78. A project manager has just received communication from an operational functional manager to complete an additional scope item for a project tha...

78. A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.
How should the project manager deal with this request?


A. Submit a change request and allocate the budget and resources needed for execution.
B. Confirm that the budget and resources are available to execute the work request.
C. Check the alternative resources available in the organization for the request.
D. Evaluate the nature of the request and plan communication accordingly.

💡 1 Resposta

User badge image

Ed Verified user icon

Nesse caso, o gerente de projeto deve avaliar a natureza do pedido e planejar a comunicação de acordo. Portanto, a resposta correta é a opção D.

0
Dislike0

Faça como milhares de estudantes: teste grátis o Passei Direto

Esse e outros conteúdos desbloqueados

16 milhões de materiais de várias disciplinas

Impressão de materiais

Agora você pode testar o

Passei Direto grátis

Você também pode ser Premium ajudando estudantes

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais