Based on the given scenario, the project manager should do the following: B. Update the risk register and discuss it with the project stakeholders. By updating the risk register, the project manager can document the potential impact of the delayed equipment delivery on the project schedule. Discussing it with the project stakeholders will help ensure that everyone is aware of the situation and can collectively work towards finding a solution or mitigating the risks associated with the delay.