Is it correct to say that creating the Work Breakdown Structure (WBS) is: a. The process of subdividing the project's work and deliverables into ...

Is it correct to say that creating the Work Breakdown Structure (WBS) is:


a. The process of subdividing the project's work and deliverables into smaller, more easily managed components.
b. The same as identifying and documenting the dependencies of project activities.
c. The same as estimating the resources needed to perform each activity (people, raw materials, equipment).
d. The process of identifying the activities necessary to produce the project's deliverables.

Essa pergunta também está no material:

Analise e encaminhamento de Projetos Publicos - modulo lV
7 pág.

💡 1 Resposta

User badge image

Ed Verified user icon

Sim, é correto afirmar que criar a Estrutura Analítica do Projeto (EAP ou WBS, do inglês Work Breakdown Structure) é o processo de subdividir o trabalho e os entregáveis do projeto em componentes menores e mais facilmente gerenciáveis. A alternativa correta é a letra "a". A EAP é uma ferramenta importante para o gerenciamento de projetos, pois ajuda a organizar e estruturar o trabalho em partes menores e mais gerenciáveis, permitindo que o gerente de projetos possa acompanhar o progresso do projeto de forma mais eficiente.

0
Dislike0

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais

Outros materiais