Baixe o app para aproveitar ainda mais
Prévia do material em texto
ITEM: 9 PAGE: 1 REPORT TO: POLICY & RESOURCES COMMITTEE ON 7 JUNE 2016 SUBJECT: PROJECT MANAGEMENT GOVERNANCE POLICY BY: CHIEF EXECUTIVE 1. REASON FOR REPORT 1.1 This report presents the Council’s new approach to project management and associated administration. It describes the proposed corporate approach to project management governance and provides assurance to Elected Members that processes and controls are in place to ensure successful project delivery within the Council. 1.2 This report is submitted to Committee in terms of Section III A (2) and (42) of the Council's Scheme of Administration relating to managing the finances of the Council and the organisation and management processes of the Council. 2. RECOMMENDATIONS 2.1 It is recommended that the Committee approves the: (i) implementation of a corporate Project Management Governance Policy for managing projects; and (ii) funding of £35,000 from Reserves for training as detailed in paragraph 7.3 of the report. 3. BACKGROUND 3.1 On 25 May 2016, Full Council approved the establishment of a small dedicated Programme Management Office (PMO) team to support and administer appropriate projects and programmes (paragraph 7 of the draft minute refers). The report also referred to an associated draft policy to ensure there are consistent standards and disciplines applied to all projects and programmes. ITEM: 9 PAGE: 2 4. THE PROJECT MANAGEMENT GOVERNANCE POLICY 4.1 A key responsibility of the PMO is the ownership and administration of the corporate Project Management Governance Policy (The Policy). A copy of The Policy is attached at Appendix 1. The Policy provides a framework for accountability and responsibilities, ensuring that project decision making is robust, logical and that projects provide value to the organisation. It offers a mechanism for ensuring that accurate and appropriate project status reports are presented regardless of the Service running the project or the type of project. 5. RESPONSIBILITIES 5.1 A core principle that applies for all projects, irrespective of the delivery methodology and terminology used, is that of accountability and responsibility. The point of accountability for a project is the Director of the Service that is leading on the project. Responsibility for ensuring that the project runs in compliance with corporate policy sits with the Project Sponsor (also referred to Senior Responsible Officer (SRO)). For construction projects, this role is sometimes known as the Project Owner - but the responsibilities are the same. It is acceptable for the Director to also have the role of Project Sponsor. The PMO will support all accountable and responsible officers. 5.2 The governance hierarchy, as shown in the diagram below, outlines the flow of reporting and decision making. The PMO will support this process. The hierarchy is based on existing high-level governance arrangements as there seems to be little benefit in creating a new structure. Instead, the roles of the various bodies will be defined more clearly. The exception is the Transformation Programme Board which replaces the defunct DBS Programme Board. 5.3 Each programme will comprise of component projects. Each project will have a Project Board. The Project Sponsor/SRO is responsible for setting up and chairing the Project. The Project Sponsor/SRO must ensure that all the responsibilities assigned to the Project Board are met. Whilst these responsibilities may be devolved to the Project Manager, accountability remains with the Project Sponsor/SRO. The resource, grade and knowledge associated with each role will vary depending on the project. The corporate PMO will support all roles. 5.4 The Project Board will provide assurance to the relevant higher level Programme Board that appropriate risk mitigation plans are in place for all project risks, regularly monitor the viability of the mitigation and report any exceptions. The PMO will facilitate this process. ITEM: 9 PAGE: 3 6. PROCESS 6.1 A critical element of The Policy is the Gateway Process. Abbreviated Gateway formats are already used by ICT, Procurement and the Asset Management Group. The process is built on the following elements: i. Key Principles - the basic rules that affect all projects during the project life cycle. The 6 major stages of a project lifecycle – Conception, Definition, Initiation & Planning, Delivery, Closure and Post Project Review. ii. Structure, Accountability and Responsibilities - who does what and what role they play in project governance. iii. Governance process (Gateways) - defines the trigger points for mandatory governance checks on project status and the evidence required for governance approvals. iv. Project Reporting and Standard Processes – defines the reporting requirements and the acceptable way of working within the governance framework. ITEM: 9 PAGE: 4 v. Prioritisation - doing the right projects recognising the organisation’s capacity constraints to undertake the work. vi. Capability - It creates the environment to do the selected projects and programmes right and the development and maintenance of an effective capability. vii. Continuous Improvement - to validate the usefulness and efficiency of the ongoing work which feeds back into the selection and capability aspects of governance. 6.2 Although the key principles are seen as best practice for all projects, in order to not stifle through bureaucracy the process will apply specifically and will be enforced for: Requires significant capital or revenue investments – significant investment means having a value of £1M or more over the lifecycle of the project; or Projects whose implementation exhibits a high level of complexity, ambiguity, tension, uncertainty or risk as identified during categorisation in accordance with Appendix 4; or Projects that are forecast to deliver substantial cost savings as identified by the Council’s Corporate Management Team (CMT). 6.3 All projects are categorised as Basic, Intermediate or Strategic. The category determines the process, governance and reporting requirements. The criteria to be considered for categorisation are Corporate Impact (including £ value) and Complexity. Projects will be rated against each factor using a low/medium/high rating. 6.4 The information required for each stage of the process is determined by the category of the project. The table below outlines the documentation required at each gateway for intermediate and strategic projects. Concept………………………...”Project Life Cycle”………………….Closure ITEM: 9 PAGE: 5 6.5 For clarity and to help understanding, definitions of a project, programme and programme management are detailed below (APM Body of Knowledge, 6 th Edition): A Project is a unique, transient endeavour, undertaken to achieve planned objectives, which could be defined in terms of outputs, outcomes, benefits or strategic objectives. o Outputs - are the tangible or intangible products typically delivered by the project. o Outcomes – are the changed circumstances or behaviours that result from the use of an output A Programme is a group of related projects and change management activities that together achieve beneficial change for an organisation. Programme Management is the coordinated management of projects and change management activities to achieve a beneficial change. 6.6 To further help address any ambiguity defininga project, the table below helps identify the key differences between a Project and “Business As Usual” (BAU): Project Business As Usual Unique Revolutionary Temporary Specific objectives for change Involves uncertainty Special team Dynamic environment Repetitive Evolutionary On going Based on experience Established/experienced personnel Stable environment 7. STANDARDS 7.1 For specific projects assessed as intermediate or strategic, there needs to be an agreed programme and project management standard. The adoption of a standard and shared approach helps develop a corporate understanding. The Office of Government and Commerce (OGC) Prince2 © and Managing Successful Programmes © standards were used for the DBS programme. 7.2 This also applies to other facets of project administration and organisation including administration processes, analysis, change techniques and compliance with local policy and procedures (eg Risk Management). The table at Appendix 2 below outlines the recommended standards. 7.3 Training and skills development will be co-ordinated by the PMO. An assessment of the training needs/standards confirms that the requirement can, in the main, be developed and delivered by council specialists and internal training teams reducing the need for external providers. However, accredited training and ITEM: 9 PAGE: 6 specialist input will still require external input. The cost of training for the first year is estimated to be £35K. This is forecast to reduce for subsequents years. 8. SUMMARY OF IMPLICATIONS (a) Moray 2026 - A Plan for the Future/ Service Plan The policy will aid the successful delivery of the Corporate Plan; Moray Integrated Joint Board’s Strategic Plan and Moray Community Planning Partnership’s Moray 2026 – A Plan For the Future. (b) Policy and Legal The Project Management Governance Policy will will reinforce compliance and improve performance, productivity and efficiency. (c) Financial Implications A revenue budget of £35K is required to funds the skills development and specialist training aspect of the policy. (d) Risk Implications The risk of not approving the proposals in this report is continuing to employ ad hoc arrangements to the management and delivery of the projects and programmes and therefore not delivering the improvements and achieve the required savings. (e) Staffing Implications There are no staffing implications. (f) Property (g) There are no property implications. (h) Equalities There are no equalities issues contained in this report. (i) Consultations The Corporate Management Team (Tier 1), Senior Management Team (SMT); Leadership Forum (Tiers 1-3) have been involved in the compilation of this report. Comments have been incorporated and there is agreement with the content. ITEM: 9 PAGE: 7 9. CONCLUSION 9.1 The implementation of a new corporate approach to project management will bring control and discipline to high risk, large investment and complex efficiency projects. It has been developed using existing best practice and lessons learnt from other local authorities. It provides a framework for the Council to work within. It defines roles, responsibilities, procedures and controls with the aims of enhancing successful project delivery. Author of Report: David Morris, Senior Programme Manager - 3801 Background Papers: Held by author (DBS SharePoint) Appendix 1 The Moray Council: Project Management Governance Policy Framework for Project Sponsors, Project Boards, Senior Management and Elected Members. Document Details & Version Control Author: D Morris Action: Draft for consultation Version: v.01 Date: 27 April 2016 D Morris Amendments: Property (EM), Finance (LP) & Training (MK) comments. v.02 29 April 2016 D Morris Amendments: Procurement (DB), Consultancy (DG), Ex DBS PMO (MA) & Property (MM) comments. v.03 09 May 2016 D Morris Final. For approval V1.0 10 May 2016 ITEM: 9 PAGE: 9 1. Introduction – Projects Defined 1.1 This policy defines a framework for the governance of project management within the Moray Council (TMC). It stipulates standard processes and governance requirements. It is based on the Prince2 Project management methodology, aligned with the Scottish Government Construction Procurement Manual and the Office of Government Commerce (OGC) Gateway framework. Projects involving procurement will also follow the standards set out in TMC Financial Regulations (Procurement Procedures). It builds on existing processes and guidance in use within the Council and intends to re-use existing controls where they have been shown to be effective. It will be subject to full review after 12 months of publication so that any improvements / lessons learned from initial implementation can be incorporated. 1.2 There are differences in the management and governance arrangements between capital projects (Property and Infrastructure) and other projects, for instance due to the specific requirements for construction projects such as the Construction (Design and Management) Regulations 2015. The framework is intended to cover all circumstances with the flexibility to adapt the principles to suit the scale and type of project. 1.3 The framework is designed to ensure that the right environment for project success is created within the Council. It will define structures and processes that will ensure that projects are managed well and in accordance with this framework’s key principles; that projects are aligned to the Council’s strategic objectives, and that any projects exhibiting conditions of failure are identified on time and appropriate corrective and mitigating measures are put in place. 1.4 Project management governance provides a framework for accountability and responsibilities, ensuring that project decision-making is robust and logical and that projects provide value to the organisation. It offers a mechanism for ensuring that projects are conceived and implemented in accordance with agreed standards and regulations. 1.5 A Project, within TMC context, is defined as: A unique, transient endeavour, undertaken to achieve planned objectives, which could be defined in terms of outputs, outcomes, benefits or strategic objectives. o Outputs - are the tangible or intangible products typically delivered by the project. o Outcomes – are the changed circumstances or behaviours that result from the use of an output. The decision to implement a planned piece of work as a project is the responsibility of Corporate Directors and the decision must be informed by the category given to the project as described at Point 5.1. 1.6 For the purpose of this policy, governance could be applied at a programme level if felt to be appropriate by the Corporate Director. A Programme, within TMC context, is defined as: A group of related projects and change management activities that together achieve beneficial change for an organisation. This would mean, for instance, that a programme consisting of a number of projects across Moray could be treated as one entity under this policy, meaning that the policy would not have to be separately applied for each individual project within the programme. 1.7 Whilst the standards and processes articulated in this document are seen as best practice for all projects within the organisation, compliance will onlybe enforced and monitored for projects that: Requires significant capital or revenue investments – significant investment means having a value of £1M or more over the lifecycle of the project and any resulting contract/s as set out in the TMC Procurement Strategy (Procurement Procedures). “Strategic” projects whose implementation exhibits a high level of complexity, ambiguity, tension, uncertainty or risk as identified during categorisation in accordance with Appendix 4. ITEM: 9 PAGE: 10 Projects that are forecast to deliver substantial cost savings as identified by the Council’s Corporate Management Team (CMT). 2 TMC Project Management Governance Principles 2.1 To provide an appropriate level of proportional and consistent governance across the Council, the project life-cycle and associated processes are underpinned by the following key principles: 2.1.1 Accountability and Responsibility: A single point of accountability will exist for all projects within a Service area. This point of accountability will be the aligned Corporate Director, while responsibility for ensuring that an individual project is run in compliance to this framework lies with the Project Sponsor (also referred to within TMC as Senior Responsible Officer (SRO)). It is acceptable for the Director also to be the Project Sponsor. The practical application of the framework and the actual management of the project will be undertaken by a suitably trained/qualified Project Manager. 2.1.2 Openness and Transparency: Project performance will be visible across the different levels of governance, and reporting will be consistent, with a minimum data requirement set for all project status reports. 2.1.3 Financial Management and Cost Transparency: All projects will adhere to the Council’s Financial Regulations. Whole life-cycle costs will be estimated for all projects, including internal staff costs, and updated cost information will inform the business case and the tender process. Changes to baseline costs will be documented. 2.1.4 Conduct of Procurements: All procurements carried out either as the key objective of a project or as a subsidiary activity must be carried out in accordance with TMC Financial Regulations (Procurement Procedures). 2.1.5 Continued Business Justification: The project Business Case in the case of change projects, and the Quality Plan (suite of technical specifications and plans) in the case of infrastructure projects, will be updated and reviewed at key decision points. Projects will only progress if the viability of the Business Case or Quality Plan is confirmed and assumptions validated. 2.1.6 Technically assured and well managed projects: All projects will be supported by sound technical and specialist advice and managed by suitably qualified and experienced Project Managers supported by appropriate project teams. Projects involving procurement will be supported by a lead Procurement Officer. When applicable, adequate feasibility studies will be completed with robust scoping and where a reference site is used, comparison will be based on requirements and accrued benefits. 2.1.7 Risk Management: All projects will have a well-defined risk and issues management strategy and a consistent approach to risk and issues reporting. 2.1.8 Well-defined roles and responsibility: Roles within projects will be well defined with training and support provided to ensure that obligations under this framework are understood and embedded within projects. It is compulsory for all members of Project Boards and all Project Sponsors to complete a training session on this framework before serving on a Project Board. For projects involving procurement, all those involved in the procurement activities must also have current procurement authorisation at the appropriate level and have had the necessary procurement training. 2.2 Supporting these principles are the monitoring checks and processes defined by this framework. These checks are carried out through a number of decision points that are based on the OGC Gateway framework. These check-points and processes are described in Section 5.0. 2.3 These checks and processes will ensure that the right environment and culture for project success is maintained across the Council with emphasis on three key project variables – the quality of the project deliverables and benefits (scope), the overall cost of the project, and the project time-scale. ITEM: 9 PAGE: 11 3 Project Life-cycle 3.1 All projects regardless of complexity, scale or subject do share common features that allows for the design of a generic life-cycle. This life-cycle shows the different stages that projects progress through and are used as mandatory governance checkpoints. 3.2 The project life-cycle will have 6 stages; Conception, Definition, Initiation & Planning, Delivery, Closure and Post Project Review. These stages apply to all transformational saving projects, capital projects (property and infrastructure), ICT projects and other services-led projects within the Council. To steer a project through the project life-cycle, a Project Board must be assigned to manage the project – this is either done by forming a new Project Board or by assigning the project to an existing Project Board with relatable project objectives. 3.3 The full make-up of a Project Board under Prince2 is described in Appendix 1, but there will be situations where a Project Board consisting of just a Sponsor and Project Manager/Procurement Lead will be sufficient. It is the responsibility of the Project Sponsor to ensure that the make-up of the Project Board adequately reflects the requirement for good project control but at the same time is not disproportionate to the scale of the project. 3.3 Conception is the stage at which an idea is created or a need (a requirement for change) is identified and a strategic decision is made as to whether or not it should be pursued. 3.4 Definition involves a full exploration of the change requirement and the development of the associated business case; the scope for the project is considered and procurement approaches investigated. 3.5 Initiation and planning – A full plan for implementing the change is created and a contract or contracts awarded to any 3rd party suppliers as a result of commercial competitions carried out as part of the project. This is the Production Information and Tender stage for capital project procedure. 3.6 Delivery – This is the implementation stage for the project, where the project objectives are delivered and responsibility handed over from project to the business. 3.7 Closure – the project is drawn to a close and a review is carried out to confirm if there are any deliverables that have yet to be delivered and to formally end the project organisation. 3.8 Post Project Review – this is the stage at which the project is reviewed to confirm achievement of expected benefits and to ensure that lessons learned are identified and propagated through the organisation. 3.9 A diagrammatic representation of the project life cycle is shown below with the appropriate documentation and governance objectives for each stage: ITEM: 9 PAGE: 12 Diagram 1 - Project Life Cycle 3.10 Current Capital project life-cycle matched to the generic project life-cycle: Diagram 2 - Project Life Cycle matched to Capital Project Life-cycle. 4 Governance Structure and Responsibilities 4.1 The governance structure is a hierarchical arrangement of lines of accountability for project governance within the Council. It shows how information about the management of a project’s status, risk and issues flows between the different levels of responsibility. 4.2 CorporateDirectors through Service Management Teams (SMT) or, where in place, existing high-level Governance Boards (HGB) will act as the single point of accountability for all projects within that Service. 4.3 Whilst overall accountability for enforcing/ensuring compliance rests with the Corporate Director/High-Level Governance Boards (HGB) and/or Service Management teams, responsibility is devolved to the Project Sponsor and the Project Board for each project. 4.4 Service Directors will ensure that an appropriate report is forwarded to the relevant Strategic Committee. These triggers are defined in Section 5. 4.5 The diagram below shows the full reporting structure for project management governance within the Council: ITEM: 9 PAGE: 13 Diagram 3 - TMC Project Management Governance Structure 4.6 For construction projects, the project management team structure defined within the Scottish Government Construction Procurement Manual will apply, with the “Project Owner” (also referred to within TMC as Senior Responsible Officer (SRO)) responsible for ensuring that the level of governance defined within the Council project management governance framework is implemented. Table 1 below maps the roles within the Scottish Government Construction Procurement Manual to the Council’s Project Management Governance Framework. Appendix 2 shows the full project team structure for the Scottish Government Construction Procurement Manual. Project Management Governance Framework Policy Roles Scottish Government Construction Procurement Manual Roles Moray Council Terminology Strategic Committees Investment Decision Maker Corporate Director/High-level Governance Board (HGB) Investment Decision Maker Project Sponsor Project Owner Senior Responsible Officer (SRO) Project Board members Project Manager Senior Supplier Senior User Project Board members Project Manager Project Sponsor Service User Representative Client Technical assurance – Service level implementation Client Adviser Client Project Team – Service level implementation (not defined within framework) External consultant Project Manager / Consultants / Contractors / Supplier Table 1 – The Scottish Government Construction Procurement Manual roles within TMC Project Management Governance structure. 4.7 Governance Responsibilities. This defines the governance responsibilities at the different layers of the governance structure: ITEM: 9 PAGE: 14 4.7.1 Elected Members – Strategic Committees a) The Strategic Committees will authorise the investment decision of appropriate projects in accordance with TMC Financial Regulations. b) The Strategic Committees will provide independent and objective scrutiny of projects that are forecast to go above the defined tolerance level (typically 10%), ensuring that sound financial decisions are made. c) They will receive regular monitoring reports from Corporate Directors and will scrutinise the reports to confirm that project/programme benefits are delivered within budget and timescale. 4.7.2 Corporate Directors/ High-level Governance Boards a) Corporate Directors serve as the single point of accountability for their assigned projects. The High-level Governance Boards (HGBs) provide scrutiny and application of the governance process. b) Current High-level Governance Boards are: Asset Management Group (AMG): chaired by the Corporate Director (Corporate Services) – responsible for ensuring the governance framework is applied for all capital projects and programmes within the capital plan. Service Management Teams (SMT): Chaired by individual Corporate Directors – responsible for ensuring the governance framework is applied to all Service-led projects. ICT Programme Board – chaired by the Head of Service (HR/ICT) – responsible for ensuring the governance framework is applied for all ICT projects and maintenance programmes. Joint (Health & Social Care) Integration Programme Board (JIPB) – chaired by the Chief Officer (Health & Social Care) – responsible for ensuring the governance framework is applied for all integration projects. c) New High-level Governance Boards are: The Project Initiation Board (PIB) – chaired by Corporate Director (Corporate Services), it will provide an initial strategic assessment of all project mandates ensuring that a project fits into the strategic and operational objectives of the Council, that it is not a duplication of work and that there are sufficient resources within the organisation to undertake the project. Transformation Programme (TPB) Board: chaired by the Chief Executive - responsible for ensuring the governance framework is applied for projects that fall within the efficiency programme. d) The HGBs will provide governance assurance to the Strategic Committees – so that elected members can be assured that current and proposed projects have embedded the structure and processes defined within this framework. e) The HGBs will review project monitoring reports, confirming that there is continuous business justification for the project and will authorise gateway progression through the project life-cycle as necessary. f) The HGBs will review and authorise project variables and re-baseline recommendations from the Project Sponsor. (Re-baselining is when a remedial action has been taken to change the baseline figure of one or ITEM: 9 PAGE: 15 more of the variables of a project; for example when the delivery time-scale is changed to account for a revised implementation date.) g) The HGBs will provide support and advice in resolving issues and in implementing mitigations against risks. This may include providing independent assurance to Project Boards. h) Make decisions on tolerance levels. 4.7.3 Project Sponsor: a) The Project Sponsor makes decisions with regard to management of the project. The Project Sponsor owns the business case and is responsible for providing continuous justification of the business case or quality plan to the HGB. b) Responsible for providing project status reports and exception reports to the HGB; making recommendation for gateway progression to the HGB. The recommendation will be supported by a stage report and a completed checklist (See Appendix 3) to show that all aspects of the project variables have been considered before a recommendation is made to the HGB. c) Work with the Project Board to ensure that proposed benefits are accrued and evidence of such benefits is captured. d) Makes recommendation on the re-baselining of project’s variables and demonstrate the astuteness of re- baselining. e) Own the risk mitigation plans and project objectives. f) Ensure that a suitably trained Project Manager is assigned and that there are appropriate resources to deliver the project. 4.7.4 Project Board: a) The Project Sponsor is responsible for setting up and chairing the Project. The Project Sponsor must ensure that all the responsibilities assigned to the Project Board are met. b) Whilst these responsibilities may be delegated to the Project Manager, true responsibility remains with the Project Sponsor. c) The Project Board will provide assurance to the relevant HGB that appropriate risk mitigation plans are in place for all project risks, regularly monitor the viability of the mitigation plan, and report any exception to the HGB. d) The Project Board will provide assurance to the HGB that the financial management of the project is within tolerance and report changes to baseline figures to the HGB. e) Seek technical assurance from the appropriate Service specialist team for theproject to ensure that proposed technical solution fits into the Council’s strategic goals. f) The membership of Project Boards will be only for officers that have completed the mandatory training course (to be developed) and ideally have experience. Project Boards may also have supplier representation when the supplier has been contracted to act as an agent for the Council or to provide specific advice relating to the requirements. The Sponsor is responsible for ensuring that they understand their role on the Project Board. ITEM: 9 PAGE: 16 5 The Governance Process – Governance Checkpoints 5.1 It is the responsibility of Corporate Directors to ensure that all change initiatives within their Service are assessed against the criteria set in Section 1.7. If a change initiative is not run in accordance with the policy, the rationale must be evidenced as to why not. The impact/complexity categorisation matrix is at Appendix 4. 5.2 The governance process provides the mechanism for the project management governance to exercise its responsibilities under this framework. The process is designed to confirm governance compliance during the key decision-making points within the project life-cycle. The principle is that these decision-making points are seen as gateways that are shut, and have to be proactively opened before a project can move forward. This is based on the OGC Gateway framework. Diagram 4 below is an overview of the process. Diagram 4 – Governance Process (High Level) 5.3 There are 5 gateway points (G1 to 5) - the expectation for each gateway is specified in the Table 2 below. It is expected that the Project Board through the Project Sponsor will provide the required evidence to the HGB to demonstrate that the project is ready to progress through the gateways, and as a minimum in procurement projects the Sponsor/Board must approve the business case, project plan, strategy, and tender board report. OGC Gateway Descriptions Project Lifecycle Stage Evidence provided to the Project Initiation Board (PIB) / High-Level Governance Board (HGB) Outcome Gateway 1 (G1) Strategic Assessment and Business Justification. Project Initiation Board (PIB) Conception Evidence showing that a Mandate has been developed – to show the justification for the project; the scope, objectives, timeframe and timescales and initial estimates of costs and benefits. Completed Gateway 1 checklist – see Appendix 3 Approval to fully investigate and define the project. Align to appropriate HGB. ITEM: 9 PAGE: 17 Gateway 2 (G2) Delivery Strategy. High-Level Governance Board (HGB) Conception Evidence showing that an Outline Business Case has been developed – to show the justification for the project; the scope, objectives, timeframe, options, timescales, risks assessment, estimates of costs and benefits. Completed Gateway 2 checklist – see Appendix 3 Approval to fully investigate and define the project. Gateway 3 (G3) Investment Decision. High-Level Governance Board (HGB) Definition Evidence showing that assumptions in the Outline Business Case have been validated and a Full Business Case has been produced – showing requirements specification (quality), cost, timescale, results of pre-market research, risks and issues and a procurement strategy. For infrastructure projects, evidence showing that a Quality Plan has been created and estimated project cost have been provided. Evidence that the Project Sponsor has nominated a Project Board. Evidence that nominated members of the Project Board have received formal training on the Council’s Project Management Framework Policy Completed Gateway 3 checklist – see Appendix 3 Approval to start pre- market activities and create project implementation plan. Gateway 4 (G4) Prepare for delivery. High-Level Governance Board (HGB) Planning and Initiation Evidence showing that a Project Initiation Document (PID) has been completed and assumptions in the Full Business Case have been clarified and validated where necessary. For infrastructure projects, evidence showing that the Quality Plan has been reviewed – with project cost updated and that design review frequency has been agreed and verification plan is in place. Evidence showing that the project cost model and other assumptions has been reviewed. Where applicable, payback period and Return on Investment (RoI) strategy agreed. Evidence showing that risk and issues management approach has been Approval to award contract and begin implementation of project delivery. ITEM: 9 PAGE: 18 agreed. Evidence of completion of appropriate competition via a tender board report. Completed Gateway 4 checklist – see Appendix 3 Gateway 4a (G4a) Project Commencement High-Level Governance Board (HGB) Delivery On-going process. Evidence showing that the project is progressing within tolerance and that risks and issues are being managed. Evidence showing that the business case has been reviewed and updated and project cost model is still valid. Evidence showing that risk and issues management strategy is working. Evidence showing that project is delivering milestones. For infrastructure projects, evidence showing that the Quality Plan has been reviewed and that design review is progressing as planned and project budget is within tolerance. Completed Gateway 4a checklist – see Appendix 3 Approval to go live / proceed. Gateway 5 (G5) Operational Review & Benefit Realisation High-Level Governance Board (HGB) Closure / Post Project Review Evidence showing that the project has delivered the key deliverables and immediate benefits are been realised. Lessons Learned. Evidence confirming that longer term project’s benefits have been delivered. Completed Gateway 5 checklist – see Appendix 3. Approval to close project and commence post project review / benefit realisation Table 2 – Mandatory Governance Checkpoints 5.4 Information will be passed up the governance structure through Project Status Reporting; these reports will be triggered by the mandatory check-points in the governance process and by exception when a project is forecast to exceed a defined tolerance level. 5.6 Mandatory trigger points for reports to committees are before check-point G3 – project definition stage and check-point G5 –post project reviews. 5.7 Exception reports will be triggered by the following conditions – • Explicit request from Strategic Committees; • Explicit request from Audit and Performance Review Committee; • If there is a significant (above 10%) increase in initial cost estimates between the G3 and G4 review. ITEM: 9 PAGE: 19 • During the Delivery Stage when a project is forecast to exceed defined tolerance level in respect of time or benefits to be delivered. 6 Project Status Reporting 6.1 Project Status Reporting provides the monitoring and control functions that enable the critical assessment of the ongoing viability of the project and reports on the overall progress of the project. 6.2 It defines how the overall status of projects, risk and issues are communicated across the governance structure. 6.3 The Project Sponsor is responsible for providing project status reports to the HGB. The Corporate Directors are accountable for providing reports to Elected Members while the Project Sponsor is responsible for generating the report. 6.4Reports to Elected Members will be provided prior to mandatory check points G3 and G5 and when tolerance levels are forecast to be exceeded. Check points are as described in Section 5 of this framework. Project Sponsors will be expected to raise exception reports between gateway points when required. 6.5 Project Sponsor will provide project status reports to the HGB at every check-point and will provide exception reports when a project requires remedial action or when a project overall RAG status is RED. The report will be circulated to members of the HGB 3 days before a HGB meeting. 6.6 The Project Manager will provide regular project status reports to the Project Board. 6.7 A project status report regardless of gateway point will contain the following minimum dataset: • Project Life-cycle Stage • Project current Gateway • Over-all Project RAG status • Project Risk RAG status • Project Issue RAG status • Statement of validation of business case or quality plan • Milestones update • Financial update • Risk and issues update • Changes and comparison to original baseline figures • Changes to original impact assessments. • Project Sponsor name and official designation • Project Sponsor Recommendation 6.8 If a project status report fails to provide the minimum dataset, then the report will be considered as in- complete and the Project Sponsor would be require to re-submit the report with the missing data. 6.9 All project status reports will be accompanied by the appropriate stage checklist (See Appendix 3) e-signed by the Project Sponsor, confirming that due diligence has been completed for key aspects of the project. 6.10 If, after going through a check-point, any changes to baseline figures outside of the agreed tolerance levels of the project would require a new gateway review for the current gateway. 6.11 BRAGG Definitions: ITEM: 9 PAGE: 20 6.11.1 Black, Red, Amber, Green, Grey (BRAGG) provides an expanded traffic light visual representation of the current state of a reported item against the current baseline. Black denotes “complete” whilst Grey is “not started”. The overall purpose of a Red, Amber, Green (RAG) status is to indicate the level of attention and the action required at a particular point in time. RAG definition will be applied and be reported separately for the overall project status, project risk management and for project issues. 6.11.2 Overall RAG status must generate consistent response across all projects within the Council, hence the overall RAG system has been defined against expected responses. 6.11.3 The overall RAG status for a project must be a cumulative of the RAG statuses of three areas of project objectives – quality (scope), cost and time. Hence a project can’t be RAGGED green if any of the three variances are RAGGED at any other colour. The project would be RAGGED with the worst RAG status. 6.11.4 Project risks are to be RAGGED against the level of control that the Project Board have on the mitigation plan. This will be based on the standard Red, Amber and Green levels. For clarity, risk can be defined as an uncertain event or set of events, which should it/they occur, will have an effect on the ability to deliver a project. Refer to Section 7.5 for more details. 6.11.5 Project issues are to be RAGGED against implementation of a resolution i.e. an indication of whether issues are under control or not. This will be based on the standard Red, Amber and Green levels. For clarity, issues are unplanned events or conditions that have already happened or are currently happening and that have impacted or are currently impacting on the objectives of the project. Refer to Section 7.5 for more details. 6.11.6 RAG definition for OVERALL Project Status and expected response: RAG Status Quality (Scope) Cost Time Response Red Deviation imminent or has occurred on the agreed project objectives and scope. Imminent increase above the 10% tolerance threshold on the estimated project cost for that particular milestone or for the whole project. Project on course to miss milestones delivery dates or projected closure date. Project Sponsor to escalate to High-Level Governance Boards (HGB) with an Exception Report. HGB to inform appropriate strategic committee if committee level tolerance threshold are broken. High level remedial action required and discussion with the Service Director for the appropriate action. Amber Likely imminent deviation from the agreed project objectives. Likely imminent increase on estimated project cost for that particular milestone delivery or for the whole project. Likely imminent issues with delivery timescale; a milestone date may be missed. Raise awareness with HGB. Project Board to take remedial action. Project to be monitored and project’s critical path reviewed. Project Board to start remedial action. ITEM: 9 PAGE: 21 Project Board to review assumptions on business cases, cost benefit report and review project’s critical path and analyse impact. Green No deviation expected from the project objectives No deviation expected from the estimated project cost. No issues with timescale; current project milestone will be delivered in time. No action required. Table 1 - RAG Definitions for Project Status Reporting 6.11.7 RAG definition for RISKS measured against Council’s control of the mitigation plan. RAG Status Description Response Red No mitigation plan in place or the Project Board has zero control over the mitigation plan or no control over key critical paths of the project or mitigation plan is unknown because the mitigation information is not available. Project Sponsor/Board to engage with stakeholders, re-assess the project’s critical pathways and identify contingency plans. Update risk register accordingly. Project Sponsor to escalate to HGB. Amber Mitigation is partly in place but does not cover end to end management of the risk as the Project Board does not have “managed control” of all aspects of the risk. Project Sponsor/Board to engage with stakeholders, re-assess the project’s critical pathways and identify contingency plans. No escalation required. Update risk register accordingly. Green Mitigation plan in place and all aspect of the risk can be control by the Project Board. Continue to monitor the risk and update risk register accordingly. Table 2 - RAG Definitions for Project Risks reporting 6.11.8 RAG definition for ISSUES measured against resolution RAG Status Description Response Red No resolution identified yet or resolution has impact on business case. Escalate to the HGB. Project Sponsor/Board to engage with stakeholders, re-assess the project’s critical pathways and business case. ITEM: 9 PAGE: 22 Service Director to consider Exception Report for Strategic Committee. Amber Resolution identified but problem with implementation. Project Sponsor/Board to engage with stakeholders Escalate to the HGB. Green Resolution identified and implementation in progress. Project will be able to proceed soon with limited impact. Maintain on Project Log and monitor as on-going. Table 3 - RAG Definitions for Project Issues reporting 6.11.9 RAG Status on re-baselined Projects a) Re-baselining is when a remedial action has been taken that changes the baseline figures of one or more ofthe variables of a project; for example when the delivery timescale is changed to account for a revised implementation date or if there is a project cost increase with budget increase agreed through the relevant HGB or Strategic Committee. It is essential that the RAG status thereafter reflects these changes. b) A new RAG status reflecting the current state of the project metrics measured against the new baseline value is to be reported. However, in order to provide a complete project life-cycle view, all re-baselined projects are to be reported on a table – showing original baseline values against new baseline values and the date that the new baseline was applied. c) This table will form part of the report to the HGB and relevant committee. The report would show the original baseline figure. 7 Standard Processes 7.1 These processes have been defined to help implement the key principles within this framework consistently across the Council. 7.2 Requirements Specification and Benefit Mapping: 7.1.1 Requirements Specification (training requirement to be developed) is the capturing and documenting of what a project is meant to achieve or deliver. It is the key to aligning project objectives to the benefits that the business is seeking. Failure to specify requirements accurately is one of the known high risks to project success. 7.1.2 A comprehensive Requirement Specification document requires consultation with all key stakeholders: - this can be achieved via benefit-mapping workshops using the Benefit toolkits (training to be developed) or via requirement workshops with stakeholders. For procurement projects a User Group will be set up to define the requirement, procurement strategy for the project and to develop supplier selection and contract award criteria. 7.1.3 The requirement specification process will take place at the Project Definition stage helping to inform the outline business case and forms one of the key metrics for measuring benefit accruals. 7.1.4 The process will help understand the requirements of the Service; it will help define the scope of the project and help identify potential dependencies. The final outcome is a Requirement Specification document. ITEM: 9 PAGE: 23 7.1.5 The Requirement Specification document must always specify a minimum viable product/outcome that will deliver the desired benefits. This can be a functional product or a quantifiable benefit like cost-saving or performance improvement. 7.1.6 A clear link between business requirements and functional requirements must be documented as this helps validate the minimum viable product/outcome description. Functional requirements describe specific tangible functionality of a product. 7.1.7 It is recognised that most projects require a procurement exercise so the corporate procurement team must be involved at Gateway 2 (G2). In the case of capital projects (property and equipment/infrastructure), corporate standards relating to procurement will apply. 7.1.8 Technical requirements must be validated by Service-based technical advisory groups where available. 7.2 Development of Full Business Case/Quality Plan: 7.2.1 The Business Case is the business justification for a project. It demonstrates why and how the requirement specification will help us meet a business need. No project should commence without a business case or quality plan in the case of infrastructure projects. Quality Plan is a suite of documents capturing the approach to specification and delivery of an infrastructure project (scheme). 7.2.2 Business Case/Quality Plan captures information on expected benefits/deliverables and estimate cost of delivering the benefits/deliverables. 7.2.3 The Business Case is owned by the Project Sponsor and updated throughout the project so as to confirm the continuous viability of the project. 7.2.4 A Mandate and Outline Business Case (OBC) are created at the Project Conception and Definition stage with several assumptions made. Validation of these assumptions and dependences must be completed before a full Business Case is signed off by the Project Board. For Infrastructure projects, a Quality Plan will serve the purpose of a Business Case within this framework. 7.2.5 The Business Case is reviewed at every gateway by the HGB and its validity confirmed in line with the principle of continuous business justification. Hence a Business Case will only be deemed valid until the date of a checkpoint. This applies to Quality Plan in that it is only valid until the next design review date. 7.3 Project Financial Management 7.3.1 Project financial management looks at the management of the financial aspects of a project. It covers the management of the project’s budget; spend profile and the management of the procurement of deliverables within the project. 7.3.2 The Project Sponsor has overall responsibility for the financial management of the project and must ensure compliance with TMC Financial Regulations. 7.3.3 The Project Sponsor must ensure that a business case has been established. This should examine all of the possibilities for meeting the Requirements Specification. In respect of projects with a value in excess of the OJEU tendering threshold, the Sponsor will be supported by a lead procurement officer. 7.3.4 The Project Sponsor will provide assurance that the cost model on which financial and budgetary assumptions about the project is based has been validated. This assurance will be provided through continuous validation of the business case at every governance decision check-point. The assurance reviews will be ITEM: 9 PAGE: 24 documented, with decisions recorded, and will be undertaken by the HGBs. For significant projects, an HGB may consider an external independent project review to be necessary. 7.3.5 The cost model will cover the whole life-cycle cost of a project; including the cost of project management products, staff costs, contractors/suppliers cost, finance costs, efficiencies and income. 7.3.6 Where a project is funded from an external non-Moray Council fund, the Project Sponsor will ensure that the terms and conditions of such funding does not negate the principles of the Council’s financial regulations. 7.3.7 Where project funding and implementation involves “arm’s length external organisations” or Community partnerships group or external grant, the Council’s Financial Regulations shall take precedence over all other arrangements. 7.3.8 At mandatory decision check-points – Gateways 3 and 5 - the Project Sponsor will provide reports to the HGB and to the appropriate Strategic Committee identifying the proposed source of funding for a project and the estimated cost. If the project cost is forecast to increase for more than 10% at any point, then the Project Sponsor will seek approval from the Strategic Committee to incur the increase. 7.4 Project Procurement 7.4.1 The Council’s procurement regulation is applicable to all project procurement exercises and it is as contained within Financial Regulations (Procurement Procedures). This provides an appropriate reference to all procurement matters. 7.4.2 Project Sponsors must ensure that all members of the Project Team and Boards have undergone Procurement Training to the appropriate levels. 7.4.3 Project Sponsors must ensure, in line with Financial Regulation 2015, before placing an order that: The expenditure is an item or service that is within the Council’s legal powers to incur. The expenditure is within the relevant estimate provision. 7.4.5 When applicable, the Project Sponsor as defined within this framework will assume the role of the “ProjectOwner” as defined within the Scottish Government Construction Procurement Manual and will ensure that relevant methodologies including but not being limited to competitive stages are initiated and corporate standards are maintained through the project life-cycle. The Corporate Director or the HGB will assume the role of the Investment Decision Maker. 7.5 Risk Management 7.5.1 The Council’s Risk Management Strategy (include link) details the corporate approach to risk management and sets out the Council’s risk management process. This strategy forms the underlying principle for the governance of project management risks within the Council. 7.5.2 Risk can be defined as an uncertain event or set of events, which should it/they occur, will have an effect on the ability to deliver a project. This could be either a positive or negative effect. Risk Management is the activity required to identify and control the exposure to uncertainty which may impact the delivery of a project’s objectives. The aim is to restrict threats to within an acceptable level (Council’s “risk appetite”), and promote opportunities which will benefit the objectives of the project. ITEM: 9 PAGE: 25 7.5.3 Risk management is not about avoiding risk-taking but is about finding ways of managing the risks to the project to still be able to realise the benefits/objectives of the project. Risk identification and management is the responsibility of the Project Board, often devolved to the Project Manager. 7.5.4 A Risk Register must be maintained for a project. The Risk Register will contain all risks that may impact the project; an action plan listing the mitigation plan – actions/control measures to manage the risks effectively and a RAG status for each risk as defined in Section 6. 7.5.5 The Risk Register must be reviewed regularly by the Project Board and the risk status must be reported along the Project Governance Structure. Section 6 - Project Status Reporting Risk RAG defines the reporting requirements and the appropriate RAG definition for Project Risk. 7.6 Issue Management 7.6.1 Issues are defined as unplanned events or conditions that have already happened or are currently happening and that have impacted or are currently impacting on the objectives of the project. 7.6.2 The management of issues requires a systematic approach to ensure that the full impact of the issue on the project is understood and managed appropriately. This approach involves capturing the issue, examining the impact of the issue, proposing a resolution and implementing the resolution. 7.6.3 An Issue Log must be created for all projects. This Log will serve as the repository for all issues and allows issues to be tracked and responsibility assigned accordingly. The Issue Log will provide a description of the issue, what is affected, who owns the issue, resolution status of the issue and a RAG status for the issue. Section 6 – Project Status Reporting Issue RAG defines. 7.6.4 The Project Sponsor will determine the priority for issues and would escalate them based on their RAG status to the HGBs through Project Report status. 8 Support and Training in the use of the Framework 8.1 To support the adoption of this framework within the Council, an online training course focusing on the application (to be developed / procured) of the framework will be provided for all staff. This is a compulsory training course (to be developed) for all project Sponsors/Owners and anyone that is required to serve on a Project Board. 8.2 Tailored workshop on the implementation of the framework will be available on request. (to be developed). It is recommended that Project Sponsors request this workshop for new Project Boards. 8.3 Training on the use of this framework will not prepare officers to become Project Managers, as Project Management is a recognised professional discipline. However, basic training on Project Management as a discipline is available through the corporate Employee Development team. External training is also available leading to formal qualification. 8.4 It is the responsibility of the Project Sponsor to ensure that a suitably qualified and experienced Project Manager is appointed for their project. 8.5. A training matrix matching accountability to training requirement will be designed to help Project Sponsor ascertain Project Board training need. This matrix will also provide a link to Project Management resource within the Council. ITEM: 9 PAGE: 26 Appendix 1 – Project Board Structure Together, the Project Sponsor, the Senior User(s) and the Senior Supplier(s) make up the Project Board. The Project Board has authority and responsibility for the project within the instructions set by corporate or programme management. A good Project Board should display four key characteristics: Authority: The members of the Project Board should be senior enough within the corporate organisation to make strategic decisions about the project. As the Project Board is accountable for the project, the individuals chosen must have sufficient authority to make these decisions and provide resources to the project, such as personnel, cash and equipment. The managerial level required to fill the roles will depend on factors such as the budget, scope and importance of the project. Credibility: The credibility of the Project Board members within the corporate organisation will affect their ability to direct the project. Ability to delegate: A key part of the Project Board’s role is to ensure that the Project Manager is given enough space to manage the project by keeping Project Board activity at the right level. Project Board members should not be involved in the detail of how the project is managed, nor in the specialist content of the project. Availability: Project Board members who meet all the above characteristics are of little value to the project if they are not available to make decisions and provide direction to the Project Manager. Project Board members are often from senior management positions, and their Project Board responsibilities will be in addition to their normal responsibilities. The concept of management by exception allows the Project Manager to keep them regularly informed of project progress but only requires decision-making at key points in the project. ITEM: 9 PAGE: 27 The frequency and detail of communication required by the Project Board during a project will be documented at project-level. Project Board members may require more detail or less frequent information at the start of the project. As the project progresses and the Project Board become more comfortable with the progress being achieved, the requirement for frequent or detailed Highlight Reports may reduce. It is important to review the level and frequency of reporting for each stage of the project. ITEM: 9 PAGE: 28 Appendix 2 – Scottish Government Construction Procurement Manual – Project Team All major works projects should have an investment decision maker, project owner and project sponsor. This section explains their roles and responsibilities, along with those of the project manager and client adviser, and sets out the abilities and training they require, and their relationship to one another (Figure 1, below). ITEM: 9 PAGE: 29 Appendix 3 – Project Sponsor Check Lists Project Sponsor Check List: Gateway 1 – Strategic Assessment & Business Justification Consideration Yes / No Strategic Fit Does this prepare the council for future demands or requirements? Alignment with Moray2023 plan? Are the project drivers identified? (Legislation / Council Priority / Service Development / Efficiency / Maintenance) Corporate Capacity & Do- ability? Do we have internal/external authority and stakeholder support for the project? High level governance, commitment and support? Realistic? Any dependencies identified? Impact of the Project List which services are affected? Outlines scale of impact? Fit with current organisation design? Timetable? Resources Do we have the skills and resources available to take this forward? Specialist input? (External/HR/ ICT) Funding Streams Funding requirement / availability to move to next Gateway? Risk Of doing the project? Of not doing the project? Value Case (Cost v Benefits) Is there value awareness – indicative outline? Equality Assessment as per council policy? Project Sponsor / PIB Check List: Gateway 2 – Delivery Strategy Considerations Yes / No Does this project contribute to wider Council and public sector strategies, within and outside the Council? Is the Outline Business Case and/or Quality Plan complete and robust – does it meet the needs of the business, is it affordable and achievable, future proof, will it deliver value for money? Are the requirements clear and unambiguous, and are they aligned with the ITEM: 9 PAGE: 30 programme to which the project contributes? Do we have enough commercial expertise to understand the supplier market capability and track record? Is the Project Plan, through to completion, sufficiently detailed and realistic? Do we have the right skills, capabilities and management expertise to ensure success? Have the critical success factors and desired benefits been identified and agreed with stakeholders? Have we explored a sufficiently wide range of options to meet the business need and identified a preferred way forward? Have we identified major risks, and do we have outline risk management plans? Can we confirm our planning assumptions, and are there plans, for the project in place for the next stage? Is there a clearly defined and agreed project management structure, with key roles and responsibilities identified? Do we have adequate risk and issue management plans and procedures? Project Sponsor Check List: Gateway 3 - Planning and Initiation Considerations Yes/No Can we confirm the Full Business Case and Benefits Realisation Plan, or the Quality Plan (for infrastructure projects), now that we have relevant information from prospective suppliers? Are the objectives of the project still aligned with those of its programme and wider organisational and public sector strategies? Is the recommended decision on delivery approach likely to deliver what we need on time and within budget, and will it provide value for money? For procurements: Have we followed the agreed procurement strategy, and have we met all statutory and procedural requirements? Do we have sound plans for managing implementation, risk and change, and are they agreed across the supply chain? Do we have continuing stakeholder support for the project? Have we addressed the technical implications, such as “buildability” for construction projects, and information assurance for IT-enabled projects? Do we have the expertise and resources to manage the supplier relationship, and are appropriate management controls in place? Have we agreed draft contracts and/or Service Level Agreements? ITEM: 9 PAGE: 31 Project Sponsor Check List: Gateway 4 – Delivery Considerations Yes / No Is the Full Business Case or Quality Plan still valid and unaffected by internal or external events or changes? Can we confirm that the Benefits Realisation Plan/Quality Plan is likely to be achieved? Are commercial/legal arrangements with the supplier up-to-date? Can we confirm that our plans for managing implementation, roll-out and operation are achievable and that we have the resources we need? Is the Project Initiation Document and management controls in place to manage the project through to operation? Do we have shared plans for managing risk, with contingency and business continuity plans in place? Has full user and system testing and/or commissioning been done to our satisfaction so that we can approve full implementation and roll-out? Is the business ready to implement the business change, with the necessary resources in place? Do we have client-side plans for managing the working relationship, including contract management, reciprocated on the supplier side? Are lessons for future projects being identified and recorded? ITEM: 9 PAGE: 32 Project Sponsor Check List: Gateway 5 - Closure and Post Project review Considerations Yes/No Was the Business Case justification for the project at Gateway Review 3 realistic, and are the expected benefits actually being delivered? For infrastructure projects – was the Quality Plan realistic? Have we done a post-implementation review or equivalent review of business benefits? Do we have the resources in place to manage the contract/SLA successfully and with continuity of key support personnel? If we have made agreed changes, can we be sure that they do not compromise any requirements of the procurement approach adopted (e.g. change of scope)? Is there still a business need for this contract/SLA? If circumstances have changed, are the service delivery approach and contract adapting to the new situation? Are we actively seeking to improve value for money and performance? Are we ready for the future, with plans for future service provision? Are we managing the working relationship effectively, with the right ‘intelligent customer’ skills? Are the exit strategy and arrangements for re-procurement still appropriate? Are we actively learning from experience and setting maturity targets? ITEM: 9 PAGE: 33 Appendix 4 PROJECT CATEGORISATION Each project is to be given a low / medium / high Corporate Impact assessment in accordance with the assessment criteria. Each project is to be given a low / medium / high Complexity assessment in accordance with the assessment criteria. The Impact and Complexity assessments are applied to the Category matrix. ITEM: 9 PAGE: 34 BASIC Category - No project board required; change can be implemented as BAU. INTERMEDIATE Category - Change should be implemented as a PROJECT but with limited governance. STRATEGIC Category - Change must be implemented as a project with full project governance in place. Appendix 2 - RECOMMENDED STANDARDS Standard Software Comment Programme Management OGC Managing Successful Programmes (MSP) MS Products/ Locally produced templates. Externally provided training. DBS standard. Project Management (Basic / Intermediate projects) APMP / Agile (tbc) MS Products/ Locally produced templates. Externally provided training. Compliments MSP / P2 Project Management (Strategic projects) OGC – Prince 2 RIBA / SGCPM MS Products/ Locally produced templates Externally provided training. ComplimentsMSP. Gateway Process (Intermediate and Strategic projects) TMC Corporate Policy Use of locally administered SharePoint site. Internal training. Based on other council / OGC approach. Project Admin (All projects) TMC Corporate Policy (DBS Control Framework) Basic user standard MS Excel spreadsheets, MS word templates Internal training. Project Plans (All projects) Basic user standard MS Project 2010 Expect PMO staff to be advanced standard. External training. Process Mapping BCS Certificate in Modelling Business Processes (Foundation). Basic user standard MS Visio Externally provided training (3-day course) Benefit Realisation TMC Corporate Policy (inc CMPs) Excel spreadsheet, word templates Internal training. Change Techniques LEAN, Kaizan, BPR tools and techniques. BCS Foundation Certificate in Business Change Nil Externally provided training (2-day course) Externally provided training (2-day course)
Compartilhar