Prévia do material em texto
https://www.certsquestions.com/PSPO-I-pdf-dumps.html Scrum PSPO-I Professional Scrum Product Owner I QUESTION & ANSWERS QUESTION 1 Which statements about the Product Backlog are correct? The Product Backlog is never baselined.A. In the Product Backlog, Items at the top are usually smaller than on the bottom.B. The Product Owner is accountable for the Product Backlog.C. The Product Backlog contains only items that are completely refined.D. Correct Answer: A,B,C Explanation/Reference: The Product Backlog is never refined as it constantly evolves. In Scrum, to "baseline" something means to fixing something - the Product Backlog will never be fixed. Items at the bottom are usually unclear and not well refined. Therefore they are usually bigger. QUESTION 2 The Sprint Review is considered as a "formal meeting". FalseA. TrueB. Correct Answer: A Explanation/Reference: Be careful with the word "formal". Scrum. org uses the word "formal" in two different ways: 1. "formal opportunities" for inspecting and adapting - this means a serious opportunity -> all Scrum Events are formal opportunity for inspecting and adapting. 2. A "formal meeting" - a meeting where people approve something and exchange signatures -> no Scrum Event is a formal meeting. QUESTION 3 Which of the following are mandatory in Scrum? Have a Product Owner.A. Do Sprint Plannings.B. Do Daily Scrums.C. Use Story Points.D. https://www.certsquestions.com/PSPO-I-pdf-dumps.html Use User Stories.E. Correct Answer: A,B,C Explanation/Reference: It is not mandatory to use User Stories or Story Points in Scrum, but it is recommended. QUESTION 4 The Developers have an internal conflict with one of the development team members. What should the Product Owner do? Ask the Scrum Master to remove the Developer from the Team?A. Let the team handle the conflict internally - they are self-organizing!B. Remove the Developer from the team?C. Correct Answer: B Explanation/Reference: It is not the responsibility of the Product Owner to resolve team conflicts - the team is self-organizing. QUESTION 5 Self-organization means, that the team can decide which Scrum events are needed. TrueA. FalseB. Correct Answer: B Explanation/Reference: All Scrum events listed in the Scrum Guide are mandatory. https://www.certsquestions.com/PSPO-I-pdf-dumps.html QUESTION 6 In the Daily Scrum, the Development Team plans the work for the next 24 hours. TrueA. FalseB. Correct Answer: A QUESTION 7 Which of the following Scrum Events are time boxed? Sprint PlanningA. Sprint RetrospectiveB. Sprint GroomingC. Hardening SprintD. Daily ScrumE. Sprint ZeroF. Correct Answer: A,B,E Explanation/Reference: There is no Sprint Zero, a Hardening Sprint or a Sprint Grooming in Scrum. QUESTION 8 Does a Product Backlog item have an item "Owner". FalseA. TrueB. Correct Answer: A https://www.certsquestions.com/PSPO-I-pdf-dumps.html Explanation/Reference: There are 3 types of information in a Product Backlog item: the description, the value and an estimated size. The ownership is not set in the Product Backlog. QUESTION 9 More Velocity means more Value! FalseA. TrueB. Correct Answer: A Explanation/Reference: There is no direct relationship between Velocity (speed) and value. QUESTION 10 It is okay to have multiple Team Leaders when you work on several products? There are no Team Leaders in Scrum.A. YesB. Correct Answer: A Explanation/Reference: Following Scrum there are no roles besides the Scrum Master, the Product Owner and the Developers. QUESTION 11 Which of the following are required by Scrum? Hardening SprintsA. Time boxed eventsB. Sprint Planning meetingsC. Story PointsD. https://www.certsquestions.com/PSPO-I-pdf-dumps.html A Sprint 0E. Correct Answer: B,C Explanation/Reference: Hardening Sprints and a Sprint 0 are not allowed by Scrum. Story Points are recommended but not mandatory. QUESTION 12 Which of the following best describes the Scrum Pillar "Transparency"? The process should be visible to the key stakeholders.A. Significant aspect of the process must be visible to those responsible for the outcome.B. The whole process should be visible to everyone.C. Correct Answer: B Explanation/Reference: Only significant aspects should be visible, not all the details. The process does not to be visible to everybody in the world. QUESTION 13 What is Velocity? Average lines of code written per Sprint.A. Average number of items done per Sprint.B. Average man-hours spent per Sprint.C. Average amount of work done per Sprint.D. Correct Answer: D https://www.certsquestions.com/PSPO-I-pdf-dumps.html Explanation/Reference: The Velocity of a team is the average amount of work (e.g. in Story Points) done per Sprint. QUESTION 14 The Product Owner can also be a member of the Development Team. TrueA. FalseB. Correct Answer: A Explanation/Reference: One person can have more than one role in Scrum. It's not recommended at all, but it's not forbidden either. A better way of asking is "Can the same person play both the Product Owner role and a Development Team member role?" QUESTION 15 Which statements describe best what happens in an organization if Scrum is introduced but the Scrum terminology is tailored to fit into the organizations environment? The change might be not obvious to everyone and therefore little change will happen.A. The organization will adapt the Scrum concepts faster due to the tailored approach.B. The change might not be obvious to every employee and some employees will not recognize it atC. all. The management may feel less enthusiastic about the new approach.D. Correct Answer: A,C,D Explanation/Reference: Scrum is a very simple framework. Instead of tailoring the terminology you should follow everything that is described in Scrum and add practices and techniques that are tailored to your organization like e.g. Planning Poker, the use of Story Points, etc https://www.certsquestions.com/PSPO-I-pdf-dumps.html QUESTION 16 To be self-organized means, that it is okay for a Development Team to don't do the Daily Scrum. FalseA. TrueB. Correct Answer: A Explanation/Reference: To be self-organized does not mean that you can make changes to the Scrum framework. As a Scrum Team, you always have to do all the Scrum Events. QUESTION 17 When does the Scrum Master cancel a Sprint? The Scrum Master does not have the authority to cancel the Sprint.A. When there's an unsolved technical dependency.B. When the Development Team asks the Scrum Master to do so.C. Correct Answer: A Explanation/Reference: The Sprint can be cancelled by the Product Owner when the Sprint Goal becomes obsolet. The Scrum Master is not allowed to do this. QUESTION 18 Which Scrum Role is responsible to define and explain Product Backlog items? The Scrum MasterA. The Product OwnerB. The DevelopersC. https://www.certsquestions.com/PSPO-I-pdf-dumps.html Correct Answer: B Explanation/Reference: The Product Owner is responsible for managing the Product Backlog. QUESTION 19 The 3 Pillars of Scrum are creativity, inspection and adaptation. TrueA. FalseB. Correct Answer: B Explanation/Reference: The 3 Pillars of Scrum are transparency, inspection and adaptation. QUESTION 20 According to Scrum .org, Sprint cancellations are often traumatic to the Scrum Team, and are very uncommon. TrueA. FalseB. Correct Answer: A https://www.certsquestions.com/PSPO-I-pdf-dumps.html