PERT (Program Evaluation and Review Technique), when used in operational planning of activities, relates to:
a. The behavior of the members in th...
PERT (Program Evaluation and Review Technique), when used in operational planning of activities, relates to:
a. The behavior of the members in the production line. b. The methods to be employed in the production lines. c. The time to be employed in the execution of tasks. d. The assignment of positions. e. The money to be spent.
A técnica PERT (Program Evaluation and Review Technique), quando usada no planejamento operacional de atividades, está relacionada ao tempo a ser empregado na execução das tarefas. Portanto, a alternativa correta é a letra C.