Which approach should the project manager take?
A. Ask the team to raise blockers or impediments in daily meetings.
B. Prioritize deliverables ba...
Which approach should the project manager take?
A. Ask the team to raise blockers or impediments in daily meetings. B. Prioritize deliverables based on business value and define frequent releases. C. Ask the team to challenge the project estimations for a faster delivery. D. Prioritize the tasks with high risks to reduce the number of iterations required.
The project manager should take approach B. Prioritize deliverables based on business value and define frequent releases. This approach ensures that the most important tasks are completed first and that there is a continuous delivery of value to the stakeholders.