Which of the following does NOT represent a possible output of risk management processes?
a. Creation of contract terms and conditions.
b. Change...
Which of the following does NOT represent a possible output of risk management processes?
a. Creation of contract terms and conditions. b. Change in the project management plan. c. Change in the project scope statement. d. Change in the communication management plan. e. Change in the project charter.