What is the main difference between PERT and CPM? a) PERT uses probabilistic treatment for defining deadlines, while CPM relies on reasonably kno...

What is the main difference between PERT and CPM?


a) PERT uses probabilistic treatment for defining deadlines, while CPM relies on reasonably known task durations.
b) PERT was developed for construction projects with unknown task durations, while CPM was developed for minimizing production downtime.
c) PERT and CPM are essentially the same method, with PERT/CPM being the most commonly used in civil construction planning.

Essa pergunta também está no material:

49 pág.

Tópicos de Atuação Profissional Universidade PaulistaUniversidade Paulista

💡 1 Resposta

User badge image

Ed Verified user icon

A principal diferença entre o PERT (Program Evaluation and Review Technique) e o CPM (Critical Path Method) é que o PERT utiliza um tratamento probabilístico para definir prazos, enquanto o CPM se baseia em durações de tarefas razoavelmente conhecidas. Portanto, a alternativa correta é a letra A.

0
Dislike0

✏️ Responder

SetasNegritoItálicoSublinhadoTachadoCitaçãoCódigoLista numeradaLista com marcadoresSubscritoSobrescritoDiminuir recuoAumentar recuoCor da fonteCor de fundoAlinhamentoLimparInserir linkImagemFórmula

Para escrever sua resposta aqui, entre ou crie uma conta

User badge image

Outros materiais