Buscar

A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that t...

A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities.

What should the project manager do?


A. Modify the project schedule to accommodate the delays in the purchase of services.
B. Request that the purchasing tasks be outsourced through an existing purchasing vendor.
C. Meet with the purchasing manager to find the source of the delays and agree on a purchasing schedule.
D. Ask the project team to keep developing other tasks that do not depend on the purchase of services.

💡 1 Resposta

User badge image

Ed Verified user icon

Nessa situação, o gerente de projeto deve tomar algumas medidas para lidar com os atrasos na compra de serviços. A resposta correta é a opção C. O gerente de projeto deve se reunir com o gerente de compras para identificar a origem dos atrasos e concordar com um cronograma de compras. Isso permitirá que o projeto avance de acordo com o planejado, garantindo que as tarefas relacionadas à compra de serviços sejam concluídas dentro do prazo.

0
Dislike0

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais