2019 14th Iberian Conference on Information Systems and Technologies (CISTI) 19 – 22 June 2019, Coimbra, Portugal ISBN: 978-989-98434-9-3 Information Flows Improvement in Production Planning using Lean concepts and BPMN An exploratory study in industrial context Ana Rita Arromba DEGEIT University of Aveiro Aveiro, Portugal ana.rita.arromba@ua.pt Leonor Teixeira IEETA/GOVCOPP/DEGEIT University of Aveiro Aveiro, Portugal lteixeira@ua.pt Ana Raquel Xambre CIDMA/ DEGEIT University of Aveiro Aveiro, Portugal raquelx@ua.pt Abstract — Technological evolution is currently triggering changes in companies’ environments. There is a continuous need of adapting processes to achieve competitive advantage. This paper describes a study developed in a sanitary systems multinational manufacturer that focuses on improving its global performance, especially in the production planning and control department. The main goals are to emphasise the importance of process modelling during the data collection, analysis and visualization procedures and to show the importance of inefficiency reduction in information flows. BPMN 2.0 was used to identify the data sources and information flows and Microsoft Power BI was used to show that it is possible to reduce waste in the processes. A combination of Lean Thinking, Information Systems and Industry 4.0 principles and methods is used. The foreseen result is an information system that connects people, data and processes in a way that efficiency is gained in the daily tasks, in the decision- making processes and in the identification and elimination of non- value-added activities. Keywords – Information Systems, BPMN, Lean, Industry 4.0. I. INTRODUCTION Companies seek to improve business processes to facilitate information flows, create value and achieve strategic results, connecting all of their departments [1]. This study focuses on the production planning of a sanitary systems firm, where the production plans are constantly being adjusted. Despite having tools to analyze large amounts of data, production planners need a thorough organization of information into Key Performance Indicators (KPIs) to enable an efficient decision- making [2]. In this case, the problem lies on an excess of files and manual tasks that impair data analysis and the decision- making process. The goal is to boost the business processes’ performance, combining ideas from Information Systems, Lean Thinking, Industry 4.0 (I4.0) and KPIs. In increasingly complex environments, companies have to improve their information flows to avoid all type of inefficiencies. In this exploratory study, the data sources and the information flows will be mapped and identified, using BPMN 2.0, helping identify and thus eliminate the non-value-added tasks. An information system supported by a business intelligence tool that centralizes and quickly shows the information in real time will be specified. It will help the planners in their daily tasks and bring efficiency to the processes. The feasibility of this study will be discussed, as well as the obtained results and future work. II. THEORETICAL BACKGROUNG In this section the main concepts behind the development of this work are briefly presented, namely: Lean, Information Systems and Industry 4.0. A. Lean Information Management and BPMN Lean is a philosophy that aims to reduce waste and non- value-added activities using the same or a smaller amount of resources [3]. Despite having its origins in production, Lean Thinking can, equally, contribute to information processes and flows, being therefore called Lean Information Management [4] [5] [6] [7]. Lean is based in 5 main principles [8]: specify value, identify value streams, make value flow, let the customer pull value and pursue perfection. Additionally, the 7 types of waste are also important in this context: Overproduction, Waiting, Transport, Extra Processing, Inventory, Motion and Defects [5]. More recently, an 8th type of waste was identified, Non-Utilized Talent. Within the context of Lean Information Management it is also important to understand that every company has its own business processes, and being able to model and represent those processes can help to achieve process efficiency [9]. Business process modelling allows the analysis, identification and specification of business processes [10] [11] and characterizes the flows between internal and external environments of a company [12]. In this context BPMN 2.0 arises as language that, according to [9], is a graphical readable and understandable modelling notation that shows the properties and execution information of a process. By using this graphical notation, it is easier to identify where the inefficient information flows are and thus apply Lean principles to improve the outputs of business processes. The determination of essential KPIs is an excellent example of this application because they represent quantitative crucial information in business environments and in planning and controlling. They help to construct information, promoting transparency and supporting decision makers [13]. Also, [14] describe a tree-like structure of KPIs to define the Performance Measurement System (PMS) of a Lean Production System. The 2019 14th Iberian Conference on Information Systems and Technologies (CISTI) 19 – 22 June 2019, Coimbra, Portugal ISBN: 978-989-98434-9-3 KPIs are identified and categorized in a multi-level hierarchy designed to give answers at strategic, tactical, and operational level. B. Information Systems An Information System (IS) is a tool that captures, monitors and displays information, “supporting people, organizations or other systems”. It is about helping people to find the information they seek without limit on its sources [15]. It also offers a diversity of opportunities for a company to automate and share its knowledge efficiently [16]. The idea is to apply an information system to the production planning, which is an area that requires cooperation between multiple units of a company. It is also argued that a strategic advantage is achieved by making the right decisions. Therefore, there is a need to have tools that quickly share information and support production planners in their decision-making. [17] propose a Hierarchical Decision Support System for production planning that enables planners to use structured planning algorithms in an interactive way. There is also a relation between information systems and the way they can support business processes. [18] suggest an approach that uses business process diagrams to manage and visualize its execution directly. This provides handlers with “means to control process execution clicking on graphical diagrams that represent executable business processes”. The execution mechanism opens new ways to follow-up the executed business processes. It is beneficial in terms of usability as the entire business process is visible to the users in a graphical form. Such tools that improve business processes of a specific area of a company are the proof that the proper use of information systems “enables the institutions to access their information for better and effective decision-making” [19] [20]. C. Industry 4.0 [21] and [22] state that I4.0 characterizes the fourth stage of the industrial revolution. The main features are the increased flexibility in manufacturing, the mass customization, improved productivity and better quality. I4.0 is associated with all the mechanisms that promote connectivity between machines, smart production systems and integrated solutions [23]. With the boom of I4.0 comes a large and complex amount of data: Big Data that disrupts the senior management of organizations, pressuring directors to make decisions more rapidly and to shape their capabilities to address environmental changes [24]. This type ofdata comes in large quantities, is unstructured, has no direct relationship and must be analyzed within a very short time to create value [25]. This requires integrated technologies with agile information systems to enable an adaptation to the changing scenarios that characterize the industrial environments in I4.0 [26]. [27] built a model that evaluates data productivity reducing its waste and considering data availability, data quality and the performance of the decision-making. With regard to the benefits of I4.0, [28] showed that the development of new systems helps to create tools that boost the processes of a company. They state that smart manufacturing from I4.0 requires the gathering of information from intelligent devices and a use (KPIs) that consolidates and shows the information in real-time, improving the performance of the processes. [29] propose a solution that considers a IS connected to several parts of a supply chain and uses advanced optimization algorithms to generate process plans, orders of operations and schedules automatically. The IS establishes the link between smart products and an ERP. Based on the analysis of the theoretical background and the existing literature, the idea supporting this work is to better explore, based on a practical case, the relationship between Information Flows and Lean philosophy, considering also the automation of some processes in a I4.0 context, and how this can help the determination and use of critical KPIs within the production planning department of the company. III. PRACTICAL CASE IN INDUSTRIAL CONTEXT A. Problem Background and Goals The main goal of this study is to show how process modelling can improve efficiency in the procedure of updating the production plans. Production Planning and Control (PPC) is an important area in the scope of manufacturing companies, because it defines the course of production. PPC is defined as a work process that seeks to allocate human resources, raw materials, and equipment/machines in a way that improves efficiency [30]. Thus, in order to increase efficiency, it is important to reduce the non-value-added activities in the process. In the case that was analysed the PPC department develops 3 plans that depend on the stage of production: Pre-Process, PVD (physical vapour deposition coating) and Assembly. Each plan has its own specifications and needs a set of detailed information to be completed. Currently, to get all the information that is required, a lot of time and resources are spent, which contributes to increased waste. The planners retrieve data from different sources and analyse it to decide what is going to be produced. As there is a lot of unstructured data during this process, there is also noise and entropy that cause disturbances, making the process unproductive. This entropy is also associated with a lack of quality in the visualization of data and some confusion with the information flows. The data needs to be analysed to have a meaning and consequently, the entropy blocks the data handling and the decision-making process of the planners. In order to solve this problem, the first phase was to map the processes, using BPMN 2.0, clarifying the relevant information flows, the data sources, the people involved and aligning the referred elements. After that, the main sources of waste, namely the non-value-added activities were identified. In this inefficient process an opportunity for improvement emerged, by creating an autonomous information system that streamlines the process, and gathers, centralizes and shows the wanted information in real time, supported by the features of a business intelligence tool – Microsoft Power BI. B. Methodology The methods and techniques used to achieve the solution are explained in this section. It was essential to gather information 2019 14th Iberian Conference on Information Systems and Technologies (CISTI) 19 – 22 June 2019, Coimbra, Portugal ISBN: 978-989-98434-9-3 about the processes, identifying the ones that needed to be improved and how to manage them, resulting in an architecture of the processes. Initially, top management established that the KPIs supporting the production planning needed to be improved, as well as the information flows’ quality. Hence, it was imperative to track the processes’ streams that include the determination of the KPIs and the development of the production plans. The information was collected using 3 different techniques: observation, documental analysis and informal interviews. First, to clarify and identify the processes, the planners’ daily tasks were observed and, while doing that, the boundaries of the processes were established, as well as its general and specific steps, the level of data processing and treatment. Second, as there is a considerable number of files, a documental analysis helped to understand the data and all the complexity associated. Additionally, through informal interviews done to the planners, it was easier to discuss the problems and identify what could be improved. The results were organized using BPMN 2.0 diagrams that represent the process mapping through an AS-IS Model. The diagrams display information sources, flows, tasks, files and people involved. As it was an already-known tool amongst the supply chain team, Microsoft Power BI, a business intelligence software, was then used to obtain the final solution. C. Results and Discussion The first plan that is developed is the assembly plan (the last part of the production process) that, when finished, supports the PVD and pre-process plans. Each plan has a responsible assigned, except for the assembly plan that, due to its complexity, is divided into 3 parts allocated to 3 planners. The planners get data from the Enterprise Resource Planning (ERP) system of the company (SAP). Since it is a multinational company, there is a dependency between this department and the Central Production Planning and Control department. This department sends a file to the company every morning, called KPIs, to identify the daily production priorities. The KPIs file gives information about the products, the required safety stocks, availability of materials, backlogs (orders that are not shipped yet), backlog in transit (products that are on their way to the client), and performance measures like OTIF (on time in full, a delivery indicator), ageing orders (orders that have serious delays) and spare parts (for products that are already sold but have a piece that is broken). These performance measures have targets to guarantee the correct control of production. The plans require several inputs, from clients’ orders to forecasts or stock, as well as some other considerations that are also critical, namely the materials availability, the production capacity, how many pieces from a specific product are produced in each shift, among others. What is planned is transmitted to the production floor through Production Orders (POs) that are released by the planners using SAP. The POs represent the “green light” to start producing. If necessary the planners use SAP to make the required adjustments to the plans. Figure 1 –Production Planning Business Process Model. Figure 2 –Assembly Plan Business Process Model. Figure 1 shows the general process required for updating the plans, which happens every week, and Figure 2 shows, in more detail, the process used to define the assembly plan. Once the plans are ready, one of the assembly planners places the information from the assembly plans in a file called Weekly Production Plan (WPP). After that, the pre-process planner 2019 14th Iberian Conference on Information Systems and Technologies (CISTI) 19 – 22 June 2019, Coimbra, Portugal ISBN: 978-989-98434-9-3 gathers the information from the WPP file, and adds the information from the PVDand Pre-Process plans to a file called Balance Sheet. This file compares what is planned with what is being produced, identifies what are the problems and how to solve them. Finally, each planner shares their plan in SharePoint, a system present in the intranet of the company. After understanding the procedure of the production planning, several problems were identified and, in order to better understand the root causes of the problems, an Ishikawa Diagram was made (see Figure 3). This diagram shows the “systematic relationship between a result or an effect and its possible causes. It is an effective tool to systematically generate ideas about causes for problems and to present these in a structured form” [31]. After observing and understanding the processes that the planners must follow to obtain the production plans, and with the help of the diagram, several possible causes of the problems were identified. The main causes of the poor decision-making and, consequently, of the ineffective performance of the production planning were identified. Figure 3 – Ishikawa Diagram It can be observed in Figure 4, the main causes that were extracted from the Ishikawa Diagram. Among them, the high quantity of support files was considered critical because it not only creates a dependency of splitting the information but also causes dispersion and redundancy of data. Figure 4 - Hidden problems of production planning In addition, many of the information flows are happening at the same time, making the processes confuse and causing a lack of data quality. Moreover, there is an excess of manual work like, for example, organization and manipulation of data provided in Excel files and transferring data between systems that are not connected. Those situations should not happen, since it increases the time wasted and the probability of occurring errors. This leads to the need for carefully selecting and filtering the data and increases the complexity required in order to have the necessary information in a speedy way. Finally, there is also an unappealing visualization of files and indicators, which also contributes to increase the effort required to obtain the necessary information, and provides a confusing and disorganized environment. With regard to the improvements that have already been implemented, the proposed solution was developed using a business intelligence tool: Microsoft Power BI. This system imports several data by connecting to different data sources, using queries. It is also possible to create customized dashboards that show various types of information, based on a user-friendly interaction. The system improved data visualization and centralization and, moreover, the access to data is instantaneous, since the dashboard is easy and fast to update. It also gives the user the possibility to select only the required information, while having access to it in nearly real time. Depending on what the user wants to view, it is possible to click in the displayed graphics that will expand and drill- down, for example, to the wanted year, month, day or to a specific value. Additionally, almost anyone can have access to the dashboards, if an authorization and a link are shared, making it possible to spread information in an broader way. A prototype was developed to show the potentiality of the features of this business intelligence tool. The KPIs used in the production planning, namely the OTIF, backlog and safety stock, were studied. Firstly, an history of those indicators, since 2013 to the present, was built in an Excel file. That file was 2019 14th Iberian Conference on Information Systems and Technologies (CISTI) 19 – 22 June 2019, Coimbra, Portugal ISBN: 978-989-98434-9-3 connected to Power BI and the several different graphics were select for each of the KPIs. This is an interactive dashboard: despite having data from 2013 to the present, the user can drill- down and select only data from a specific year (see Figure 5). This information system was evaluated using 3 metrics: Coverage, Response Time and Effort. This prototype covers all the KPIs used before, not adding any new ones, however. It shows a considerable gain of time regarding the provision of the wanted indicators and, as it is easy to use, it reduces the planners’ effort to access information. The results point out an improvement on the quality of the information flows throughout the production planning process. However, to better understand, quantify and enhance those improvements, it is important to combine Lean’s 8 types of waste with its impact on the information flows. To do so, Table I and II compare and make an analysis of the initial and the future situation, as well as the results and the improvement of quality resulting from the implemented information system. It can be said that the general improvement of the information flows directly contributed to a better performance of the production planning department. The fact that the data is more transparent also boosts the information flows performance and reveals efficiency not only in the production planning processes, but also in the production itself. TABLE I. IMPACTS ON INFORMATION FLOWS Type of Waste Impact on Information Flows Defects The excess of data sources sometimes makes the information created not reliable Overproduction The excess of non-value added data creates an excess of non- value added information flows Waiting Planners have to wait for the right information because resources are not easily available Non-utilized Talent Planners do not innovate or create new ways of efficiently sharing information Transportation Excess of steps to achieve the right information and excess of movement of the non-value added one Inventory Excess of files that provide the same data, causing redundancy on the information created Motion Decentralization of data that creates dispersion as it is not well organized Extra work As the files are confuse, there is a need for creating new information to obtain another As it can be seen when comparing the two tables, by applying Lean to the information flows it is possible to improve data quality and data productivity, since it is more structured an organized. TABLE II. EXPECTED IMPROVEMENTS ON INFORMATION FLOWS Type of Waste Impact on Information Flows Defects There is a common data source, improving data quality, productivity and reducing errors Overproduction The easy access to Power BI and its information leads to less but more efficient information flows Waiting Better visualization of data leads to faster and better decision- making Non-utilized Talent Planners can think about different ways of displaying the same information in the same platform Transportation The data is centered in the same IS, reducing the steps to achieve the right information Inventory The standardization of the dashboard reduces the number of files with redundant data Motion The data is structured and organized in the same place, reducing the unecessary movements Extra work Interactive and user-friendly dashboard that substantially reduces the effort of the planners There is a rational management of the files that are associated with the production planning, as well as a decrease in the human resources that are needed to do the data collection, treatment and analysis, making use of I4.0 principles in the way data is acquired treated and displayed. This dashboard is essential to reduce the number of files of support the planners used, reducing the effort they put in their tasks. As it is the user that defines what he/she wants to analyze, there is a reduction in the excess of information that is created. It is also an interactive and user-friendly platform with some important visual improvements in the format of the visualization of the graphics. The 8 types of waste were addressed and somefurther improvements on the information flows are expected. IV. CONCLUSIONS AND FUTURE WORK Business Process Modelling was crucial because it represents comprehensive solutions whenever talking about processes that need to be improved. It helps to understand the processes but also people, flows, tasks and files involved. It also makes it possible to identify the problems, especially with respect to the information flows, and points that require improvements, as well as the requirements needed to get from the problem to the desired solution. Hence, it is possible to detail and identify the necessary data for each step of the processes. BPMN 2.0 facilitated this exploratory work as it establishes the connection between processes and systems, and, in this case, it helps to understand where a process can be automatized thus serving as a basis for a future work related with the automation of processes. The use of Power BI helped to reduce the manual tasks performed by the planners, particularly in the updating of the information that is visualized and used. However, as Industry 4.0 is still a growing concept and has a variety of features, there is still a lot to be explored in the information flows perspective. An information system that centralizes the data was established. To develop a new system, the requirements defined need to be tested to understand whether they are feasible or not. One of the main challenges was precisely to integrate all the sources of data so that the information would be available on the same platform. Therefore, this solution represents a connection between several areas of knowledge used to solve the identified problems: Lean Thinking, to understand how to improve the information flows’ quality; Industry 4.0, to Figure 5 - Power BI prototype 2019 14th Iberian Conference on Information Systems and Technologies (CISTI) 19 – 22 June 2019, Coimbra, Portugal ISBN: 978-989-98434-9-3 understand the powerful features of Power BI; and Information Systems, to understand how to support the production planning process. To test if the system contributed to gain processes’ efficiency, 3 main performance measures were proposed: Coverage (if the KPIs are the same or if there are new ones); Response Timing (if the tool is considerably reducing the time the planners spend when accessing the wanted data); and Effort (if the planners still have to struggle to get the right information at the right time). Power BI is a software that provides visibility to the information flows, applying Lean concepts to Information Management, making it easier to understand if everyone is on the same page. A suggestion for future work is a more detailed feasibility analysis of this system, both in technical and economic aspects, to make sure this is a right solution for this manufacturing company. The definition of new indicators is also a suggestion, depending on the needs but focusing on the customer service. The quality of information flows gets naturally deteriorated over time and, bearing that in mind, for future work it is suggested that this system is monitored and maintained, also considering that the external environment of the company is changing, as well as customer requirements and the planners’ focus. To conclude, it is also important to point out that improving a process in a company is not easy, no matter if it is in the Production Planning or in another department. It requires change to the way people perform certain tasks, and changes sometimes can be hard to implement. It is recommended that the solution developed should not be too complex or it will become something that the planners will not use. If this new system is seen and showed as a way of improving and having better results, changes like the one proposed in this exploratory study can be successful. ACKNOWLEDGMENT This work was supported by Fundação para a Ciência e a Tecnologia (FCT), through CIDMA - Center for Research and Development in Mathematics and Applications, within project UID/MAT/04106/2019 and through IEETA in the context of the project UID/CEC/00127/2013. REFERENCES [1] R. Paim, H. Mansur Caulliraux, and R. Cardoso, “Process management tasks: a conceptual and practical view,” Bus. Process Manag. J., vol. 14, no. 5, pp. 694–723, Sep. 2008. [2] L. F. Gelders and L. N. Van Wassenhove, “Production planning: a review,” Eur. J. Oper. Res., vol. 7, no. 2, pp. 101–110, Jun. 1981. [3] P. G. Saleeshya, P. Raghuram, and N. Vamsi, “Lean manufacturing practices in textile industries - a case study,” Int. J. Collab. Enterp., vol. 3, no. 1, p. 18, 2012. [4] M. Bevilacqua, F. E. Ciarapica, and C. Paciarotti, “Implementing lean information management: the case study of an automotive company,” Prod. Plan. Control, vol. 26, no. 10, pp. 753–768, Jul. 2015. [5] B. J. Hicks, “Lean information management: Understanding and eliminating waste,” Int. J. Inf. Manage., vol. 27, no. 4, pp. 233–249, Aug. 2007. [6] A. Castle and R. Harvey, “Lean information management: the use of observational data in health care,” Int. J. Product. Perform. Manag., vol. 58, no. 3, pp. 280–299, Mar. 2009. [7] R. Smith and A. Ibbitson, The lean information management toolkit. Ark Group, 2011. [8] J. P. Womack and D. T. Jones, “Lean Thinking—Banish Waste and Create Wealth in your Corporation,” J. Oper. Res. Soc., vol. 48, no. 11, pp. 1148–1148, Nov. 1997. [9] M. Chinosi and A. Trombetta, “BPMN: An introduction to the standard,” Comput. Stand. Interfaces, vol. 34, no. 1, pp. 124–134, Jan. 2012. [10] A. Awadid, “Supporting the consistency in multi-perspective Business Process Modeling: A mapping approach,” in 2017 11th International Conference on Research Challenges in Information Science (RCIS), 2017, pp. 414–419. [11] R. S. Aguilar-Savén, “Business process modelling: Review and framework,” Int. J. Prod. Econ., vol. 90, no. 2, pp. 129–149, Jul. 2004. [12] S. Ouali, M. Mhiri, and L. Bouzguenda, “A Multidimensional Knowledge Model for Business Process Modeling,” Procedia Comput. Sci., vol. 96, pp. 654–663, Jan. 2016. [13] H. Meier, H. Lagemann, F. Morlock, and C. Rathmann, “Key Performance Indicators for Assessing the Planning and Delivery of Industrial Services,” Procedia CIRP, vol. 11, pp. 99–104, Jan. 2013. [14] G. Ante, F. Facchini, G. Mossa, and S. Digiesi, “Developing a key performance indicators tree for lean and smart production systems,” IFAC-PapersOnLine, vol. 51, no. 11, pp. 13–18, Jan. 2018. [15] L. Vilcahuamán and R. Rivas, Asset & Risk Management Related to Healthcare Technology. Academic Press, 2017. [16] F. Rahimi, C. Møller, and L. Hvam, “Business process management and IT management: The missing integration,” Int. J. Inf. Manage., vol. 36, no. 1, pp. 142–154, Feb. 2016. [17] L. Özdamar, M. A. Bozyel, and S. I. Birbil, “A hierarchical decision support system for production planning (with case study),” Eur. J. Oper. Res., vol. 104, no. 3, pp. 403–422, Feb. 1998. [18] J. Bicevskis and Z. Bicevska, “Business Process Models and Information System Usability,” Procedia Comput. Sci., vol. 77, pp. 72–79, Jan. 2015. [19] M. Al-Emran, V. Mezhuyev, A. Kamaludin, and K. Shaalan, “The impact of knowledge management processes on information systems: A systematic review,” Int. J. Inf. Manage., vol. 43, pp. 173–187, Dec. 2018. [20] G. Kebede, “Knowledge management: An information science perspective,” Int. J. Inf. Manage., vol. 30, no. 5, pp. 416–424, Oct. 2010. [21] G. L. Tortorella and D. Fettermann, “Implementation of Industry 4.0 and lean production in Brazilian manufacturing companies,” Int. J. Prod. Res., vol. 56, no. 8, pp. 2975–2987, Apr. 2018. [22] C. Leyh, S. Martin, and T. Schäffer, “Industry 4.0 and Lean Production – A Matching Relationship? An analysis of selected Industry 4.0 models,” 2017, pp. 989–993. [23] R. Y. Zhong, X. Xu, E. Klotz, and S. T. Newman, “Intelligent Manufacturingin the Context of Industry 4.0: A Review,” Engineering, vol. 3, no. 5, pp. 616–630, Oct. 2017. [24] A. Merendino et al., “Big data, big decisions: The impact of big data on board level decision-making,” J. Bus. Res., vol. 93, pp. 67–78, Dec. 2018. [25] L. Teixeira, C. Ferreira, and B. S. Santos, “An Information Management Framework to Industry 4.0: A Lean Thinking Approach,” Hum. Syst. Eng. Des., vol. 876, no. Lim, pp. 1063–1069, 2019. [26] P. Chaudhary, M. Hyde, and J. A. Rodger, “Exploring the Benefits of an Agile Information System,” Intell. Inf. Manag., vol. 09, no. 05, pp. 133– 155, 2017. [27] G. Miragliotta, A. Sianesi, E. Convertini, and R. Distante, “Data driven management in Industry 4.0: a method to measure Data Productivity,” IFAC-PapersOnLine, vol. 51, no. 11, pp. 19–24, Jan. 2018. [28] D. L. Brandl and D. Brandl, “KPI Exchanges in Smart Manufacturing using KPI-ML,” IFAC-PapersOnLine, vol. 51, no. 11, pp. 31–35, Jan. 2018. [29] M. Trstenjak and P. Cosic, “Process Planning in Industry 4.0 Environment,” Procedia Manuf., vol. 11, pp. 1744–1750, Jan. 2017. [30] W.J. Stevenson, Operations Management, 12th ed, McGraw-Hill Education, New York, 2014. [31] V. M. Magar and V. B. Shinde, “Application of 7 Quality Control (7 QC) Tools for Continuous Improvement of Manufacturing Processes,” Int. J. Eng. Res. Gen. Sci., vol. 2, no. 4, pp. 364–371, 2014.