A Product Owner is entitled to postpone the start of a new Sprint after the conclusion of a previous Sprint for the following reason: A) Not enough...

A Product Owner is entitled to postpone the start of a new Sprint after the conclusion of a previous Sprint for the following reason:
A) Not enough Product Backlog items are “Ready”.
B) The Product Owner has not identified a Sprint Goal.
C) There is no acceptable reason. A new Sprint starts immediately after the conclusion of the previous Sprint.
D) The QA department needs more time to make the previous Increment “Done”.
E) The stakeholders are not happy with the value produced in the previous Sprint.

Essa pergunta também está no material:

QUESTÕES-SCRUM 500 PERGUNTAS E RESPOSTAS
241 pág.

Scrum Centro Universitário UNINTERCentro Universitário UNINTER

💡 1 Resposta

User badge image

Ed Verified user icon

A resposta correta é a alternativa A) Não há itens suficientes no Product Backlog que estejam prontos para serem trabalhados. O Product Owner é responsável por garantir que o Product Backlog esteja atualizado e priorizado, e que os itens estejam prontos para serem trabalhados antes do início de um novo Sprint. Se não houver itens suficientes prontos, o início do novo Sprint pode ser adiado até que haja itens suficientes prontos para serem trabalhados.

0
Dislike0

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais