What is the purpose of the 'capacete' installed on top of the pile during its installation? I - To absorb the blows of the pile driver. II - To st...

What is the purpose of the 'capacete' installed on top of the pile during its installation?

I - To absorb the blows of the pile driver.
II - To standardize the tensions applied to the pile.
III - To prevent the pile from breaking during installation.
a) Only I is correct.
b) Only II is correct.
c) Only III is correct.
d) I and II are correct.
e) I, II and III are correct.

Essa pergunta também está no material:

Apostila de Fundações   Técnicas Construtivas
23 pág.

Fundações Universidade Vila VelhaUniversidade Vila Velha

💡 1 Resposta

User badge image

Ed Verified user icon

O objetivo do "capacete" instalado no topo da estaca durante sua instalação é absorver os impactos do martelo vibratório. Portanto, a alternativa correta é a letra A) Somente I está correta.

0
Dislike0

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais