According to the PMBOK, what are the inputs for creating the Work Breakdown Structure (WBS)?


a. Organizational process assets; project scope statement; scope management plan; approved change requests.
b. Organizational process assets; project WBS statement; WBS management plan; unapproved change requests.
c. Organizational structure assets; project scope statement; contingency management plan; approved specification requests.
d. Organizational process assets; project risk statement; risk management plan.

Essa pergunta também está no material:

Analise e encaminhamento de Projetos Publicos - modulo lV
7 pág.

💡 1 Resposta

User badge image

Ed Verified user icon

De acordo com o PMBOK, as entradas para criar a Estrutura Analítica do Projeto (EAP ou WBS) são: a. Ativos de processos organizacionais; declaração do escopo do projeto; plano de gerenciamento do escopo; solicitações de mudança aprovadas.

0
Dislike0

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais