Which two things should the development team do during the first sprint?
A) Create a increment of potentially deliverable software.
B) Analyse, describe and document the requirement for the subsequent sprint.
C) Develop at least one piece of functionality.
D) Make up a plan for the rest of the project.
E) Analyse, describe and design the complete architecture and infrastructure.

a) A) Create a increment of potentially deliverable software.
b) B) Analyse, describe and document the requirement for the subsequent sprint.
c) C) Develop at least one piece of functionality.
d) D) Make up a plan for the rest of the project.
e) E) Analyse, describe and design the complete architecture and infrastructure.

Essa pergunta também está no material:

QUESTÕES-SCRUM 500 PERGUNTAS E RESPOSTAS
241 pág.

Scrum Centro Universitário UNINTERCentro Universitário UNINTER

💡 1 Resposta

User badge image

Ed Verified user icon

A resposta correta é A) Create a increment of potentially deliverable software e C) Develop at least one piece of functionality. Durante o primeiro sprint, a equipe de desenvolvimento deve criar um incremento de software potencialmente entregável e desenvolver pelo menos uma funcionalidade. As outras opções não são recomendadas para o primeiro sprint, pois podem levar a atrasos e problemas no projeto.

0
Dislike0

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais