A project manager has been approached by the project sponsor about adding to the project scope How should the project manager accommodate this requ...

A project manager has been approached by the project sponsor about adding to the project scope
How should the project manager accommodate this request?


A. Update the project team about the change request
B. Disregard the request since the project scope is finalized
C. Adjust the project schedule to accommodate the new project scope requests
D. Create a change request lor the change control board (CCB) to review

💡 1 Resposta

User badge image

Ed Verified user icon

A resposta correta para essa pergunta é a alternativa D. O gerente de projeto deve criar uma solicitação de mudança para que o Comitê de Controle de Mudanças (CCB) possa revisar. Isso é importante para garantir que todas as mudanças no escopo do projeto sejam avaliadas e aprovadas adequadamente, evitando assim problemas futuros.

0
Dislike0

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais