Prévia do material em texto
Commissioning & Operational Readiness – a standardized assessment methodology Abstract: Considering the value of a one-day delay in achieving a project’s in-service date, this is a significant business risk to manage. The Commissioning & Operational Readiness Assessment is a standardized assessment methodology that helps improve schedule performance by enabling organizations to ensure transition readiness through each phase of commissioning and startup. The transition from construction to operation is the commissioning and startup. Correct commissioning is vital to the satisfactory operation of any plant or facility, and it is essential that sufficient time and resources be allocated to different stages of commissioning and startup. Special efforts are needed to ensure safety and reliability at commissioning. Since commissioning, startup and shutdown activities have been responsible for many accidents, failure and other issues, these activities merit special attention. Processing plant commissioning embraces activities such as cleaning, flushing, verifications (Punching sessions), leak tests, performance evaluation (prior ready for commissioning RFC) and functional tests essential for bringing a newly installed facility into routine operation (prior ready for operations RFO). Commissioning is the startup for the very first time, is the last major phase before operation, there is a risk that commissioning will take place under great time-pressure or even some delayed commissioning activities may continue after the initial operation of the plant. “Is the highest risk period in the lifetime of the plant. Fig.2 BP America (in Texas) Refinery Explosion Accident Description Accident: BP America (Texas City) Refinery Explosion Location: Location: Texas City, TX Accident Occurred On: 03/23/2005 | Final Report Released On: 03/20/2007 Accident Type: Oil and Refining - Fire and Explosion Investigation Status: The Board approved its final report by a vote of 5- 0 at a public meeting in Texas City on March 20, 2007. At approximately 1:20 p.m. on March 23, 2005, a series of explosions occurred at the BP Texas City refinery during the restarting of a hydrocarbon isomerization unit. Fifteen workers were killed, and 180 others were injured. Many of the victims were in or around work trailers located near an atmospheric vent stack. The explosions occurred when a distillation tower flooded with hydrocarbons and was overpressurized, causing a geyser-like release from the vent stack. Keywords: Commissioning, operational readiness, assessment 1.Introduction Following any tech transfer project, the subsequent startup of the manufacturing line is almost always full of challenges. The goal is to startup as soon as possible once the project is completed but also to achieve steady state throughput as quickly as possible after the startup begins. This type of startup is what is called a “Vertical Startup.” In practice, vertical startups are rare because management teams typically focus their attention on having the facility and the equipment qualified in time to meet the process qualification milestone. The consequence of this thinking is that a broad range of workstreams are often neglected or receive inadequate attention although they are critical to startup. Workstreams like staffing, training, procedure development, supply chain, analytical methods, etc. must all be ‘ready to go’ by this important milestone. The result can be like having perfectly tuned race cars lined up on the starting line of a Formula 1 race, but with untrained drivers, little gas, unpracticed pit crews, and no spare parts. Before a plant or facility is handed over for normal operation, it should be inspected, checked, cleaned, flushed, verified, and tested. This process is called commissioning and involves both the contractor and operators of a facility (client). The primary objective of this article is to inform the reader (particularly those who are a part of management teams) about commissioning and startups and how Operational Readiness is the organizational state that needs to be reached for vertical startups to exist. The secondary objective is to help the reader build an understanding of Operational Excellence in addition to Operational Readiness. 1 Email address: arvindo.candeio3@gmail.com Introduction to the Commissioning and Operational Readiness Assessment. A.J. Candeio Commissioning & Reliability Engineer 6 Publications 22 citations August 2024 Fig.1 Soap leak testing & verification (marked up P&ID is needed) 2. Commissioning Methodology Overall commissioning includes four construction milestones and three project milestones. Construction milestones: practical or civil completion (PC or CC) Mechanical Completion (MC) Electrical Completion (EC) Instrumentation Completion (IC) Project milestones: Ready for commissioning (RFC) Ready for Operations (RFO) Beneficial operations (BO) Careful planning is necessary for commissioning and startup, integration of systems, particularly control systems with others, has to be seamless. Commissioning execution plan (CEP) is the high-level commissioning plan that is used to generate the method of statement (discipline commissioning master plan). A correct startup sequence and procedure are needed and should be followed with utmost care and diligence. For any machinery or equipment, specific set of spare parts is needed for commissioning and start up. Generous quantities of spare parts should be provided for this phase so commissioning and startup are not delayed for lack of spare parts or tools. 2.1 Pre-commissioning This stage often involves many activities such as installation; inspections of equipment, piping, and machinery, checking of units and facilities against designs (punching sessions), such as the piping and instrumentation diagram (P&ID), flushing and cleaning, pressure testing, functional testing, simulation and more. Flushing Air blowing / card board blasting, Service blowing Pigging (the most efficient method of pipe cleaning) Flushing procedure during the pre-commissioning activities is needed for piping and checkout form should be filled and signed off prior to mechanical completion. Many process piping systems constructed in new plants do not require significantly high cleanliness levels and are often “flushed” with water after hydrostatic testing. At this stage, the actions of controllers and motorized valves should be checked. Major equipment should be also thoroughly inspected, monitored and final closed in (Boxing up vessels) in the presence of commissioning team or client. Initial measurements of critical clearances should be taken for later comparison control. 2.2 Importance of redline drawings (P&ID) Redlines are a critical aspect of the construction process. All deviations must be drawn in red so the project team can see the change. It helps ensure that all the designers and workers are always on the same page about what is being constructed and when. Dealing with project changes is a part of being a contractor, and every change should be documented. Redline drawing is the first step, with an as-built drawing following it. For the inspections of equipment during pre-commissioning phase, it is useful to ask Maintenance Manager / Engineer(s) to attend the activities or even participate in the commission for inspection and testing of all equipment and rotatingmachinery including electrical or mechanical machines. After all maintenance staff should take care of these machines and equipment during operations and the commissioning stage is the best opportunity to start this task. During the commissioning phase prior RFC all Standard operation procedures (SOP’s), potential deviation analysis (PDA’s) should be developed, and training or awareness should be conducted to operators and mechanical artisan. 2 Email address: arvindo.candeio3@gmail.com July 2024 Fig.4 Mechanical punching Test Pack M-001 3. Typical challenges and Problems in Commissioning Shortcomings in basic design contributes less to commissioning difficulties than errors in detail design and construction. The reason is the fundamental concepts have generally the most researched, examined and evaluated by senior technical staff. Also, shortcomings in basic designs are usually discovered and mitigated in the detail design. On the other hand, in the areas of detail design, installation and construction, surprises are not uncommon. Faulty or absent venting arrangements occurs frequently. For example, if vessel vents are too close to the inlet nozzles, feed materials might be vented unintentionally. A pump set up with insufficient suction head to meet NPSHR has been reported during commissioning of many plants. The situation may be worsened by partial suction restriction due the plugging of a temporary strainer or similar condition. The results, in terms of cavitation, could be problematic and damaging. Lack of detailed assessments where a flow is split often leads to unsatisfactory results. Examples are a sampling stream in parallel with the main flow and a level control maintained by recirculation as well as outflow, with a control valve on one flow only. In general, such a problem can happen in any place where the flow is split. When a control valve on a line is actuated, the flow of both would be affected and accurate control of these flows is not usually possible by only one valve. Sometime a dedicated control valve is needed on each line to properly control flow of each line. The automatic control is another hot topic in the commissioning. Whereas realistic simulation exercises attempt to test control performance as much as possible, there have been severe limitations to do so in the absence of job fluids and normal operating conditions. Commissioning plans should therefore be viable on the assumption that some control devices will not operate when needed and alternative means of operation and control should be included. Sudden major leaks from piping or equipment after pressure testing have been reported in some occasions, but such leaks are relatively uncommon if the piping and facilities are properly fabricated, inspected and tested. However, others of disfunctional pressurization and leaks have been common in the commissioning. There have been dangerous incidents where fluids from a high-pressure circuit leaked into an ancillary low -pressure circuit through a faulty item such as defective equipment, tube or valve. This resulted in release of a large quantity of pressurized material and even high-pressure flammable material. Careful attention should be given to all systems including low pressure auxiliary and ancillary systems and their potential interfaces and exposures to other process or high-pressure circuits. For instances, there was a case that high pressure gas in a compressor pressurized the lubrication oil system because of faulty internal part inside the machinery which caused extensive damages. Vacuum leaks are a common problem during commissioning of vacuum systems, particularly air leaks into vacuum system. Wrong or imperfect application of materials of construction have been widely reported as serious problems in commissioning (e.g., wrong gaskets). Two examples are wrong initial material selection and secondly, errors in manufacturing, fabrication, and welding. Thank and vessel linings have been a known source of problem and poor performance during commissioning. In theory, lining is a good and cost- effective solution. Unfortunately, in many cases, defects and problems became apparent at the commissioning stage. 4. WHY A FOCUS ON READINESS? Getting off to a good start is the essence of Operational Readiness (OR). OR is a management approach widely used in the chemical production and energy sectors which has direct applicability to drug makers. These industries use formal Operational Readiness and Assessment (OR&A) programs as a risk management paradigm to guide management practices for performing pre-startup reviews of (1) new processes regardless of scale, from big plants to small plant startups, (2) processes that have been shut down for modification, and (3) processes that have been administratively shut down for other reasons. However, being “ready” needs to go beyond just performing pre-startup reviews – particularly for the life sciences industry. It needs to include an analysis of the product input and output variances and the control strategy deployed – not to mention evaluating the actual startup afterwards, which is one of the best performance indicators of OR. Key elements of operational readiness assessment: For the long–term operational success and viability of a new facility, operational efficiencies require attention and development during the design and construction phases which are heavily influenced by the high pressures imposed for schedule and budget compliance. If not planned well in advance, the transition from construction to operation can be chaotic. A predictable opening day that can confidently deliver stable and reliable building performance is dependent on three key components: facility readiness, people readiness, and information readiness. 3 Email address: arvindo.candeio3@gmail.com July 2024 Fig 5-Operational Readiness diagram. Courtesy of Jacobs. 4.1 Facility Transition Planning to Asset Management For the long–term operational success and viability of a new facility, asset management requires attention and development during the design and construction phase where the focus is predominantly on building the physical assets, driven by the high pressures imposed for schedule and budget compliance. If not planned, the baton pass from construction to occupancy and asset management can be less efficient and less effective. Understanding the potential risks and cost overruns associated with transitioning a new facility can enable the owning organizations to effectively and predictably plan for smooth transitions from construction to operational readiness and long term asset management that contribute to lower O&M costs, increased facility longevity and a superior customer or occupant experience. With an increase in the level of technology in facilities coming online in the near future, it is imperative that the transition planning, workforce preparation, and data transference are consistent and reliable for organizations expanding their portfolio and seeking an integrated operations and asset management program from opening day of a new facility. Engagement of the operations and support teams, including security, environmental health safety and security, facility management, and engineering and maintenance, throughout the system startup and commissioningphases will have staff better prepared to accept full operations and maintenance responsibility during the transition to a fully operational facility with the ability to support the owning organization in a productive and safe environment. To become operationally ready, leaders must begin working toward that objective early in the project – ideally at the beginning stages of the project during the preliminary design review (but no later than the Design Qualification). This early involvement may surprise most operations managers, but this effort is essential. 5. Formal operational readiness and assessment program Lastly, companies should develop and implement an OR&A program that anticipates problems and either eliminates them or puts management systems in place to mitigate them. OR&A programs have historically recognized that an operational system is comprised of multiple elements: 1 People, 2 Procedures, and 3 Equipment. Consequently, an organization’s preparedness efforts need to address these three areas individually as well as in an integrated fashion. Logic trees are frequently used for this effort as a visual diagnosis that lays out a problem and all its possible solutions, allowing you to choose the best course of action. Do the people match the equipment? Is the equipment properly operable for the people who have been selected and trained to operate it? Do the procedures match the equipment? E.g., have we avoided situations in which the operators have been given Version 1 procedures manuals to operate Version 2 equipment? Do the procedures match the people who are to use them? Acknowledgements The author like to thank to the respectable reviewers for giving proper instruction to improve the quality of this paper. About the Author Arvindo Candeio, graduated from Eduardo Mondlane University in Mechanical Engineering between 2008-2013, son of two public servants: Joao Candeio and Juliana Sadraque. I was born in a small border town in Mucumbura - Tete Province, I went through a difficult time due to the effects of the civil war, during my childhood I was a cattle and goat herder and helped my parents cultivate corn, beans, and sorghum in the village of Mapalo, 5 km from the administrative post of Mucumbura. References [1] Oil & gas Mozambique Project_ learnings from FLNG Coral, IPF Integrated processing facility and IGF Initial gas facility IBL and OBL 2023-2024 [2] https://www.wbdg.org/resources/transitioning-new-facility- from-construction-operations-asset-management Email address: arvindo.candeio3@gmail.com 4 July 2024