23) Which two things should the development team do during the first sprint? A) Create a increment of poten- tially deliverable software. B...

23) Which two things should the development team do during the first sprint?

A) Create a increment of poten- tially deliverable software.

B) Analyse, describe and document the requirement for the subsequente sprint.

C) Develop at least one piece of functionality.

D) Make up a plan for the rest of the project.

E) Analyse, describe and design the complete architecture and infrastructure.

a) A) Create a increment of potentially deliverable software.
b) C) Develop at least one piece of functionality.

Essa pergunta também está no material:

QUESTÕES-SCRUM 500 PERGUNTAS E RESPOSTAS
241 pág.

Scrum Centro Universitário UNINTERCentro Universitário UNINTER

💡 1 Resposta

User badge image

Ed Verified user icon

A resposta correta é a alternativa "a) A) Create a increment of potentially deliverable software." e "b) C) Develop at least one piece of functionality." Durante o primeiro sprint, a equipe de desenvolvimento deve criar um incremento de software potencialmente entregável e desenvolver pelo menos uma funcionalidade. As outras alternativas não são atividades recomendadas para o primeiro sprint, como analisar, descrever e documentar requisitos para o próximo sprint, criar um plano para o restante do projeto ou analisar, descrever e projetar a arquitetura e infraestrutura completa.

0
Dislike0

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais