In order to carry out an organizational change project, it is necessary to allocate human resources to constitute the work team; budgetary resource...
In order to carry out an organizational change project, it is necessary to allocate human resources to constitute the work team; budgetary resources to cover expenses; material resources; technological resources and physical space. To obtain these resources, the administrator must prepare a PMO proposal and present it to the board of directors, and only after approval can he start the project. Therefore, for the elements that make up a PMO proposal, correlate them with their definitions and mark the CORRECT sequence:
A sequência correta é: 9, 5, 8, 3, 7, 4, 6, 2, 1.
1. Definição do problema e justificativa da proposta (9)
2. Objetivos do projeto (5)
3. Escopo do projeto (8)
4. Cronograma (3)
5. Orçamento (7)
6. Equipe de trabalho (4)
7. Riscos (6)
8. Metodologia (2)
9. Resultados esperados (1)