Which approach should the project manager take? A. Ask the team to raise blockers or impediments in daily meetings. B. Prioritize deliverables ba...

Which approach should the project manager take?


A. Ask the team to raise blockers or impediments in daily meetings.
B. Prioritize deliverables based on business value and define frequent releases.
C. Ask the team to challenge the project estimations for a faster delivery.
D. Prioritize the tasks with high risks to reduce the number of iterations required.

💡 1 Resposta

User badge image

Ed Verified user icon

The project manager should take approach B. Prioritize deliverables based on business value and define frequent releases. This approach ensures that the most important tasks are completed first and that there is a continuous delivery of value to the stakeholders.

0
Dislike0

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais