76. In a daily standup meeting, a developer indicates that a backlog item will not be delivered because they need to take an unexpected leave for t...

76. In a daily standup meeting, a developer indicates that a backlog item will not be delivered because they need to take an unexpected leave for the next couple of days. The backlog item is a prerequisite for a feature expected by users in the next sprint review.
What should the project lead do?


A. Ask the developer to postpone the leave until the backlog item is delivered.
B. Ask the development manager to provide a replacement for a couple of days.
C. Work with the product owner to change the priorities in the sprint backlog.
D. Work with the product owner to inform the users that the feature is delayed.

💡 1 Resposta

User badge image

Ed Verified user icon

Nessa situação, o líder do projeto deve trabalhar com o product owner para informar aos usuários que a entrega da funcionalidade será adiada. Portanto, a alternativa correta é a letra D.

0
Dislike0

Faça como milhares de estudantes: teste grátis o Passei Direto

Esse e outros conteúdos desbloqueados

16 milhões de materiais de várias disciplinas

Impressão de materiais

Agora você pode testar o

Passei Direto grátis

Você também pode ser Premium ajudando estudantes

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais