Read the following excerpt: "The detailed work is carried out through the decomposition of deliverables into activities, and this is only possible ...

Read the following excerpt:
"The detailed work is carried out through the decomposition of deliverables into activities, and this is only possible if we know the scope in all its dimensions. That is, scope statement, WBS (Work Breakdown Structure), and WBS dictionary (Work Breakdown Structure). Without the detailed scope of the project, defining the activities is almost impossible." Source: BRANCO, R. H. F.; VINHA JR, R.; LEITE, D. E. S. Collaborative project management. 1st Ed. São Paulo: Saraiva, 2016.
A well-defined WBS (Work Breakdown Structure) ensures less uncertainty, fewer deviations in time estimates. Considering the mentioned citation and the concepts covered in the unit, analyze the following statements and the relationship between them.
I. A planning package is a component of the work breakdown structure below the work package and above the control account, with known work content.
II. A control account can include one or more planning packages.
Now, choose the CORRECT alternative:
Correct: Statement I is a false proposition, and II is a true proposition.


Correta: A asserção I é uma proposição falsa, e a II é uma proposição verdadeira.

Essa pergunta também está no material:

AOL-3_GestaoProjetos
5 pág.

Desenvolvimento e Gestao de Projetos Faculdade Maurício de Nassau de Lauro de FreitasFaculdade Maurício de Nassau de Lauro de Freitas

💡 1 Resposta

User badge image

Ed Verified user icon

Correto: A asserção I é uma proposição falsa, e a II é uma proposição verdadeira.

0
Dislike0

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais

Outros materiais