What is the purpose of the Sprint Retrospective?

To review and approve the work done by the Development Team during the Sprint.
To inspect the Increment and adapt the Product Backlog if needed.
To plan the work that will be done in the next Sprint.
To identify and plan improvements to the way the Scrum Team works.
a) Only I is correct.
b) Only II is correct.
c) Only III is correct.
d) Only IV is correct.
e) IV is correct.

Essa pergunta também está no material:

2020-Scrum-Guide-PortugueseBR-3 0
16 pág.

Product Management OutrosOutros

💡 1 Resposta

User badge image

Ed Verified user icon

A resposta correta é a alternativa d) Only IV is correct. O objetivo da Sprint Retrospective é identificar e planejar melhorias na forma como a equipe Scrum trabalha. Durante a retrospectiva, a equipe revisa o Sprint anterior e discute o que funcionou bem e o que pode ser melhorado. Com base nessas discussões, a equipe identifica ações concretas para melhorar seu processo de trabalho e aumentar sua eficiência. As outras alternativas estão incorretas, pois a revisão e aprovação do trabalho da equipe de desenvolvimento é feita durante a Sprint Review, a inspeção do incremento e adaptação do Product Backlog é feita durante a Sprint Review e a planificação do trabalho a ser feito na próxima Sprint é feita durante a Sprint Planning.

0
Dislike0

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais