mining block should contain information such as area, overburden thickness and volume, coal thickness and tonnage, and coal quality. Short-term planning often requires smaller blocks (i.e., 60 × 60 m), depending on drill spac- ing and quality variations. A smaller mining block provides increased accuracy relative to production volumes and qual- ity. Long-term planning does not require the same accuracy, so larger mining blocks may be acceptable (i.e., 250 × 60 m), thereby reducing data requirements and the amount of time required to input and analyze the data for mine scheduling. Points to consider when developing the design of mine pits include the following: Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. Strip Mine Planning and Design 93 • Orientation of the pit with respect to the strike and dip of the seam and site topography. Pits with inside curves result in insufficient spoil room and additional rehandle and should be avoided. Outside curves create additional spoil room and provide for spoil-side access to the coal seam. Similarly, mining up-dip creates more spoil room and reduces the potential for spoil failure. If the terrain is relatively flat, straight pits usually give better control over the pit and tend to result in better productivity. • Prominent structural features, such as faulting, along with intersecting drainages and groundwater. A groundwater dewatering system, such as drilling wells ahead of the active pits, may be required to reduce the impact on highwall stability. The water produced from dewatering wells can later be used for dust suppression on haul roads and while drilling on blast patterns. • Length and width of the pit. Generally, a maximum pit length of 1.6 km (1 mi) is a good rule where ramp access to the pit floor is sufficient. Most ramps are spoil side, but there are occasions when highwall ramps and drilling and blasting ramps are required. Minimum pit width is driven by the depth of the pit and equipment clearances needed in the pit bottom. There generally needs to be sufficient width in the bottom of the pit to operate coal-loading equipment with truck and drill access. Keeping the pit width to a minimum is necessary to minimize rehandling. • Haul access. This consideration of pit design should provide sufficient room for drilling, blasting, and coal extraction. Intermediate spoil ramps, usually at least one per pit, are required to access the pit bottom from either side of the main haulage ramp. Pit-end ramps are also a consideration, so that coal extraction, drilling, and blasting are not cut off by overburden operations. Haulage access design becomes more complex for multiple-seam operations. • Highwall and pit-end ramps. These are used when spoil material is unstable. The disadvantage of highwall ramps is that the ramp must be re-established after each cut, and the main haul road requires relocation when mining advance encroaches on the existing haul road. Rehandle Rehandle is defined as material that is moved more than once to uncover the same amount of resource. A normal amount of rehandle for a dragline is 10%; however, this depends on the dragline mining method. Some circumstances require increased rehandle, such as when pit width and/or overbur- den depth is greater than the average design for the equipment being used. In such cases, rehandling material may be more cost-effective than purchasing additional equipment or using equipment that is more costly on a unit production basis. When rehandle costs and volumes for major production equipment increase beyond normal limits, the availability and effective productivity of the equipment for stripping is decreased. Utilizing truck and shovel prestripping on a dragline pit may decrease rehandle significantly, resulting in additional strip- ping capacity but increasing total stripping cost. Managing rehandle becomes a trade-off between production capacity and lowest-cost utilization of the equipment. Another source of high-dragline rehandle occurs when draglines have to mine across a coal ramp. As the dragline approaches the ramp, it becomes difficult to spoil the overbur- den material in front of the ramp to its final spoil destination in a single pass. This material must temporarily be dumped on the ramp and subsequently rehandled for final spoiling. In many cases, this inefficiency is reduced by removing some of the rehandle material with truck and shovel or loader-truck assistance. Unnecessary rehandle can occur when stockpiles are placed too close to the active pit or when production schedul- ing requires rehandle of stockpiled material. Spoiland high- wall failures, which can also result in unnecessary rehandle, may result from poor maintenance of the pit bottom (i.e., large amounts of standing water), stacking spoils too high, high- wall/spoil angles that exceed design parameters, or weak floor structure. An elevated water table, water in the pit, and poor surface-water drainage can all greatly influence highwall and spoil stability. Unplanned rehandle is an unnecessary cost that can have a direct impact on production cost. Mining Sequence For a new property, the mine planning process comprises set- ting a target production, selecting the equipment necessary to meet that production rate, and running a projected production schedule to determine the economics of the plan. Production sensitivities are then run to determine if the plan can be improved by changing the production level, equipment, pro- duction sequence, or other preselected parameters. It is not uncommon, and indeed it is acceptable, to run several itera- tions to produce an economically optimized mine plan. For an operating mine, production targets and equipment fleet may be preset. In such situations, meeting the target pro- duction rate becomes the focus of planning runs to best fit adjustments to pit configuration and sequencing to the equip- ment for a given production rate. In this case, planning options may include supplementing, replacing, or idling existing equipment to meet the required production rate. The mining sequence is considered in the pit design phase. A typical example of mine sequencing is a dragline oper- ation initiated with a box cut. In a dragline operation, the box cut is typically the initial excavation, which creates sufficient spoil room for the first dragline pit. Figure 3 illustrates three box-cut scenarios. A typical mining sequence would involve topsoil removal, overburden removal, coal removal, backfilling of the resulting Cut End Cut Spoil A Seam A Overburden Cut End Cut with Rehandle Spoil Borrow Pit Spoil Spoil A Seam A2 A1 Overburden Cut Borrow Pit Spoil A Seam A Overburden Source: Skelly and Loy 1975 Figure 3 Box-cut methods Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. 94 SME Surface Mining Handbook pit with overburden spoils, and grading of the spoils to the final reclamation configuration, followed by reclamation grad- ing, replacement of soil materials, and revegetation. For most regulated operations, unless there is a variance in the permit, soil materials and, in some cases, underlying weathered mate- rials are stripped and stockpiled for future replacement on regraded spoil materials. In some cases, these materials can be directly replaced on existing regraded spoil areas, avoiding the need for stockpiling and often resulting in better reclamation. Figures 4A–4G illustrate the steps in a typical dragline sequence. Figure 4A shows the pit as it would look at the end of the previous cycle. The coal is extracted and the pit is ready for the next cut, which is shown by the vertical dashed line. Figures 4B and 4C illustrate the results of cast blasting on both the upper and lower seams. Figure 4D shows the upper bench being graded in preparation for the dragline bench. Figure 4E illustrates the several phases of stripping that a dragline would perform; the first is extending the bench to allow the dragline to walk out far enough to cast the next cut of spoil to build a spoil-side bench for the dragline to sit on. In Figure 4F, the dragline is moved to the spoil side, where the bench has been graded to an elevation that allows the dragline to uncover the coal seam. Finally, Figure 4G shows the section immediately before removing the coal, which is the last step in the cycle. When the coal has been extracted, the cycle is repeated. The purpose of generating range diagrams (Figure 5) is to determine the amount of material moved by the production equipment in each sequential step. These volumes are then used to determine the productivity of the equipment for that specific pit geometry. Overburden thickness and changes in the coal seam geometry can affect the production levels and a different configuration may be required. The trade-off with the cast-blasting technique is the loss of coal and dilution due to fracturing of the coal seam at the exposed highwall of the pit, sometimes referred to as the wedge (Figure 6). Other configurations that could be compared to cast blasting would be a pre-bench truck and shovel or scraper fleet, depending on the depth of the material above the first seam. Computer programs that simulate dragline scenarios are used to generate the equipment volumes needed for scheduling. By using the volumes and tonnages from the mining blocks and adjusting the equipment configuration and rate of production for different geometries and sequencing, a database of schedul- ing volumes can be generated by pit and equipment type with rehandle quantities and expected coal production tonnage. Each scheduled scenario produces operating hours for each piece of equipment. By using the equipment operating hours and apply- ing an estimated or historical equipment cost per hour through an economic model, scenarios are compared to evaluate the impacts of each on NPV. This process is used in both proposed and ongoing mine projects to provide justification for equip- ment purchases and modifications to the mine plan. Specialized Blasting Techniques For strip (open-cast) mining, overburden must often be frag- mented by blasting so it can be efficiently and economically excavated. For many years, mining engineers have consid- ered cast blasting (explosives casting) of overburden both to take advantage of the explosive energy used to fragment the overburden and to reduce material excavation and handling costs (Brealey and Atkinson 1968; McDonald et al. 1983). The low cost and high gas pressures of ANFO explosives make cast blasting more attractive as a production tool. The advantages of cast blasting become increasingly significant for thick overburden with resistant layers requiring high powder factors (kilograms of explosives per cubic meter of overburden blasted)—0.65 kg/m3 is typical for some very strong sandstones, for example, in the United States, South Africa, and Australia. Applications have shown that in certain circumstances, cast blasting in deep overburden can be more economic than conventional stripping. This method, which is based on reducing the primary overburden removal by the (A) (B) (C) (D) (E) (F) (G) Source: Hrebar and Atkinson 1998 Figure 4 Dragline pit sequence cross section Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. Strip Mine Planning and Design 95 dragline (Figure 7), has the added advantage of promoting gravity segregation of the cast material. Large rock fragments come to rest near the pit floor to form the base of the spoils, thereby improving spoil drainage and stability. Figure 8 illus- trates a typical cast blasted profile. Presplit blasting may be used in conjunction with cast blasting to dewater permeable overburden and create stable highwalls. Additionally, in strong ground, a vertical face can be created in conjunction with cast blasting, rather than the irregu- lar sloping face produced by conventional blasting (Figure 9). It is obvious from Figure 9B that the vertical face, with greatly reduced distance from the front row of blastholes to the toe of the highwall, will result in far more efficient cast blasting. However, cast blast patterns using angled blastholes (Figure 10) tend to produce more casting distance (projectile effect) than cast pattern using vertical holes (toppling effect). In cast blast- ing, rows of blastholes parallel to the highwall are detonated sequentially, initiated from the highwall progressively from front to back, resulting in maximum overburdencast across the pit. Experience shows that marginally more overburden is Figure 5 Dragline range diagram Cast Pro�le Coal Wedge Cast-to-Final Coal Overburden Figure 6 Potential coal wedge loss Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. 96 SME Surface Mining Handbook cast using this design, but a section of overburden between the presplit line and the last row of blastholes may remain in place (Figure 11). Typically, the first three front rows of a cast blast pattern will move the most volume of material the farthest to its final resting location (i.e., cast-to-final). The fourth row and up to the last row tend not to cast and subsequently the mate- rial is moved by stripping equipment. Cast blast patterns are usually designed using a square or staggered pattern. Choosing which pattern to use is site specific and will need to be tested to determine which will achieve the lowest blasting cost and the greatest cast-to-final volume movement. The geometry of the spoil after cast blasting must be con- trolled to provide a section suitable for dragline operations while moving as much overburden as possible across the pit. The best results appear to occur with about a 30° offset using a staggered V pattern with relatively long, interrow delays. Figure 12 illustrates a typical section and the desired sec- tion. The throw depression can be greater than desirable, and some minor rehandling of the thrown spoil is necessary to establish a bench for dragline operations. Depending on the type of overburden (such as mudstone, sandstone, shale, coal stringers, or a combination), the spacing-to-burden ratio of the blasting pattern should be determined using site-specific geologic factors and requires detailed consideration to control the trajectory of the thrown spoil. For example, a porous sand- stone layered with several coal stringers will degrade the blast energy and not cast as well as a solid hard sandstone, which will yield a more efficient cast. The presence of coal stringers and weak layers in the overburden allows the blast energy to escape rather than confine the blasting gas in the borehole and may result in a violent blast with undesirable flyrock. A means of evaluating the feasibility and effectiveness of cast blasting is the use of the linear relationship of cast volume to depth/width (d/w) ratio. This is a ratio varying from 0.4 to 0.9, where d is the pit depth from the highwall crest to the bot- tom of the lowermost seam and w is the width of the exposed pit bottom (toe of highwall to toe of spoils). Generally, the Interburden 38 m (125 ft) Lower Coal Seam Main Coal Seam Prime Dragline Burden Truck and Shovel Prestrip Blast P ro�le 27.5 m (90 ft) 30 m (98 ft) 11.5 m (38 ft) Section Width 305 m (1,000 ft) Prime D/L Truck and Shovel Total Spoil 822,045 358,209 463,837 Spoil Handled Once: 760,254 92% Rehandled Once: 61,791 8% 822,045 100% Bank Cubic Yards Dozer Extended Bench Courtesy of Mincom, Inc., Denver, Colorado Figure 7 Typical pit section Saving in Dragline StrippingProfile After Blast B Profile After Blast A Dragline Seat Spoil Heap Large Fragments in Base of Spoil Heap New Profile Blast B Blast A Source: Hrebar and Atkinson 1998 Figure 8 Blast cast profile (A) (B) Source: Hrebar and Atkinson 1998 Figure 9 Blast cast profile: (A) conventional blasting profile, (B) presplitting profile Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. Strip Mine Planning and Design 97 greater the d/w ratio value, the greater the cast-to-final volume into the empty pit. A potential negative side effect of large cast blasts is the unintended development of ground vibration (depending on the size of the cast pattern), airblasts, and fumes. If the mine is located in a remote area this may not be a problem; how- ever, if the mine is located near towns, inhabited dwellings, industrial facilities, and such, it may pose an issue. One must adjust several parameters to resolve such issues; for example, blast smaller cast patterns (which decreases efficiency), adjust blast-delay timing (longer delays), avoid cast blasting on cloudy days to reduce airblasts, or use highly water-resistant bulk product (to reduce fumes). Single-Seam, Cross-Pit, Chop-Down Operation A dragline used in the chop-down mode is about 60% efficient compared with the conventional drag mode. Bucket mainte- nance costs are also higher (although this is considerably alle- viated by the better fragmentation achieved in cast blasting). The depth/width ratio of the pit should exceed 0.4 for cast blasting to be considered (i.e., this method is best suited to deeper pits). Figure 13 shows the method of operation. The dragline bench height in Figure 13C can be fixed so that the spoil crests are essentially level, virtually eliminating the need to grade the spoil peaks during reclamation. This advantage can only be fully realized, however, if the height of the dragline bench above the top of the seam does not exceed the optimum dig- ging depth. Where this height exceeds the optimum digging depth, the bucket must be cast and dragged prior to the swing cycle, thereby increasing cycle times. In these circumstances, it is usually more economic to level the spoil peaks with either the dragline (rehandle) or conventional mobile equipment. The single-seam, chop-down method may be used to strip seam partings in multiple-seam operations. This operation results in a reduction of dragline productivity of up to 50%, but if the ratio of parting to lower seam thickness is low, this approach can be an economical option. Two-Seam Method The steps utilizing cast blasting are illustrated in the following sequence (refer to Figures 4A–C, and as described previously in the “Mining Sequence” section): 1. The pit section prior to blasting (Figure 4A). 2. Interburden blasted into the void left after extracting the mineral from the previous strip. Large rocks will form the base of the spoil heap and are not handled by the dragline (Figure 4B). 3. Blasted overburden. The throw depression of the inter- burden blast is filled by overburden spoil (Figure 4C). This method results in an increase in dragline productivity above that of conventional dragline stripping, but insufficient experience is available in comparable conditions to quantify this increase. However, other marked advantages include: • Both seams are exposed, allowing simultaneous seam recovery. The upper seam can be dozed over the side of Remains In Situ Presplit Line Last Row of HolesProfile Before BlastProfile After Blast Source: Hrebar and Atkinson 1998 Figure 11 Blasting with parallel tie-up Angled Drill Hole Empty Pit Spoils Coal Overburden Figure 10 Example of a cast blast pattern profile with angled drill holes Highwall X-delay Presplit Line Dragline Seat Rehandle Actual Profile Desired Profile Throw Depression 40% 60% Percentage Blast Over 1 2 4 6 1 2 3 4 5 6 Source: Hrebar and Atkinson 1998 Figure 12 Blasting method Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. 98 SME Surface Mining Handbook the bench (or by other suitable means) onto the lower seam, thereby concentrating and simplifying mineral loading operations and improving blending. The volume of in-pit exposed reserves is increased, allowing greater flexibility in operation. • Spoil stability is enhanced by gravity segregation of the cast blast materials, with larger durable rock forming a base for the spoils. • With both seams exposed simultaneously, additional drag- line moves and dead-heading can be eliminated or reduced. • Reduced need to handle durable rock materials with the dragline can result in reduced bucket maintenance costs. This method can also be used for single-seam, thick- overburden applications to eliminatechop-down operations for upper overburden benches. Where weathered material exists near the surface, the upper bench can be presplit with more closely spaced holes than for the lower, more competent overburden. Provided weathering is not too deep, the upper bench slope can be increased, up to a maximum of 90° (verti- cal), because presplitting will limit blasting effects and reduce drainage concerns. Highwall a b c a d b c Edge of Seam Throw Depression Blasted Profile Optimum Bench Height Presplit Line (A) (B) (C) Source: Hrebar and Atkinson 1998 Figure 13 Cross-pit, chop-down with single-seam method of operation Stripping Previously Worked Deposits In some situations, thick coal seams that have been previously partially extracted by underground methods (e.g., room-and- pillar mining) can be economically recovered by strip mining. In these situations, stability and the safe operation of the drag- line can be in question where conventional dragline stripping is proposed. Cast blasting provides an alternative stripping method for suspect areas where the dragline is not located over the pillared coal, thereby minimizing stability and drag- line safety concerns. Equipment Selection The following criteria are among those that should be con- sidered when selecting equipment for a new or expanding operation: • The life of the project. Certain capital and operating cost considerations should be evaluated. Smaller equip- ment (e.g., scrapers) has lower capital costs but much higher operating costs, depending on the haul distance and the unit volume moved. In comparison, draglines have much higher capital costs and much lower unit operating costs. For example, a scraper may have a capi- tal purchase cost of $2 million, with a recurring replace- ment cost every 5 years, a unit capacity of 23 m3, a life of 35,000 hours, and an operating cost of $0.98/m3 varying with the haulage cycle. A 115-m3 dragline might have a capital purchase price of $50 million, an operating cost of $0.20/m3, and a life of 150,000 hours. It typically will last for the life of the project, which could be 30 years, with a single major rebuild costing $10 million. • Depth and thickness of the seam(s) overburden and coal, with total depth to last minable seam. Typically, pits up to 150 m in depth can be surface mined. • Strike and dip of the property. Is the deposit type more suited to area mining or contour mining? • Comparison with similar operations. Consider similar operations, but do not restrict the decision by existing convention. In the 1980s, there were only truck and shovel operations in the PRB. The first dragline was introduced in 1982, and since then draglines have dominated U.S. surface mines in Wyoming, Montana, Colorado, Texas, and North Dakota. • Combinations of mining methods. This may require an array of equipment types. • Equipment type and size. For draglines, evaluate the equipment type and size by generating range diagrams from cross sections across the length of the reserve. Figure 7 (or Figure 5) illustrates a typical range diagram and the volume distribution. Choose typical cross sec- tions that represent variations in the reserve. For truck and shovel operations, bench height and passes per cycle help to determine equipment matching. Three to five bucket passes by a shovel to fill a truck is considered a good match. It will be important to select equipment that can handle changes in pit geometry. • Dragline capacity. Multiple-seam operations require handling of intermittent coal and interburden, which will impact the productivity of a dragline and require loader-truck equipment to handle the smaller seams. Dragline capacity must take into account such production interruptions. Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. Strip Mine Planning and Design 99 • Haulage scenarios. Evaluate haulage scenarios for truck and shovel and scraper operations. • Cast blasting. Look at the possibility of augmenting pro- duction with cast blasting. • Used draglines. Evaluate the market for used draglines that are currently idle. Finding a dragline that can be relo- cated for half the cost of a new dragline may fit the mine plan needs. All options should be evaluated for the highest NPV and IRR. Ground Control and Pit Slope Stability Effective ground control and planning for pit slope stabil- ity comprise a two-step process. First, geological structures and groundwater conditions that may affect stability need to be identified and characterized. The planning process then focuses on the proper layout and design of the pit geometry and mine structures to address site-specific structural and groundwater conditions. In addition to adequate exploration drilling, sampling, and logging to characterize geology, lithology, general struc- ture, water levels, and reserve characteristics, seismic stud- ies can prove invaluable in delineating structural features and characteristics. Groundwater studies can also provide supple- mental information on groundwater occurrence and flows. Proper pit layout minimizes exposure of structural uncon- formities in the pit highwall, provides for effective drainage of both surface water and groundwater, and avoids geometries that tend to adversely concentrate ground forces (i.e., noses or notches). Similar considerations are appropriate for mine structures, including mine spoils, overburden and waste piles, tailings facilities, water impoundments, and mine buildings. For pit slopes and spoil piles, as well as engineered structures such as tailings facilities and water impoundments, geotechnical analysis by qualified professionals is appropri- ate. These analyses assess both static and dynamic (seismic) stability and are often required by applicable regulations. In the case of engineered structures, foundation testing is often a component of the geotechnical analysis and specific recom- mendations for foundation preparation and drainage measures are incorporated into project construction plans. MINE SAFETY As a critical element of modern mining operations, safety must be a key consideration in planning all aspects of mine operations: layout and design of pit geometry and mine struc- tures and facilities, road design, equipment selection, and operations planning and scheduling. Applicable regulatory requirements often factor in safety as well as environmental considerations. However, effective protection of worker safety and health requires thought and effort well beyond the scope of regulations. For this reason, the planning phase should address both engineered safety con- siderations (i.e., pit design and equipment safety features) and safety systems (i.e., worker training, safety awareness, equip- ment inspection and maintenance, and health monitoring). LAND RECLAMATION On completion of active mining operations, whether for an individual mining area or for the mine as a whole, mine dis- turbance areas should be returned to a stable condition. The potential for any short- or long-term adverse environmental effects or hazards to wildlife and human health and safety should be minimized, and productive postmining land use(s) should be supported. After completion of the initial phase of mine planning and prior to mine permitting, a postmin- ing topography (PMT) of the mine is developed. A rigorous review of the PMT is performed by regulatory agencies where several rounds of revisions and amendments are normally car- ried out prior to approval. Once the PMT is approved and the mine has progressed a few years, the reclamation process of the mine can start by backfilling the voids with overburden using truck and shovel material and grading mine pit areas using dozers or scrapers to near the approved PMT surface. The backfilled elevation is controlled using a GPS survey crew or equipment fitted with GPS guidance system. The PMT surface shouldblend with the surrounding terrain to promote effective drainage. Once the overburden material is graded to near PMT level (e.g., 0.6 to 0.9 m below final PMT) the overburden must be sampled and analyzed for pH levels and other natural occur- ring elements. If the analysis meets acceptable limits imposed by the regulatory agencies, replacing stockpiled soil materi- als (topsoil) can begin. If the overburden sample analysis is not satisfactory, then overburden material must be removed, replaced, resampled, and reanalyzed. This process is repeated throughout all backfilled areas. Topsoil material for reclamation generally comes from two locations: stockpiles or topsoil removal ahead of the active pit mining. If there are no areas available to receive topsoil directly from pit advancement, then it needs to be stockpiled for later use. Topsoil stockpile slopes are graded with shal- low sides (i.e., 3:1 slopes) to avoid erosion due to heavy rain runoff. Berms and ring ditches are also constructed around the perimeter of the stockpile to contain the topsoil and avoid contamination with the surrounding overburden. Seeding of a topsoil stockpile is required to grow vegetation and maintain its organic composition. After a graded area is spread with topsoil, the topsoil depth and location are measured and recorded. (Generally, topsoil replacement depth is determined in the approved recla- mation plan.) Once topsoil replacement depth is achieved, the topsoil is disked and seeded. A seed mixture that is compatible with native vegetation species is designated in the approved reclamation plan and normally targets a higher vegetation yield than what was originally present during premining. Once seeding is complete, the vegetation in the area must grow and thrive on its own without further human intervention (i.e., no fertilizers or watering). After a few growing seasons, the process of monitoring vegetation growth and animal popula- tion begins: this can take several years. The reclamation of the postmining land conserves and attracts indigenous and nonin- digenous animals to the area, hence promoting a sustainable ecosystem. As part of the planning process, it is sometimes possible to enhance the natural conditions and land uses that existed prior to mining or to make land modifications that may facili- tate higher and better land uses. Effective land reclamation can minimize the potential for any short- or long-term liabilities and maintain or increase the value of mined lands. Land reclamation is important in promoting a positive perception of the operator and the min- ing industry as a whole as being environmentally aware and responsible. Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved. 100 SME Surface Mining Handbook RECENT MAJOR CHANGES Major changes and developments over the last few years in terms of strip mining can best be summarized as follows: • Improved mine planning software on a year-to-year basis. Most mine planning software programs of today are com- puter-aided design (CAD) driven with three-dimensional modeling and visualization. In the past, planning was more of a two-dimensional modeling system consisting of data input, black-box calculations, and results. • Better computers to handle the graphics and calculations needed in mine planning software. • Refined data acquisition using GPS survey systems, LiDAR laser scanners, UAV (drone) with laser or pho- togrammetry data-acquisition system (although this pro- duces large electronic files). • Improved cast blast software design using a CAD system as well as usage of electronic detonators for precise blast timing as compared to pyrotechnic systems. • GPS-controlled equipment with onboard electronic design plan (for draglines, shovels, dozers, drills, etc.), which reduces surveyor assistance. Future Changes for the Next Generation Major changes and developments for the next generation in terms of strip mining include: • Major technological advances for mining equipment (GPS guidance and tracking systems) • Introduction of fully functional autonomous/remote- operated equipment (haul trucks, dozers, drills, blades, etc.) • Quicker surveyed field-data acquisition using drones (field to office) • Equipment/personnel proximity detection systems (colli- sion avoidance) • Equipment operator fatigue monitoring systems (eye detection/safety) • Improved equipment communication systems to handle all equipment monitoring and data gathering • Opposition to strip mining (coal) due to climate change ACKNOWLEDGMENTS The majority of this chapter is based on the excellent chapter by Jerry M. Nettleton and the late Ernest T. Shonts Jr., which appeared in SME’s Mining Engineering Handbook, 3rd edi- tion (Darling 2011). ABOUT THE AUTHOR Hector Choy began his career in coal mining as a haul truck operator and working in the drilling and blasting crew for Teck Corporation at the Bullmoose Mine in British Columbia. Choy then attended the British Columbia Institute of Technology and graduated with a Technologist Certificate in Mining, fol- lowed by a Bachelor of Science (Mining Engineering) with a minor in Business Finance from Montana College of Mineral Science and Technology in Butte, Montana. Thereafter he joined Shell Mining Company and worked for 3 years in underground coal with duties including feasibility studies, underground short- and long-range planning, longwall and continuous miner panel design, ventilation, roof control, and hoisting. Choy then transitioned to surface coal mining for Trapper Mine in Craig, Colorado, where his duties included haul road design and long-range dragline planning before he moved to Arch Resources at Black Thunder Mine near Gillette, Wyoming, where for 28 years he has held a number of significant positions including pit and engineering supervisor, and later, short- and long-range planning supervisor. SUGGESTED FURTHER READING Brealey, S.C., and Atkinson, T. 1968. Opencast mining. Mining Engineering 123(12):147–163. Hrebar, M.J., and Atkinson, T. 1998. Strip mine planning and design. In SME Mining Engineering Handbook, 2nd ed. Edited by H.L. Hartman. Littleton, CO: SME. Kennedy, B.A. 1990. Surface Mining, 2nd ed. Littleton, CO: SME. Pfleider, E.P. 1972. Surface Mining. New York: SME-AIME. REFERENCES Bise, C.J. 2003. Mining Engineering Analysis, 2nd ed. Littleton, CO: SME. Brealey, S.C., and Atkinson, T. 1968. Opencast mining. Mining Engineering 123(12):147–163. Bucyrus-Erie Company. 1979. Shovel/truck. In Surface Mining Supervisory Training Program. South Milwaukee, WI: Bucyrus-Erie Company. Cassidy, S.M. 1973. Elements of Practical Coal Mining. New York: SME-AIME. Caterpillar, Inc. 2018. Caterpillar Performance Handbook, Edition 48. Peoria, IL: Caterpillar. Chironis, N.P. 1978. Coal Age Operating Handbook of Coal Surface Mining and Reclamation, vol. 2. New York: McGraw-Hill. Darling, P.G. 2011. Mining Engineering Handbook, 3rd ed. Littleton, CO: SME. Hrebar, M.J., and Atkinson, T. 1998. Strip mine planning and design. In SME Mining Engineering Handbook, 2nd ed. Edited by H.L. Hartman. Littleton, CO: SME. Jones, J.R. 1977. The process of developing a western coal mine. In 1977 Mining Yearbook. Denver: Colorado Mining Association. pp. 132–138. Kennedy, B.A. 1990. Surface Mining, 2nd ed. Littleton, CO: SME. Kirk, S.J., ed. 1989. Western Surface Coal Mining. Littleton, CO: SME. Komatsu. 2013. Specifications and Applications Handbook, 31st ed. Tokyo, Japan: Komatsu. McDonald, K.L., Smith, W.K., and Crosby, W.A. 1983. Productivity improvements for dragline operations using controlled blasting in a single and multiple seam open- cast operation at Reitspruit, South Africa. CIM Bulletin 76(851). Pfleider, E.P. 1972. Surface Mining. New York: SME-AIME. Secor, E.S., Larwood, G.M., Gupta, A.B., et al. 1977. Coal Recovery from Bituminous Coal Surface Mines in the EasternUnited States—A Survey. Information Circular 873. Washington, DC: U.S. Bureau of Mines. Skelly and Loy. 1975. Economic Engineering Analysis of U.S. Surface Coal Mines and Effective Land Reclamation. USBM Contract No. SO 24104. Washington, DC: U.S. Bureau of Mines. Stermole, F.J., and Stermole, J.M. 2019. Economic Evaluation and Investment Decision Methods. Golden, CO: Investment Evaluations Corporation. Copyright © 2023 Society for Mining, Metallurgy & Exploration Inc. All rights reserved.