What is the definition of Work Breakdown Structure (WBS)? a. Subdivision of the project's work and deliverables, but only appears in the project ...

What is the definition of Work Breakdown Structure (WBS)?


a. Subdivision of the project's work and deliverables, but only appears in the project charter as the main objective of the project's goals.
b. Subdivision of the project's work and deliverables is part of the project charter.
c. Hierarchical orientation that controls from the project charter to the work deliveries to achieve the project's objectives.
d. Hierarchical decomposition oriented to the work deliveries to be executed by the project team.

Essa pergunta também está no material:

Analise e encaminhamento de Projetos Publicos - modulo lV
7 pág.

💡 1 Resposta

User badge image

Ed Verified user icon

A definição de Work Breakdown Structure (WBS) é a letra "d": Hierarchical decomposition oriented to the work deliveries to be executed by the project team. A WBS é uma estrutura hierárquica que divide o trabalho do projeto em partes menores e mais gerenciáveis, chamadas de entregas, que são atribuídas à equipe do projeto para execução.

0
Dislike0

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais